Notice of Force Majeure Event Sample Clauses

Notice of Force Majeure Event. Neither Party shall be responsible for any failure to perform due to a Force Majeure Event provided that such Party gives notice to the other Party of the Force Majeure Event as soon as reasonably practicable, but not later than five (5) days after the date on which such Party knew or should reasonably have known of the commencement of the Force Majeure Event, specifying the nature and particulars thereof and the expected duration thereof; provided, however, that the failure of a Party to give notice of a Force Majeure Event shall not prevent such Party from relying on this Section except to the extent that the other Party has been prejudiced thereby.
Notice of Force Majeure Event. As soon as practicable and in any case within 3 days of the date of occurrence of a Force Majeure Event or the date of knowledge thereof, the Party which is rendered wholly or partially unable to perform any of its obligations under this Agreement because of a Force Majeure Event (the “Affected Party”) shall notify the other party of the same, setting out, inter alia, the following in reasonable detail:
Notice of Force Majeure Event. In the event either Party is delayed or rendered unable to perform due to a Force Majeure Event, the affected Party shall give notice thereof and its expected duration to the other Party promptly after the occurrence of the Force Majeure Event; and thereafter, the obligations of the affected Party will be suspended during the continuance of the Force Majeure Event. The affected Party shall take commercially reasonable steps to remedy the Force Majeure Event with all reasonable dispatch, but such obligation shall not require the settlement of strikes or labor controversies on terms unfavorable to the affected Party.
Notice of Force Majeure Event. If a Party’s ability to perform its obligations under this Agreement is affected by a Force Majeure Event (in the case of Contractor), the Party claiming relief shall as soon as practical but no later than five (5) Business Days after the date on which the affected Party has actual knowledge of a Force Majeure Event first prevents or delays performance under this Agreement, give Notice (a “Delay Notice”) describing in detail the particulars of the occurrence giving rise to the claim, including an estimate of the event’s anticipated duration and effect (if reasonably estimable) upon the performance of its obligations, and any action being taken to avoid or minimize its effect. The Party claiming relief due to a Force Majeure Event shall have a continuing obligation to deliver to the other Party regular updated reports and any additional documentation and analysis supporting its claim regarding a Force Majeure promptly after such information becomes available to such Party. If a Party fails to timely notify the other Party as provided in this Section 8.2 with respect to a Force Majeure Event, such Party’s failure to timely notify the other Party of a Force Majeure Event, shall not constitute a waiver of such Party’s right to relief due to such Force Majeure Event.
Notice of Force Majeure Event. Neither Party will be liable or deemed to be in breach of this Agreement for failure of performance under this Agreement due to a Force Majeure Event. If any Party is unable to perform its obligations under this Agreement due to a Force Majeure Event, the Party unable to perform shall promptly notify the other Party.
Notice of Force Majeure Event. In addition to satisfying the notification provisions set forth in Sections 3.5(b) and (c), as applicable, within three (3) Business Days of the commencement of a Force Majeure Event, the Party desiring to invoke a Force Majeure Event as a cause for delay in its performance of, or failure to perform, any obligation (other than the payment of money) hereunder, shall provide the other Party Notice of the occurrence giving rise to the Force Majeure Event with details to be supplied within seven (7) Business Days thereafter describing the particulars of the Force Majeure Event, including the expected duration and effect of such Force Majeure Event. Failure to provide timely Notice constitutes a waiver of a claim of a Force Majeure Event. Promptly, but in any event within ten (10) days, after a Notice is given pursuant to the preceding sentence, the Parties shall meet to discuss the basis and terms upon which the arrangements set out in this Agreement shall be continued taking into account the effects of such Force Majeure Event.
Notice of Force Majeure Event. The Affected Party shall give notice to the other Parties in writing of the occurrence of any of the Force Majeure Events (the FM Notice), as soon as it arises or as soon as reasonably practicable and in any event within 10 Days after the Affected Party knew of its occurrence, and of the adverse effect it has or is likely to have on the performance of its obligations under this Agreement, the actions being taken in accordance with Clause 19.5 and an estimate of the period of time required to overcome the Force Majeure Event and/or its nature and effects (if it is possible to estimate the same). If, following the issue of the FM Notice, the Affected Party receives or becomes aware of any further information relating to the Force Majeure Event, it shall submit such further information to the other Party as soon as reasonably practicable. Any Party claiming to have been affected by a Force Majeure Event shall not be entitled to any relief unless it has complied with all the provisions of this Clause 19.2.
Notice of Force Majeure Event. If a Party’s performance is affected by an event of Force Majeure, the affected Party shall give written notice to the other Party as soon as practicable, but in no event more than fourteen (14) days after the Force Majeure event occurs. In that event, the duties of the affected Party shall be suspended during the continuance of the Force Majeure event; provided, however, that the affected Party shall use all reasonable commercial efforts to eliminate or ameliorate the effects of the event of Force Majeure.
Notice of Force Majeure Event. If a party reasonably considers that a Force Majeure Event has occurred affecting it, it must:
Notice of Force Majeure Event. Neither Party will be liable or deemed to be in breach of this Agreement for failure of performance under this Agreement due to a Force Majeure Event. If any Party is unable to perform its obligations under this Agreement due to a Force Majeure Event, the Party unable to perform shall promptly notify the other Party. Any deficiency in the performance of Demand Resources or ILR Resources, as defined in the PJM RAA and OATT, will be subject to penalties assessed by PJM in accordance with the PJM RAA and OATT, as well as a diminished payment from the Utility, notwithstanding the Force Majeure Event.