Common use of Processing bv Sunrun Clause in Contracts

Processing bv Sunrun. Once the fully-completed documents referenced in Section 4.2(a) are received by Sunrun, Sunrun shall use reasonable efforts to process the new deal and execute and deliver to Contractor the Addendum within three (3) Business Days. Should Sunrun fail to process the new deal and execute and deliver to Contractor the Addendum within three (3) Business Days of receiving the foregoing documents, Contractor’s sole and exclusive remedy shall be a day for day extension of the Guaranteed Substantial Completion Date, equivalent to the number of Business Days of Sunrun’s delay in executing and delivering the Addendum.

Appears in 2 contracts

Sources: Master Solar Facility Turnkey Contract (SolarMax Technology, Inc.), Master Solar Facility Turnkey Contract (SolarMax Technology, Inc.)