Programming Information. 1.2.1 No later than *** (***) Days before the start of each Contract Year, Project Co shall notify the Transporter of (i) the Major Scheduled Maintenance Quantity to be exercised under the DES SPA for the upcoming Contract Year, if any, (ii) planned maintenance periods at the Corpus Christi Facility for during the upcoming Contract Year and (iii) Project Co's good faith estimate of the Gross Heating Value of LNG to be delivered during the coming Contract Year. 1.2.2 No later than *** (***) Days before the start of each Contract Year, the Transporter shall notify Project Co of the proposed schedule of cargoes for each Month of such Contract Year, which shall be consistent with the information provided by DES Buyer pursuant to Section 8.1.2 of the DES SPA. Such schedule shall provide for the delivery, on a reasonably even and ratable basis throughout the relevant Contract Year, taking into consideration planned maintenance at the Corpus Christi Facility, of a number of cargoes corresponding to the number of cargoes the Transporter intends to schedule under the DES ADP in respect of such Contract Year, adjusted for (i) any cargo(es) scheduled in the FOB ADP for the prior Contract Year and intended for delivery to DES Buyer during such Contract Year and (ii) the Transporter’s reasonable estimate of the number of cargoes that need to be included in such Contract Year’s FOB ADP for delivery under the DES ADP during the following Contract Year. The Transporter's notice shall include the following information in respect of each proposed cargo: (A) the LNG Tanker (if known); (B) the FOB SCQ, provided that the sum of the FOB SCQs in respect of all cargoes included in Transporter’s proposed schedule shall equal *** percent (***%) of the sum of the DES SCQs for all cargoes that the Transporter intends to schedule in the DES ADP for such Contract Year, adjusted for (i) any cargo(es) scheduled in the FOB ADP for the prior Contract Year and intended for delivery to DES Buyer during such Contract Year and (ii) the Transporter’s reasonable estimate of the number of cargoes that need to be included in such Contract Year’s FOB ADP for delivery under the DES ADP during the following Contract Year; (C) the Production Facility; (D) the proposed FOB Delivery Window; (E) the anticipated Receiving Terminal; (F) whether the Transporter requests to designate such cargo as a “Diverted Cargo”, subject to satisfaction of the Diversion Conditions; and (G) any other information that may affect annual scheduling. The Transporter shall also inform Project Co of any anticipated periods for maintenance to be conducted with respect to the LNG Tankers identified in Paragraph 1.2.2(A) above. The Transporter may update the proposed FOB Delivery Windows provided to Project Co pursuant to Paragraph 1.2.2(D) above subject to notifying Project Co of such updated information no later than *** (***) Days before the start of the upcoming Contract Year. If requested by the Transporter, the Parties shall consult regarding any such updates to the proposed FOB Delivery Windows. 1.2.3 No later than *** (***) Days before the start of each Contract Year, Project Co shall notify the Transporter of the proposed schedule of cargoes for each Month of such Contract Year, using reasonable efforts to adopt FOB Delivery Windows that are as close as reasonably practicable to the FOB Delivery Windows proposed by the Transporter.
Appears in 1 contract
Sources: Shipping Services Agreement (Cheniere Corpus Christi Holdings, LLC)
Programming Information. 1.2.1 No later than *** (***) Days before the start of each Contract Year, Project Co shall notify the Transporter of (i) the Major Scheduled Maintenance Quantity to be exercised under the DES SPA for the upcoming Contract Year, if any, (ii) planned maintenance periods at the Corpus Christi Facility for during the upcoming Contract Year and (iii) Project Co's good faith estimate of the Gross Heating Value of LNG to be delivered during the coming Contract Year.
1.2.2 No later than *** (***) Days before the start of each Contract Year, the Transporter shall notify Project Co of the proposed schedule of cargoes for each Month of such Contract Year, which shall be consistent with the information provided by DES Buyer pursuant to Section 8.1.2 of the DES SPA. Such schedule shall provide for the delivery, on a reasonably even and ratable basis throughout the relevant Contract Year, taking into consideration planned maintenance at the Corpus Christi Facility, of a number of cargoes corresponding to the number of cargoes the Transporter intends to schedule under the DES ADP in respect of such Contract Year, adjusted for (i) any cargo(es) scheduled in the FOB ADP for the prior Contract Year and intended for delivery to DES Buyer during such Contract Year and (ii) the Transporter’s reasonable estimate of the number of cargoes that need to be included in such Contract Year’s FOB ADP for delivery under the DES ADP during the following Contract Year. The Transporter's notice shall include the following information in respect of each proposed cargo:
(A) the LNG Tanker (if known);
(B) the FOB SCQ, provided that the sum of the FOB SCQs in respect of all cargoes included in Transporter’s proposed schedule shall equal *** percent (***%) of the sum of the DES SCQs for all cargoes that the Transporter intends to schedule in the DES ADP for such Contract Year, adjusted for (i) any cargo(es) scheduled in the FOB ADP for the prior Contract Year and intended for delivery to DES Buyer during such Contract Year and (ii) the Transporter’s reasonable estimate of the number of cargoes that need to be included in such Contract Year’s FOB ADP for delivery under the DES ADP during the following Contract Year;
(C) the Production Facility;
(D) the proposed FOB Delivery Window;
(E) the anticipated Receiving Terminal;
(F) whether the Transporter requests to designate such cargo as a “Diverted Cargo”, subject to satisfaction of the Diversion Conditions; and
(G) any other information that may affect annual scheduling. The Transporter shall also inform Project Co of any anticipated periods for maintenance to be conducted with respect to the LNG Tankers identified in Paragraph 1.2.2(A) above. The Transporter may update the proposed FOB Delivery Windows provided to Project Co pursuant to Paragraph 1.2.2(D) above subject to notifying Project Co of such updated information no later than *** (***) Days before the start of the upcoming Contract Year. If requested by the Transporter, the Parties shall consult regarding any such updates to the proposed FOB Delivery Windows.
1.2.3 No later than *** (***) Days before the start of each Contract Year, Project Co shall notify the Transporter of the proposed schedule of cargoes for each Month of such Contract Year, using reasonable efforts to adopt FOB Delivery Windows that are as close as reasonably practicable to the FOB Delivery Windows proposed by the Transporter.
Appears in 1 contract
Sources: Shipping Services Agreement (Cheniere Corpus Christi Holdings, LLC)
Programming Information. 1.2.1 No later than *** (***) Days before the start of each Contract Year, Project Co shall notify the Transporter of (i) the Major Scheduled Maintenance Quantity to be exercised under the DES SPA for the upcoming Contract Year, if any, (ii) planned maintenance periods at the Corpus Christi Facility for during the upcoming Contract Year and (iii) Project Co's good faith estimate of the Gross Heating Value of LNG to be delivered during the coming Contract Year.
1.2.2 No later than *** (***) Days before the start of each Contract Year, the Transporter shall notify Project Co of the proposed schedule of cargoes for each Month of such Contract Year, which shall be consistent with the information provided by DES Buyer pursuant to Section 8.1.2 of the DES SPA. Such schedule shall provide for the delivery, on a reasonably even and ratable basis throughout the relevant Contract Year, taking into consideration planned maintenance at the Corpus Christi Facility, of a number of cargoes corresponding to the number of cargoes the Transporter intends to schedule under the DES ADP in respect of such Contract Year, adjusted for (i) any cargo(es) scheduled in the FOB ADP for the prior Contract Year and intended for delivery to DES Buyer during such Contract Year and (ii) the Transporter’s reasonable estimate of the number of cargoes that need to be included in such Contract Year’s FOB ADP for delivery under the DES ADP during the following Contract Year. The Transporter's notice shall include the following information in respect of each proposed cargo:
(A) the LNG Tanker (if known);
(B) the FOB SCQ, provided that the sum of the FOB SCQs in respect of all cargoes included in Transporter’s proposed schedule shall equal (i) in respect of any Contract Year beginning prior to the Conversion Date, (1) *** percent (***%) of the sum of the DES SCQs for the “T1Q Cargoes” (as defined in the DES SPA) that the Transporter intends to schedule in the DES ADP for such Contract Year, plus (2) *** percent (***%) of the DES SCQs for the “T2Q Cargoes” (as defined in the DES SPA) that the Transporter intends to schedule in the DES ADP for such Contract Year; and (ii) in respect of any Contract Year beginning on or after the Conversion Date, *** percent (***%) of the sum of the DES SCQs for all cargoes that the Transporter intends to schedule in the DES ADP for such Contract Year, adjusted for (i) any cargo(es) scheduled in the FOB ADP for the prior Contract Year and intended for delivery to DES Buyer during such Contract Year and (ii) the Transporter’s reasonable estimate of the 99 number of cargoes that need to be included in such Contract Year’s FOB ADP for delivery under the DES ADP during the following Contract Year;
(C) the Production Facility;
(D) the proposed FOB Delivery Window;
(E) the anticipated Receiving Terminal;
(F) whether the Transporter requests to designate such cargo as a “Diverted Cargo”, subject to satisfaction of the Diversion Conditions; and
(G) any other information that may affect annual scheduling. The Transporter shall also inform Project Co of any anticipated periods for maintenance to be conducted with respect to the LNG Tankers identified in Paragraph 1.2.2(A) above. The Transporter may update the proposed FOB Delivery Windows provided to Project Co pursuant to Paragraph 1.2.2(D) above subject to notifying Project Co of such updated information no later than *** (***) Days before the start of the upcoming Contract Year. If requested by the Transporter, the Parties shall consult regarding any such updates to the proposed FOB Delivery Windows.
1.2.3 No later than *** (***) Days before the start of each Contract Year, Project Co shall notify the Transporter of the proposed schedule of cargoes for each Month of such Contract Year, using reasonable efforts to adopt FOB Delivery Windows that are as close as reasonably practicable to the FOB Delivery Windows proposed by the Transporter.
Appears in 1 contract
Sources: Shipping Services Agreement (Cheniere Corpus Christi Holdings, LLC)
Programming Information. 1.2.1 No later than *** (***) Days before the start of each Contract Year, Project Co shall notify the Transporter of (i) the Major Scheduled Maintenance Quantity to be exercised under the DES SPA for the upcoming Contract Year, if any, (ii) planned maintenance periods at the Corpus Christi Facility for during the upcoming Contract Year and (iii) Project Co's ’s good faith estimate of the Gross Heating Value of LNG to be delivered during the coming Contract Year.
1.2.2 No later than *** (***) Days before the start of each Contract Year, the Transporter shall notify Project Co of the proposed schedule of cargoes for each Month of such Contract Year, which shall be consistent with the information provided by DES Buyer pursuant to Section 8.1.2 of the DES SPA. Such schedule shall provide for the delivery, on a reasonably even and ratable basis throughout the relevant Contract Year, taking into consideration planned maintenance at the Corpus Christi Facility, of a number of cargoes corresponding to the number of cargoes the Transporter intends to schedule under the DES ADP in respect of such Contract Year, adjusted for (i) any cargo(es) scheduled in the FOB ADP for the prior Contract Year and intended for delivery to DES Buyer during such Contract Year and (ii) the Transporter’s reasonable estimate of the number of cargoes that need to be included in such Contract Year’s FOB ADP for delivery under the DES ADP during the following Contract Year. The Transporter's ’s notice shall include the following information in respect of each proposed cargo:
(A) the LNG Tanker (if known);
(B) the FOB SCQ, provided that the sum of the FOB SCQs in respect of all cargoes included in Transporter’s proposed schedule shall equal *** percent (***%) of the sum of the DES SCQs for all cargoes that the Transporter intends to schedule in the DES ADP for such Contract Year, adjusted for (i) any cargo(es) scheduled in the FOB ADP for the prior Contract Year and intended for delivery to DES Buyer during such Contract Year and (ii) the Transporter’s reasonable estimate of the number of cargoes that need to be included in such Contract Year’s FOB ADP for delivery under the DES ADP during the following Contract Year;
(C) the Production Facility;
(D) the proposed FOB Delivery Window;
(E) the anticipated Receiving Terminal;
(F) whether the Transporter requests to designate such cargo as a “Diverted Cargo”, subject to satisfaction of the Diversion Conditions; and
(G) any other information that may affect annual scheduling. The Transporter shall also inform Project Co of any anticipated periods for maintenance to be conducted with respect to the LNG Tankers identified in Paragraph 1.2.2(A) above. The Transporter may update the proposed FOB Delivery Windows provided to Project Co pursuant to Paragraph 1.2.2(D) above subject to notifying Project Co of such updated information no later than *** (***) Days before the start of the upcoming Contract Year. If requested by the Transporter, the Parties shall consult regarding any such updates to the proposed FOB Delivery Windows.
1.2.3 No later than *** (***) Days before the start of each Contract Year, Project Co shall notify the Transporter of the proposed schedule of cargoes for each Month of such Contract Year, using reasonable efforts to adopt FOB Delivery Windows that are as close as reasonably practicable to the FOB Delivery Windows proposed by the Transporter.
Appears in 1 contract
Sources: Shipping Services Agreement (Cheniere Corpus Christi Holdings, LLC)
Programming Information. 1.2.1 No later than *** (***) Days before the start of each Contract Year, Project Co shall notify the Transporter of (i) the Major Scheduled Maintenance Quantity to be exercised under the DES SPA for the upcoming Contract Year, if any, (ii) planned maintenance periods at the Corpus Christi Facility for during the upcoming Contract Year and (iii) Project Co's good faith estimate of the Gross Heating Value of LNG to be delivered during the coming Contract Year.
1.2.2 No later than *** (***) Days before the start of each Contract Year, the Transporter shall notify Project Co of the proposed schedule of cargoes for each Month of such Contract Year, which shall be consistent with the information provided by DES Buyer pursuant to Section 8.1.2 of the DES SPA. Such schedule shall provide for the delivery, on a reasonably even and ratable basis throughout the relevant Contract Year, taking into consideration planned maintenance at the Corpus Christi Facility, of a number of cargoes corresponding to the number of cargoes the Transporter intends to schedule under the DES ADP in respect of such Contract Year, adjusted for (i) any cargo(es) scheduled in the FOB ADP for the prior Contract Year and intended for delivery to DES Buyer during such Contract Year and (ii) the Transporter’s reasonable estimate of the number of cargoes that need to be included in such Contract Year’s FOB ADP for delivery under the DES ADP during the following Contract Year. The Transporter's notice shall include the following information in respect of each proposed cargo:
(A) the LNG Tanker (if known);
(B) the FOB SCQ, provided that the sum of the FOB SCQs in respect of all cargoes included in Transporter’s proposed schedule shall equal *** percent (***%) of the sum of the DES SCQs for all cargoes that the Transporter intends to schedule in the DES ADP for such Contract Year, adjusted for (i) any cargo(es) scheduled in the FOB ADP for the prior Contract Year and intended for delivery to DES Buyer during such Contract Year and (ii) the Transporter’s reasonable estimate of the number of cargoes that need to be included in such Contract Year’s FOB ADP for delivery under the DES ADP during the following Contract Year;
(C) the Production Facility;
(D) the proposed FOB Delivery Window;
(E) the anticipated Receiving Terminal;
(F) whether the Transporter requests to designate such cargo as a “Diverted Cargo”, subject to satisfaction of the Diversion Conditions; and
(G) any other information that may affect annual scheduling. The Transporter shall also inform Project Co of any anticipated periods for maintenance to be conducted with respect to the LNG Tankers identified in Paragraph 1.2.2(A) above. The Transporter may update the proposed FOB Delivery Windows provided to Project Co pursuant to Paragraph 1.2.2(D) above subject to notifying Project Co of such updated information no later than *** (***) Days before the start of the upcoming Contract Year. If requested by the Transporter, the Parties shall consult regarding any such updates to the proposed FOB Delivery Windows.
1.2.3 No later than *** (***) Days before the start of each Contract Year, Project Co shall notify the Transporter of the proposed schedule of cargoes for each Month of such Contract Year, using reasonable efforts to adopt FOB Delivery Windows that are as close as reasonably practicable to the FOB Delivery Windows proposed by the Transporter.
Appears in 1 contract
Sources: Shipping Services Agreement (Cheniere Corpus Christi Holdings, LLC)