Common use of Narrative Report Clause in Contracts

Narrative Report. As part of the CPM schedule update, the Contractor prepares a written narrative report, highlighting the progress during the past update period. This written report includes, but is not necessarily limited to the following information: a. Summary of Work accomplished during the past update period; b. Contract milestone comparison chart; c. Analysis of critical path(s); d. Analysis of time lost/gained during the update period; e. Identification of problem areas; and f. Recommended solutions to current problems.

Appears in 2 contracts

Sources: Construction Contract, Consulting Agreement

Narrative Report. As part of the CPM schedule Schedule update, the Contractor prepares you must prepare a written narrative report, highlighting the progress during the past update period. This written report includes, but is not necessarily limited to must include the following information: a. Summary of Work accomplished during the past update period; b. Contract milestone comparison chart; c. Analysis of critical path(s); d. Analysis of time lost/gained during the update period; e. Identification of problem areas; and f. Recommended solutions to current problems.

Appears in 1 contract

Sources: Design Build Agreement