Project Delay. If the Contractor is delayed in the completion of the Work as a result of a direction from a Governmental Authority given for the purpose of suspending the Project as a whole (“Project Delay”), including an order from a court pursuant to an application from: any Person to suspend the Project as a whole; or any Person asserting infringement of treaty and Aboriginal rights, including Aboriginal title, such delay will be deemed to be a suspension by BC Hydro under Section 17.1 of this Schedule 2 [General Conditions].
Appears in 1 contract
Sources: Civil Works Contract
Project Delay. If the Contractor is delayed in the completion performance of the Work as a result of a direction from a Governmental Authority given for the purpose of suspending the Project as a whole (“Project Delay”), including an order from a court pursuant to an application from: :
(a) any Person person to suspend the Project as a whole; or or
(b) any Person person asserting infringement of treaty and Aboriginal rights, including Aboriginal title, such delay will be deemed to be a suspension by BC Hydro under Section 17.1 of this Schedule 2 [General Conditions].
Appears in 1 contract
Sources: Main Civil Works Contract