Notice of Force Majeure Event. (a) As soon as practicable and in any case within 7 days of the date of occurrence of a Force Majeure Event or the date of knowledge thereof, the Affected Party shall notify Independent Consultant and the other Party of the same setting out, inter alia, the following in reasonable detail:
Appears in 7 contracts
Samples: Draft Concession Agreement, Concession Agreement, Concession Agreement
Notice of Force Majeure Event. (a) As A soon as practicable and in any case within 7 days of the date of occurrence of a Force Majeure Event or the date of knowledge thereof, the Affected Party shall notify Independent Consultant and the other Party and also the Project Engineer and the First Party representative of the same setting out, inter alia, the following in reasonable detail:
Appears in 3 contracts
Samples: Agreement (BioCrude Technologies USA, Inc.), Agreement (BioCrude Technologies USA, Inc.), Agreement (BioCrude Technologies USA, Inc.)
Notice of Force Majeure Event. (a) a. As soon as practicable and in any case within 7 days of the date of occurrence of a Force Majeure Event or the date of knowledge thereof, the Affected Party shall notify Independent Consultant and the other Party of the same setting out, inter alia, the following in reasonable detail:
Appears in 3 contracts
Samples: Concession Agreement, Concession Agreement, Concession Agreement
Notice of Force Majeure Event. (a) As soon as practicable and in any case within 7 days of the date of occurrence of a Force Majeure Event or the date of knowledge thereof, the Affected Party shall notify Independent Consultant Engineer and the other Party of the same setting out, inter alia, the following in reasonable detail:
Appears in 2 contracts
Samples: Concession Agreement, Concession Agreement
Notice of Force Majeure Event. (a) As soon as practicable and in any case within 7 days of the date of occurrence of a Force Majeure Event or the date of knowledge thereof, the Affected Party shall notify Independent Consultant the Project Engineer, and the other Party of the same setting out, inter alia, the following in reasonable detail:
Appears in 2 contracts
Samples: Concession Agreement, Concession Agreement
Notice of Force Majeure Event. (a) As soon as practicable and in any case within 7 seven (7) days of the date of occurrence of a Force Majeure Event or the date of knowledge thereof, the Affected Party shall notify Independent Consultant and the other Party of the same setting out, inter alia, the following in reasonable detail:
Appears in 2 contracts
Samples: Project Implementation Agreement, Project Implementation Agreement
Notice of Force Majeure Event. (a) a. As soon as practicable and in any case within 7 (seven) days of the date of occurrence of a Force Majeure Event or the date of knowledge thereof, the Affected Party shall notify Independent Consultant CoC/ Project Officer if applicable and the other Party party of the same setting out, inter alia, the following in reasonable detail:
Appears in 1 contract
Samples: Draft Concession Agreement
Notice of Force Majeure Event. (a) As soon as practicable and in any case within 7 days of the date of occurrence of a Force Majeure Event or the date of knowledge thereof, the Affected Party shall notify Independent Project Monitoring Consultant and the other Party of the same setting out, inter alia, the following in reasonable detail:
Appears in 1 contract
Samples: Draft Concession Agreement
Notice of Force Majeure Event. (a) As soon as practicable and in any case within 7 days of the date of occurrence of a Force Majeure Event or the date of knowledge thereof, the Affected Party affected party shall notify Independent Consultant and the other Party party of the same same, setting out, inter alia, the following in reasonable detail:
Appears in 1 contract
Samples: Draft Concession Agreement
Notice of Force Majeure Event. (a) As soon as practicable and in any case within 7 (Seven) days of the date of occurrence of a Force Majeure Event or the date of knowledge thereof, the Affected Party shall notify Independent Consultant and the other Party of the same setting out, inter alia, the following in reasonable detail:
Appears in 1 contract
Samples: Concession Agreement
Notice of Force Majeure Event. (a) As soon as practicable and in any case within 7 (seven) days of the date of occurrence of a Force Majeure Event or the date of knowledge thereof, the Affected Party shall notify Construction Supervisor / Independent Consultant Engineer and the other Party of the same setting out, inter alia, the following in reasonable detail:
Appears in 1 contract
Samples: Concession Agreement
Notice of Force Majeure Event. (a) 22.1.1 As soon as practicable and in any case within 7 (seven) days of the date of occurrence of a Force Majeure Event or the date of knowledge thereof, the Affected Party affected thereby shall notify Independent Consultant and the other Party of the same setting out, inter alia, the following in reasonable detail:
Appears in 1 contract
Samples: Concession Agreement
Notice of Force Majeure Event. (ai) As soon as practicable and in any case within 7 days of the date of occurrence of a Force Majeure Event or the date of knowledge thereof, the Affected Party shall notify Independent Consultant Engineer and the other Party of the same setting out, inter alia, the following in reasonable detail:
Appears in 1 contract
Samples: www.mpcb.gov.in