Narrative Report. The project scheduler shall provide a narrative with each schedule update which shall include the following information. i. Introduction: An executive summary of the schedule narrative. ii. Project Description: A brief description of the Project. iii. Discussion of changes and variances by each Contract and specific recommendations. iv. Anticipated award dates, actual award dates, contractors selected and any recommendations for changes to the bid strategy going forward.