NON-CURABLE DEFAULTS. Notwithstanding the other provisions of Section 17.1, Owner may also elect to declare Contractor in material default and may terminate Contractor immediately upon written notice (unless a longer period is otherwise expressly provided in this Agreement with regard to the matters in Sections 17.1.2.1 through 17.1.2.5 below, it being agreed that the cure periods in Section 17.1.1 above do not apply to Sections 17.1.2.1 through 17.1.2.5) and/or take such other action as Owner may be allowed, in the event of any of the following: 17.1.2.1 The commencement of an action or petition by or against Leighton, China/Macau, China/HK or any Guarantor under applicable bankruptcy laws; or any general assignment by Leighton, China/Macau, China/HK or any Guarantor for the benefit of its creditors; or the appointment of a receiver, trustee or manager to take charge of the assets of Leighton, China/Macau, China/HK or any Guarantor; or any of Leighton, China/Macau, China/HK or any Guarantor becomes insolvent, goes into liquidation, has a receiving or administrative order made against it or compounds with its creditors; or if any act is done or event occurs which (under any applicable Law) has a similar effect to any of the acts or events outlined herein; 17.1.2.2 The exercising of any mechanics’ or materialmens’ lien rights on Owner’s property, the Site, the Project and/or the Work by a Subcontractor, Vendor, laborer, materialman, or supplier or any other party providing services or material engaged by, on behalf of, or acting under the direction of Contractor or any Subcontractor or Vendor in connection with the Work, unless that Owner’s property, the Site, the Project and/or the Work, as applicable, is released from such lien(s) or, at Owner’s option, satisfied by bond or other security, in an amount and with a bonding company reasonably satisfactory to Owner and Owner’s Lenders within the time periods set forth in and pursuant to Section 7.19.2 hereof; 17.1.2.3 Failure of Contractor for five successive days or an aggregate of seven days in any thirty (30) day period (other than Sundays or national holidays), to have an adequate number of laborers or Subcontractors at the Site who are actively and productively working on the Project, unless a Permissible Delay exists for such absence, unless within five (5) days after written notice from Owner Contractor has and thereafter maintains an adequate number of laborers and Subcontractors on Site actively and productively working on the Project; or 17.1.2.4 Failure of Contractor after five (5) days following request from Owner’s Lenders to provide Owner and Owner’s Lenders with the evidence required under Section 3.1.3 of this Agreement.
Appears in 1 contract
NON-CURABLE DEFAULTS. Notwithstanding the other provisions of Section 17.1, Owner may also elect to declare Contractor in material default and may terminate Contractor immediately upon written notice (unless a longer period is otherwise expressly provided in this Agreement with regard to the matters in Sections 17.1.2.1 through 17.1.2.5 17.1.2.4 below, it being agreed that the cure periods in Section 17.1.1 above do not apply to Sections 17.1.2.1 through 17.1.2.517.1.2.4) and/or take such other action as Owner may be allowed, in the event of any of the following:
17.1.2.1 The commencement of an action or petition by or against Leighton, China/Macau, China/HK or any Guarantor under applicable bankruptcy laws; or any general assignment by Leighton, China/Macau, China/HK or any Guarantor for the benefit of its creditors; or the appointment of a receiver, trustee or manager to take charge of the assets of Leighton, China/Macau, China/HK or any Guarantor; or any of Leighton, China/Macau, China/HK or any Guarantor becomes insolvent, goes into liquidation, has a receiving or administrative order made against it or compounds with its creditors; or if any act is done or event occurs which (under any applicable Law) has a similar effect to any of the acts or events outlined herein;
17.1.2.2 The exercising of any mechanics’ or materialmens’ lien rights on Owner’s property, the Site, the Project and/or the Work by a Subcontractor, Vendor, laborer, materialman, or supplier or any other party providing services or material engaged by, on behalf of, or acting under the direction of Contractor or any Subcontractor or Vendor in connection with the Work, unless that Owner’s property, the Site, the Project and/or the Work, as applicable, is released from such lien(s) or, at Owner’s option, satisfied by bond or other security, in an amount and with a bonding company reasonably satisfactory to Owner and Owner’s Lenders within the time periods set forth in and pursuant to Section 7.19.2 hereof;
17.1.2.3 Failure of Contractor for five successive days or an aggregate of seven days in any thirty (30) day period (other than Sundays or national holidays), to have an adequate number of laborers or Subcontractors at the Site who are actively and productively working on the Project, unless a Permissible Delay exists for such absence, unless within five (5) days after written notice from Owner Contractor has and thereafter maintains an adequate number of laborers and Subcontractors on Site actively and productively working on the Project; or
17.1.2.4 Failure of Contractor after five (5) days following request from Owner’s Lenders to provide Owner and Owner’s Lenders with the evidence required under Section 3.1.3 3.1.5 of this Agreement.
Appears in 1 contract