Common use of Notice of Substantial Completion shall establish the Date of Substantial Completion of the Project Clause in Contracts

Notice of Substantial Completion shall establish the Date of Substantial Completion of the Project. The Construction Manager acknowledges and agrees that because the departments, agencies and institutions of the State of Colorado are generally involved with the business of the public at large, greater care must be taken in establishing the Date of Substantial Completion than might otherwise be the case to ensure that a project or building or discrete physical portion of the Work is fully usable and safe for public use, and that such care necessarily raises the standard by which the concept of Substantial Completion is applied for a public building.

Appears in 5 contracts

Samples: www.cuanschutz.edu, www.colorado.gov, www.colorado.gov

AutoNDA by SimpleDocs
Time is Money Join Law Insider Premium to draft better contracts faster.