Project Master Schedule. 4.4.1 The Project Master Schedule approved as part of a GMP shall be updated and maintained throughout the Work by ▇▇▇▇. 4.4.2 The Project Master Schedule shall be revised by ▇▇▇▇ as required by conditions and progress of the Work, but such revisions shall not relieve ▇▇▇▇ of its obligations to complete the Work within the Contract Time, as such dates may be adjusted in accordance with the Contract Documents.
Appears in 2 contracts
Sources: Construction Manager at Risk Agreement, Construction Manager at Risk Agreement