Proposal Request. 7.3.1.1 The A/E shall prepare and issue a Proposal Request to the CM to obtain the CM’s Proposal for the adjustment of the Contract Sum or Contract Times, or both, associated with a contemplated Modification. .1 In any Proposal for an adjustment of the Contract Sum, the CM shall specifically identify the items set forth in Section 7.7. .2 In any Proposal for an adjustment of the Contract Times, the CM shall specifically identify the items set forth in Section 7.8. .3 The CM’s cost of preparing and providing Proposals is included in the Contract Sum. 7.3.1.2 The CM shall respond with a Proposal to the A/E and Contracting Authority within 14 days after receiving the Proposal Request. The allowable time for the CM’s response may be extended by written agreement of the CM and A/E. 7.3.1.3 The CM shall hold the Proposal valid and open for acceptance for at least 45 days. The acceptance period may be adjusted by mutual consent of the CM and Contracting Authority. The time limits described under this Section 7.3.1.3 apply only to Proposals submitted in response to a Proposal Request. 7.3.1.4 A Proposal may be accepted by the Contracting Authority only through a Change Order. A Proposal Request does not authorize the CM to proceed with a change in the Work. 7.3.1.5 If the CM does not timely submit a Proposal within the time required in Section 7.3.1.2, the CM waives its right to an adjustment to the Contract Sum or Contract Times, or both, associated with the contemplated change in the Work. 7.3.1.6 If the Project is administered using the State’s web-based project management software, the CM shall respond to a Proposal Request issued by the A/E with its Proposal using the “Change Order” or “Contract Modifications” business process.
Appears in 2 contracts
Sources: Construction Manager at Risk Agreement, Professional Services
Proposal Request. 7.3.1.1 The A/E Contracting Authority shall prepare and issue a Proposal Request to the CM DB to obtain the CMDB’s Proposal for the adjustment of the Contract Sum or Contract Times, or both, associated with a contemplated Modification.
.1 In any Proposal for an adjustment of the Contract Sum, the CM DB shall specifically identify the items set forth in Section 7.7.
.2 In any Proposal for an adjustment of the Contract Times, the CM DB shall specifically identify the items set forth in Section 7.8.
.3 The CMDB’s cost of preparing and providing Proposals is included in the Contract Sum.
7.3.1.2 The CM DB shall respond with a Proposal to the A/E and Contracting Authority within 14 days after receiving the Proposal Request. The allowable time for the CMDB’s response may be extended by written agreement of the CM DB and A/E.Contracting Authority.
7.3.1.3 The CM DB shall hold the Proposal valid and open for acceptance for at least 45 days. The acceptance period may be adjusted by mutual consent of the CM DB and Contracting Authority. The time limits described under this Section 7.3.1.3 apply only to Proposals submitted in response to a Proposal Request.
7.3.1.4 A Proposal may be accepted by the Contracting Authority only through a Change Order. A Proposal Request does not authorize the CM DB to proceed with a change in the Work.
7.3.1.5 If the CM DB does not timely submit a Proposal within the time required in Section 7.3.1.2, the CM DB waives its right to an adjustment to the Contract Sum or Contract Times, or both, associated with the contemplated change in the Work.
7.3.1.6 If the Project is administered using the State’s web-based project management software, the CM DB shall respond to a Proposal Request issued by the A/E Contracting Authority with its Proposal using the “Change Order” or “Contract Modifications” business process.
Appears in 2 contracts
Sources: Professional Services, Professional Services
Proposal Request. 7.3.1.1 The A/E shall prepare and issue a Proposal Request to the CM to obtain the CM’s Proposal for the adjustment of the Contract Sum or the Contract Times, or both, associated with a contemplated Modification.
.1 In any Proposal for an adjustment of the Contract Sum, the CM shall specifically identify the items set forth in Section 7.7.
.2 In any Proposal for an adjustment of the Contract Times, the CM shall specifically identify the items set forth in Section 7.8.
.3 The CM’s cost of preparing and providing Proposals is included in the Contract Sum.
7.3.1.2 The CM shall respond with a Proposal to the A/E and the Contracting Authority within 14 days after receiving the Proposal Request. The allowable time for the CM’s response may be extended by written agreement of the CM and the A/E.
7.3.1.3 The CM shall hold the Proposal valid and open for acceptance for at least 45 days. The acceptance period may be adjusted by mutual consent of the CM and the Contracting Authority. The time limits described under this Section 7.3.1.3 apply only to Proposals submitted in response to a Proposal Request.
7.3.1.4 A Proposal may be accepted by the Contracting Authority only through a Change Order. A Proposal Request does not authorize the CM to proceed with a change in the Work.
7.3.1.5 If the CM does not timely submit a Proposal within the time required in Section 7.3.1.27.3.1.3, the CM waives its right to an adjustment to the Contract Sum or Contract Times, or both, associated with the contemplated change in the Work.
7.3.1.6 If the Project is administered using the OAKS CIthe State’s web-based project management software, the CM shall respond to a Proposal Request issued by the A/E with its Proposal using the “Change Order” (Agency/Higher Education) or “Contract Modifications” (School Facilities) business process.
Appears in 1 contract
Sources: Cm at Risk Contract