Common use of Operational Acceptance Clause in Contracts

Operational Acceptance. Central Xxxxxx shall notify Con Edison upon completion of the construction of the Second Tie. Central Xxxxxx shall inspect and accept the Second Tie up to and including circuit breaker B9756 to confirm its compliance with the requirements of Section 3.0l (a) and its fitness for commercial operation. Con Edison shall test and accept the disconnect switch to be located in its substation and its associated indication and operational controls to confirm their compliance with the requirements of Section 3.0l (a) and their fitness for commercial operation. Central Xxxxxx and Con Edison will both test the relay protection equipment that operates circuit breaker B9756. Promptly after those matters have been confirmed to Con Edison's reasonable satisfaction, Con Edison shall provide written notification to Central Xxxxxx that the Second Tie is acceptable.

Appears in 3 contracts

Samples: Facilities Agreement, Facilities Agreement, Facilities Agreement

AutoNDA by SimpleDocs

Operational Acceptance. Central Xxxxxx shall notify Con Edison upon completion of the construction of the Second Tie. Central Xxxxxx shall inspect and accept the Second Tie up to and including circuit breaker B9756 to confirm its compliance with the requirements of Section 3.0l (a3.0l(a) and its fitness for commercial operation. Con Edison shall test and accept the disconnect switch to be located in its substation and its associated indication and operational controls to confirm their compliance with the requirements of Section 3.0l (a) and their fitness for commercial operation. Central Xxxxxx and Con Edison will both test the relay protection equipment that operates circuit breaker B9756. Promptly after those matters have been confirmed to Con Edison's reasonable satisfaction, Con Edison shall provide written notification to Central Xxxxxx that the Second Tie is acceptable.

Appears in 2 contracts

Samples: Facilities Agreement, Facilities Agreement

AutoNDA by SimpleDocs

Operational Acceptance. Central Xxxxxx shall notify Con Edison upon completion of the construction of the Second Tie. Central Xxxxxx shall inspect and accept the Second Tie up to and including circuit breaker B9756 to confirm its compliance with the requirements of Section 3.0l (a3.0l(a) and its fitness for commercial operation. Con Edison shall test and accept the disconnect switch to be located in its substation and its associated indication and operational controls to confirm their compliance with the requirements of Section 3.0l (a) and their fitness for commercial operation. Central Xxxxxx and Con Edison Xxxxxx will both test the relay protection equipment that operates circuit breaker B9756. Promptly after those matters have been confirmed to Con EdisonXxxxxx's reasonable satisfaction, Con Edison Xxxxxx shall provide written notification to Central Xxxxxx that the Second Tie is acceptable.

Appears in 1 contract

Samples: Facilities Agreement