Common use of Parties to Perform Obligations Clause in Contracts

Parties to Perform Obligations. Notwithstanding the existence of any Dispute and difference referred to the Arbitration Tribunal as provided in Article 13.3 and save as the Arbitration Tribunal may otherwise direct by a final or interim order, the Parties hereto shall continue to perform their respective obligations (which are not in dispute) under this Contract.

Appears in 4 contracts

Samples: Assam Power, Assam Power, www.nsgm.gov.in

AutoNDA by SimpleDocs

Parties to Perform Obligations. Notwithstanding the existence of any Dispute and difference referred to the Arbitration Tribunal Appropriate Commission or the arbitral tribunal as provided in Article 13.3 clause 21.3 and save as the Arbitration Tribunal Appropriate Commission or the arbitral tribunal may otherwise direct by a final or interim order, the Parties hereto shall continue to perform their respective obligations (which are not in dispute) under this ContractAgreement.

Appears in 3 contracts

Samples: Agreement (BioCrude Technologies USA, Inc.), Agreement (BioCrude Technologies USA, Inc.), Agreement (BioCrude Technologies USA, Inc.)

Parties to Perform Obligations. 14.4.1 Notwithstanding the existence of any Dispute and difference referred to the Appropriate Commission or the Arbitration Tribunal as provided in Article 13.3 14.3 and save as the Appropriate Commission or the Arbitration Tribunal may otherwise direct by a final or interim order, the Parties hereto shall continue to perform their respective obligations (which are not in dispute) under this ContractAgreement.

Appears in 2 contracts

Samples: Power Purchase Agreement, Power Purchase Agreement

Parties to Perform Obligations. Notwithstanding the existence of any Dispute and difference referred to the Appropriate Commission or the Arbitration Tribunal as provided in Article 13.3 17.3 and save as the Appropriate Commission or the Arbitration Tribunal may otherwise direct by a final or interim order, the Parties hereto shall continue to perform their respective obligations (which are not in dispute) under this ContractAgreement.

Appears in 1 contract

Samples: Power Purchase Agreement

Parties to Perform Obligations. 16.4.1 Notwithstanding the existence of any Dispute and difference referred to the Arbitration Tribunal as provided in Article 13.3 Article16.3 and save as the Arbitration Tribunal may otherwise direct by a final or interim order, the Parties hereto shall continue to perform their respective obligations (which are not in dispute) under this ContractPPA or RFP.

Appears in 1 contract

Samples: Power Purchase Agreement

Parties to Perform Obligations. Notwithstanding the existence of any Dispute and difference referred to the Commission or the Arbitration Tribunal as provided in Article 13.3 16.3 and save as the Commission or the Arbitration Tribunal may otherwise direct by a final or interim order, the Parties hereto shall continue to perform their respective obligations (which are not in dispute) under this ContractAgreement.

Appears in 1 contract

Samples: Implementation and Service Agreement

Parties to Perform Obligations. Notwithstanding the existence of any Dispute and difference referred to the Appropriate Commission or the Arbitration Tribunal as provided in Article 13.3 12.3 and save as the Arbitration Tribunal may otherwise direct by a final or interim order, the Parties hereto shall continue to perform their respective obligations (which are not in dispute) under this ContractAgreement.

Appears in 1 contract

Samples: Power Purchase Agreement

Parties to Perform Obligations. Notwithstanding the existence of any Dispute and difference referred to the Commission or the Arbitration Tribunal as provided in Article 13.3 11.4.4 and save as the Commission or the Arbitration Tribunal may otherwise direct by a final or interim order, the Parties hereto shall continue to perform their respective obligations (which are not in dispute) under this ContractAgreement.

Appears in 1 contract

Samples: Implementation Agreement

Parties to Perform Obligations. 16.4.1 Notwithstanding the existence of any Dispute and difference referred to the Arbitration Tribunal as provided in Article 13.3 Article16.3 and save as the Arbitration Tribunal may otherwise direct by a final or interim order, the Parties hereto shall continue to perform their respective obligations (which are not in dispute) under this ContractPPA or RFS.

Appears in 1 contract

Samples: Power Purchase Agreement

Parties to Perform Obligations. Notwithstanding the existence of any Dispute and difference referred to the Appropriate Commission or the Arbitration Tribunal as provided in Article 13.3 12.3 and save as the Appropriate Commission or the Arbitration Tribunal may otherwise direct by a final or interim order, the Parties hereto shall continue to perform their respective obligations (which are not in dispute) under this ContractAgreement.

Appears in 1 contract

Samples: Power Purchase Agreement

AutoNDA by SimpleDocs

Parties to Perform Obligations. 16.4.1 Notwithstanding the existence of any Dispute and difference referred to the Arbitration Tribunal as provided in Article 13.3 16.3 and save as the Arbitration Tribunal may otherwise direct by a final or interim order, the Parties hereto shall continue to perform their respective obligations (which are not in dispute) under this ContractPPA or RFP.

Appears in 1 contract

Samples: Power Purchase Agreement

Parties to Perform Obligations. Notwithstanding the existence of any Dispute and difference referred to the Arbitration Tribunal as provided in Article 13.3 arbitration and save as the Arbitration Tribunal arbitrator may otherwise direct by a final or interim order, the Parties hereto shall continue to perform their respective obligations (which are not in dispute) under this ContractAgreement.

Appears in 1 contract

Samples: Power Delivery Agreement

Parties to Perform Obligations. Notwithstanding the existence of any Dispute and difference referred to MPERC or the Arbitration Tribunal as provided in Article 13.3 and save as MPERC or the Arbitration Tribunal may otherwise direct by a final or interim order, the Parties hereto shall continue to perform their respective obligations (which are not in dispute) under this Contractagreement.

Appears in 1 contract

Samples: mperc.in

Parties to Perform Obligations. Notwithstanding the existence of any Dispute and difference referred refereed to the Arbitration Tribunal as provided in Article 13.3 17.3 and save as the Arbitration Tribunal Arbitrator may otherwise direct by a final or interim orderaward, the Parties hereto shall continue to perform their respective obligations (which are not in dispute) under this ContractAgreement throughout the Term of the Agreement and the Customer shall make the payments against the Monthly Invoices, other than those invoices under disputes.

Appears in 1 contract

Samples: Power Purchase Agreement

Parties to Perform Obligations. 15.4.1 Notwithstanding the existence of any Dispute and difference referred to the Arbitration Tribunal as provided in Article 13.3 15.3 and save as the Arbitration Tribunal may otherwise direct by a final or interim order, the Parties hereto shall continue to perform their respective obligations (which are not in dispute) under this ContractPPA or RFP.

Appears in 1 contract

Samples: Power Purchase Agreement