Common use of Notification Requirements Clause in Contracts

Notification Requirements. Upon the occurrence of a Force Majeure Event, the affected Party shall notify the other Party as soon as reasonably practicable and in any event within 10 (ten) business days of it becoming aware of the relevant Force Majeure Event. Such notification shall give sufficient details to identify the particular event claimed to be a Force Majeure Event and shall contain detailed information relating to the failure to perform (or delay in performing), including the date of occurrence of the Force Majeure Event, the effect of the Force Majeure Event on the ability of the affected Party to perform, the action being taken in accordance with Clause 14.2(a) and an estimate of the period of time required to overcome the Force Majeure Event. The affected Party shall provide the other Party with any further information it receives or becomes aware of which relates to the Force Majeure Event and provide an update on the estimate of the period of time required to overcome its effects.

Appears in 4 contracts

Samples: Framework Agreement, Framework Agreement, Framework Agreement

AutoNDA by SimpleDocs

Notification Requirements. Upon the occurrence of a Force Majeure Event, the affected Party shall notify the other Party as soon as reasonably practicable and in any event within 10 ten (ten10) business days Working Days of it becoming aware of the relevant Force Majeure Event. Such notification shall give sufficient details to identify the particular event claimed to be a Force Majeure Event and shall contain detailed information relating to the failure to perform (or delay in performing), including the date of occurrence of the Force Majeure Event, the effect of the Force Majeure Event on the ability of the affected Party to perform, the action being taken in accordance with Clause 14.2(a) Clause11.2 and an estimate of the period of time required to overcome the Force Majeure Event. The affected Party shall provide the other Party with any further information it receives or becomes aware of which relates to the Force Majeure Event and provide an update on the estimate of the period of time required to overcome its effects.

Appears in 3 contracts

Samples: Professional Consultant Service Agreement, Insert Agreement, Insert Agreement

Notification Requirements. Upon the occurrence of a Force Majeure Event, the affected Party shall notify the other Party as soon as reasonably practicable and in any event within 10 ten (ten10) business days Working Days of it becoming aware of the relevant Force Majeure Event. Such notification shall give sufficient details to identify the particular event claimed to be a Force Majeure Event and shall contain detailed information relating to the failure to perform (or delay in performing), including the date of occurrence of the Force Majeure Event, the effect of the Force Majeure Event on the ability of the affected Party to perform, the action being taken in accordance with Clause 14.2(a12.2(a) and an estimate of the period of time required to overcome the Force Majeure Event. The affected Party shall provide the other Party with any further information it receives or becomes aware of which relates to the Force Majeure Event and provide an update on the estimate of the period of time required to overcome its effects.

Appears in 3 contracts

Samples: Study Agreement, Study Agreement, Study Agreement

Notification Requirements. Upon the occurrence of a Force Majeure Event, the affected Party shall notify the other Party as soon as reasonably practicable and in any event within 10 one (ten1) business days Working Days of it becoming aware of the relevant Force Majeure Event. Such notification shall give sufficient details to identify the particular event claimed to be a Force Majeure Event and shall contain detailed information relating to the failure to perform (or delay in performing), including the date of occurrence of the Force Majeure Event, the effect of the Force Majeure Event on the ability of the affected Party to perform, the action being taken in accordance with Clause 14.2(a12.2(a) and an estimate of the period of time required to overcome the Force Majeure Event. The affected Party shall provide the other Party with any further information it receives or becomes aware of which relates to the Force Majeure Event and provide an update on the estimate of the period of time required to overcome its effects.

Appears in 2 contracts

Samples: Insert Agreement, Insert Agreement

Notification Requirements. Upon the occurrence of a Force Majeure Event, the affected Party shall notify the other Party as soon as reasonably practicable and in any event within 10 ten (ten10) business days Business Days of it becoming aware of the relevant Force Majeure Event. Such notification shall give sufficient details to identify the particular event claimed to be a Force Majeure Event and shall contain detailed information relating to the failure to perform (or delay in performing), including the date of occurrence of the Force Majeure Event, the effect of the Force Majeure Event on the ability of the affected Party to perform, the action being taken in accordance with Clause 14.2(a) and an estimate of the period of time required to overcome the Force Majeure Event. The affected Party shall provide the other Party with any further information it receives or becomes aware of which relates to the Force Majeure Event and provide an update on the estimate of the period of time required to overcome its effects.

Appears in 2 contracts

Samples: Framework Agreement, Framework Agreement

Notification Requirements. Upon the occurrence of a Force Majeure Event, the affected Party shall notify the other Party Parties as soon as reasonably practicable and in any event within 10 ten (ten10) business days Business Days of it becoming aware of the relevant Force Majeure Event. Such notification shall give sufficient details to identify the particular event claimed to be a Force Majeure Event and shall contain detailed information relating to the failure to perform (or delay in performing), including the date of occurrence of the Force Majeure Event, the effect of the Force Majeure Event on the ability of the affected Party to perform, the action being taken in accordance with Clause 14.2(a16.2(a) and an estimate of the period of time required to overcome the Force Majeure Event. The affected Party shall provide the other Party with any further information it receives or becomes aware of which relates to the Force Majeure Event and provide an update on the estimate of the period of time required to overcome its effects.

Appears in 2 contracts

Samples: Framework Agreement, Framework Agreement

Notification Requirements. Upon the occurrence of a Force Majeure Event, the affected Party shall notify the other Party as soon as reasonably practicable and in any event within 10 ten (ten10) business days Working Days of it becoming aware of the relevant Force Majeure Event. Such notification shall give sufficient details to identify the particular event claimed to be a Force Majeure Event and shall contain detailed information relating to the failure to perform (or delay in performing), including the date of occurrence of the Force Majeure Event, the effect of the Force Majeure Event on the ability of the affected Party to perform, the action being taken in accordance with Clause 14.2(a) 11.2 and an estimate of the period of time required to overcome the Force Majeure Event. The affected Party shall provide the other Party with any further information it receives or becomes aware of which relates to the Force Majeure Event and provide an update on the estimate of the period of time required to overcome its effects.

Appears in 1 contract

Samples: Professional Consultant Service Agreement

Notification Requirements. Upon the occurrence of a Force Majeure Event, the affected Party shall notify the other Party as soon as reasonably practicable and in any event within 10 (ten) business days of it becoming aware of the relevant Force Majeure Event. Such notification shall give sufficient details to identify the particular event claimed to be a Force Majeure Event and shall contain detailed information relating to the failure to perform (or delay in performing), including the date of occurrence of the Force Majeure Event, the effect of the Force Majeure Event on the ability of the affected Party to perform, the action being taken in accordance with Clause 14.2(a) 14.2. and an estimate of the period of time required to overcome the Force Majeure Event. The affected Party shall provide the other Party with any further information it receives or becomes aware of which relates to the Force Majeure Event and provide an update on the estimate of the period of time required to overcome its effects.

Appears in 1 contract

Samples: Service Agreement

Notification Requirements. Upon the occurrence of a Force Majeure Event, the affected Party shall notify the other Party as soon as reasonably practicable and in any event within 10 (ten) business Business days of it becoming aware of the relevant Force Majeure Event. Such notification shall give sufficient details to identify the particular event claimed to be a Force Majeure Event and shall contain detailed information relating to the failure to perform (or delay in performing), including the date of occurrence of the Force Majeure Event, the effect of the Force Majeure Event on the ability of the affected Party to perform, the action being taken in accordance with Clause 14.2(a13.2(a) and an estimate of the period of time required to overcome the Force Majeure Event. The affected Party shall provide the other Party with any further information it receives or becomes aware of which relates to the Force Majeure Event and provide an update on the estimate of the period of time required to overcome its effects.

Appears in 1 contract

Samples: Service Agreement

Notification Requirements. Upon the occurrence of occurrenceof a Force Majeure Event, ,the affected Party shall notify the other Party as soon as reasonably practicable asreasonablypracticable and in any event within 10 ten (ten10) business days of Working Daysof it becoming aware of the relevant Force Majeure Event. Such notification shall give sufficient details to identify the particular event claimed to be a Force Majeure Event and shall contain detailed information relating to the failure to perform (or delay in performing), including the date of occurrence of the Force Majeure Event, the effect of the Force Majeure Event on the ability of the affected Party to perform, the action being taken in accordance with Clause 14.2(a) and accordancewith Clause11.2(a)and an estimate of estimateof the period of time required to overcome the Force Majeure overcomethe ForceMajeure Event. The affected Party shall provide the other Party with any further information it receives or becomes aware of which relates to the Force Majeure Event and provide an update on the estimate of the period of time required to overcome its overcomeits effects.

Appears in 1 contract

Samples: www.railbaltica.org

Notification Requirements. Upon the occurrence of a Force Majeure Event, the affected Party shall notify the other Party as soon as reasonably practicable and in any event within 10 (ten) business days of it becoming aware of the relevant Force Majeure Event. Such notification shall give sufficient details to identify the particular event claimed to be a Force Majeure Event and shall contain detailed information relating to the failure to perform (or delay in performing), including the date of occurrence of the Force Majeure Event, the effect of the Force Majeure Event on the ability of the affected Party to perform, the action being taken in accordance with Clause 14.2(a15.2(a) and an estimate of the period of time required to overcome the Force Majeure Event. The affected Party shall provide the other Party with any further information it receives or becomes aware of which relates to the Force Majeure Event and provide an update on the estimate of the period of time required to overcome its effects.

Appears in 1 contract

Samples: www.railbaltica.org

Notification Requirements. Upon the occurrence of a Force Majeure Event, the affected Party shall notify the other Party as soon as reasonably practicable and in any event within 10 evenwt ithin ten (ten10) business days Working Days of it becoming aware of the relevant Force Majeure Event. .Such notification shall give sufficient details to identify the particular event claimed to be a Force Majeure Event and shall contain detailed information relating to the failure to perform (or delay in performing), including the date of occurrence of the Force Majeure Event, the effect of the Force Majeure Event on the ability of the affected Party to perform, the action being taken in accordance with Clause 14.2(a) Clause12.2(a)of this Agreement and an estimate of the period of time required to overcome the Force Majeure Event. The affected Party shall provide the other Party with any further information it receives or becomes aware of which relates to the Force Majeure Event and provide an update on the estimate of the period of time required to overcome its effects.

Appears in 1 contract

Samples: Services Agreement

Notification Requirements. Upon the occurrence of a Force Majeure Event, the affected Party shall notify the other Party as soon as reasonably practicable and in any event within 10 (ten) business days Working Days of it becoming aware of the relevant Force Majeure Event. Such notification shall give sufficient details to identify the particular event claimed to be a Force Majeure Event and shall contain detailed information relating to the ht e failure to perform (or delay in performing), including the date of occurrence of the Force Majeure Event, the effect of the Force Majeure Event on the ability of the affected Party to perform, the action being taken in accordance with Clause 14.2(aClause12.2(a) and an andan estimate of the period of time required to overcome the Force Majeure Event. The affected Party shall provide the other Party with any further information it receives or becomes aware of which relates to the Force Majeure Event and provide an update on the onthe estimate of the period of time required to overcome its effects.

Appears in 1 contract

Samples: Study Agreement

Notification Requirements. Upon the occurrence of a Force Majeure Event, the affected Party shall notify the other Party as soon as reasonably practicable and in any event evnet within 10 ten (ten10) business days Working Days of it becoming aware of the relevant Force Majeure Event. Such notification shall give sufficient details to identify the particular event claimed to be a Force Majeure Event and shall contain detailed information relating to relatingto the failure to perform (or delay in performing), including the date of occurrence of the Force Majeure Event, the effect of the Force Majeure Event on the ability of the affected Party to perform, the action being taken in accordance with Clause 14.2(a) and 10.2(a)and an estimate of the period of time required to overcome the Force Majeure Event. The affected Party shall provide the other Party with any further information it receives or becomes aware of which relates to the Force Majeure Event and provide an update on the estimate of the period of time required to overcome its effects.

Appears in 1 contract

Samples: Study Agreement

Notification Requirements. Upon the occurrence of a Force Majeure Event, the affected Party shall notify the other Party as soon as reasonably practicable and in any event within 10 ten (ten10) business days of it becoming Working Days otf bi ecoming aware of the relevant Force Majeure Event. Such notification shall give sufficient details to identify the particular event claimed to be a Force Majeure Event and shall contain detailed information relating to the failure to perform (or delay in delayin performing), including the date of occurrence of the Force Majeure Event, the effect of the Force Majeure Event on the ability of the affected Party to perform, the action being taken in accordance with Clause 14.2(aClause10.2(a) and an estimate of the period of time required to overcome the Force Majeure Event. The affected Party shall provide the other Party with any further information it receives or becomes aware of which relates to the Force Majeure Event and provide an update on the estimate of the period of time required to overcome its effects.

Appears in 1 contract

Samples: Study Agreement

Notification Requirements. Upon the occurrence of a Force Majeure Event, the affected Party shall notify the other Party Parties as soon as reasonably practicable and in any event within 10 ten (ten10) business days Working Days of it becoming aware of the relevant Force Majeure Event. Such notification shall give sufficient details to identify the particular event claimed to be a Force Majeure Event and shall contain detailed information relating to the failure to perform (or delay in performing), including the date of occurrence of the Force Majeure Event, the effect of the Force Majeure Event on the ability of the affected Party to perform, the action being taken in accordance with Clause 14.2(a11.2(a) and an estimate of the period of time required to overcome the Force Majeure Event. The affected Party shall provide the other Party Parties with any further information it receives or becomes aware of which relates to the Force Majeure Event and provide an update on the estimate of the period of time required to overcome its effects.

Appears in 1 contract

Samples: Insert Agreement

Notification Requirements. Upon the occurrence of a Force Majeure Event, the affected Party shall Partyshall notify the other Party as Partiesas soon as reasonably practicable and in any event within 10 ten (ten) business days 10)BusinessDays of it becoming aware of the relevant Force Majeure Event. Such notification shall give sufficient details to identify the particular event claimed to be a Force Majeure Event and shall contain detailed containdetailed information relating to the failure to perform (or delay in performing), including the date of occurrence of the Force Majeure Event, the effect of the Force Majeure Event on the ability of the affected Party to perform, the action being taken in accordance with Clause 14.2(aClause14.2(a) and an estimate of the period of time required to overcome the Force Majeure Event. The affected Party shall provide the other Party with any further information it receives or becomes aware of which relates to the Force Majeure Event and provide an update on the estimate of the period of time required to overcome its effects.

Appears in 1 contract

Samples: www.railbaltica.org

AutoNDA by SimpleDocs

Notification Requirements. Upon the occurrence of a Force Majeure Event, the affected Party shall notify the other Party as soon as reasonably practicable and in any event within 10 three (ten3) business days Working Days of it becoming aware of the relevant Force Majeure Event. Such notification shall give sufficient details to identify the particular event claimed to be a Force Majeure Event and shall contain detailed information relating to the failure to perform (or delay in performing), including the date of occurrence of the Force Majeure Event, the effect of the Force Majeure Event on the ability of the affected Party to perform, the action being taken in accordance with Clause 14.2(a) Clause11.2 and an estimate of the period of time required to overcome the Force Majeure Event. The affected Party shall provide the other Party with any further information it receives or becomes aware of which relates to the Force Majeure Event and provide an update on the estimate of the period of time required to overcome its effects.

Appears in 1 contract

Samples: Professional Consultanstervice Agreement

Notification Requirements. Upon the occurrence of a Force Majeure Event, the affected Party shall notify the other Party as soon as reasonably practicable and in any event within 10 (ten) business days of it becoming aware of the relevant Force Majeure Event. Such notification shall give sufficient details to identify the particular event claimed to be a Force Majeure Event and shall contain detailed information relating to the failure to perform (or delay in performing), including the date of occurrence of the Force Majeure Event, the effect of the Force Majeure Event on the ability of the affected Party to perform, the action being taken in accordance with Clause 14.2(a14.2.1.(a) and an estimate of the period of time required to overcome the Force Majeure Event. The affected Party shall provide the other Party with any further information it receives or becomes aware of which relates to the Force Majeure Event and provide an update on the estimate of the period of time required to overcome its effects.

Appears in 1 contract

Samples: Framework Agreement

Notification Requirements. Upon the occurrence of a Force Majeure Event, the affected Party shall notify the other Party as soon as reasonably practicable and in any event within 10 withinten (ten10) business days Working Days of it becoming aware of the relevant Force Majeure Event. Such EventS. uch notification shall give sufficient details to identify the particular event claimed to be a Force Majeure Event and shall contain detailed information relating to the failure to perform (or delay in performing), including the date of occurrence of the Force Majeure Event, the effect of the Force Majeure Event on the ability of the affected Party to perform, the action being taken in accordance with Clause 14.2(a) Clause11.2 and an estimate of the period of time required to overcome the Force Majeure Event. .The affected Party shall provide the other Party with any further information it receives or becomes aware of awareof which relates to the Force Majeure Event and provide an update on the estimate of the period of time required to overcome its effects.

Appears in 1 contract

Samples: Professional Consultant Service Agreement

Notification Requirements. Upon the occurrence of a Force Majeure Event, the affected Party shall notify the other Party as soon as reasonably practicable and in any event within 10 ten (ten10) business days Working Days of it becoming aware of the relevant Force Majeure Event. Such notification shall give sufficient details to identify the particular event claimed to be a Force Majeure Event and shall contain detailed information relating to the failure to perform (or delay in performing), including the date of occurrence of the Force Majeure Event, the effect of the Force Majeure Event on the ability of the affected Party to perform, the action being taken in accordance with Clause 14.2(a10.2(a) and an estimate of the period of time required to overcome the Force Majeure Event. The affected Party shall provide the other Party with any further information it receives or becomes aware of which relates to the Force Majeure Event and provide an update on the estimate of the period of time required to overcome its effects.

Appears in 1 contract

Samples: Study Agreement

Notification Requirements. Upon the occurrence of a Force Majeure Event, the affected Party shall notify the other Party as soon as reasonably practicable and in any event within 10 ten (ten10) business days Working Days of it becoming aware of the relevant Force Majeure Event. .Such notification shall give sufficient details to identify the particular event claimed to be a Force Majeure Event and shall contain detailed information relating to the failure to perform (or delay in performing), including the date of occurrence of the Force Majeure Event, the effect of the Force Majeure Event Eevnt on the ability of the affected Party to perform, the action being taken in accordance with Clause 14.2(a) Clause12.2(a)of this Agreement and an estimate of the period of time required to overcome the Force Majeure Event. The affected Party shall provide the other Party with any further information it receives or becomes aware of which relates to the Force Majeure Event and provide an update on the estimate of the period of time required to overcome its effects.

Appears in 1 contract

Samples: Services Agreement

Notification Requirements. Upon the occurrence of a Force Majeure Event, the affected Party shall notify the other Party as soon as reasonably practicable and in any event within 10 three (ten3) business days Working Days of it becoming aware of the relevant Force Majeure Event. Such notification shall give sufficient details to identify the particular event claimed to be a Force Majeure Event and shall contain detailed information relating to the failure to perform (or delay in performing), including the date of occurrence of the Force Majeure Event, the effect of the Force Majeure Event on the ability of the affected Party to perform, the action being taken in accordance with Clause 14.2(a) 11.2 and an estimate of the period of time required to overcome the Force Majeure Event. The affected Party shall provide the other Party with any further information it receives or becomes aware of which relates to the Force Majeure Event and provide an update on the estimate of the period of time required to overcome its effects.

Appears in 1 contract

Samples: Professional Consultant Service Agreement

Notification Requirements. Upon the occurrence of a Force Majeure Event, the affected Party shall notify the other Party as soon as reasonably asreasonably practicable and in any event within 10 withinten (ten10) business days Working Days of it becoming aware of the relevant Force Majeure Event. Such notification shall give sufficient details to identify the particular event claimed to be a Force Majeure Event and shall contain ocntain detailed information relating to the failure to perform (or delay in performing), including the date of occurrence of the Force Majeure Event, the effect of the Force Majeure Event on the ability of the affected Party to perform, the action being taken in accordance with Clause 14.2(a) Clause11.2 and an estimate of the period of time required to overcome the Force Majeure Event. The affected Party shall provide the other Party with any further information it receives or becomes aware of which relates to the Force Majeure Event and provide an update on the estimate of the period of time required to overcome its effects.

Appears in 1 contract

Samples: Agreement

Notification Requirements. Upon the occurrence of a Force Majeure Event, the affected Party shall notify the other Party as soon as reasonably practicable and in any event within 10 three (ten3) business days Working Days of it becoming aware of the relevant Force Majeure Event. Such notification noitfication shall give sufficient details to identify the particular event claimed to be a Force Majeure Event and shall contain detailed information relating to the failure to perform (or delay in performing), including the date of occurrence of the Force Majeure Event, the effect of the Force Majeure Event on the ability of the affected Party to perform, the action being taken in accordance with Clause 14.2(a) Clause11.2 and an estimate of the period of time required to overcome the Force Majeure Event. The affected Party shall provide the other Party with any further information it receives or becomes aware of which relates to the Force Majeure Event and provide an update on the estimate of the period of time required to overcome its effects.

Appears in 1 contract

Samples: Agreement

Notification Requirements. Upon the occurrence of a Force Majeure Event, the affected Party shall notify the other Party as soon as reasonably practicable and in any event within 10 3 (tenthree) business days of it becoming aware of the relevant Force Majeure Event. Such notification shall give sufficient details to identify the particular event claimed to be a Force Majeure Event and shall contain detailed information relating to the failure to perform (or delay in performing), including the date of occurrence of the Force Majeure Event, the effect of the Force Majeure Event on the ability of the affected Party to perform, the action being taken in accordance with Clause 14.2(a) and an estimate of the period of time required to overcome the Force Majeure Event. The affected Party shall provide the other Party with any further information it receives or becomes aware of which relates to the Force Majeure Event and provide an update on the estimate of the period of time required to overcome its effects.

Appears in 1 contract

Samples: Supply Agreement

Notification Requirements. Upon the occurrence of a Force Majeure Event, the affected theaffected Party shall notify the other Party as soon as reasonably practicable and in any event within 10 ten (ten10) business days Working Days of it becoming aware of the relevant Force Majeure Event. Such notification shall give sufficient details to identify the particular event claimed to be a Force Majeure Event and shall contain detailed information relating to the failure to perform (or delay in performing), including the date of occurrence of the Force Majeure Event, the effect of the Force Majeure Event on the ability of the affected Party to perform, the action being taken in accordance with Clause 14.2(a11.2(a) and an estimate of the period of time required to overcome the Force Majeure Event. The affected Party shall provide the other Party with any further information it receives or becomes aware of which relates to the Force Majeure Event and provide an update on the estimate of the period of time required to overcome its effects.

Appears in 1 contract

Samples: Insert Agreement