Narrative Report. As part of the CPM schedule update, the Contractor prepares a written narrative report, highlighting the progress during the past update period. This written report includes, but is not necessarily limited to the following information: a. Summary of Work accomplished during the past update period; b. Contract milestone comparison chart; c. Analysis of critical path(s); d. Analysis of time lost/gained during the update period; e. Identification of problem areas; and f. Recommended solutions to current problems.
Appears in 2 contracts
Sources: Construction Contract, Consulting Agreement
Narrative Report. As part of the CPM schedule Schedule update, the Contractor prepares you must prepare a written narrative report, highlighting the progress during the past update period. This written report includes, but is not necessarily limited to must include the following information:
a. Summary of Work accomplished during the past update period;
b. Contract milestone comparison chart;
c. Analysis of critical path(s);
d. Analysis of time lost/gained during the update period;
e. Identification of problem areas; and
f. Recommended solutions to current problems.