Common use of Monthly progressreports Clause in Contracts

Monthly progressreports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority and the Authority’s Engineer a monthly report on progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s Engineer. Contract AgreementPage 75 of 159

Appears in 1 contract

Sources: Contract Agreement

Monthly progressreports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority and the Authority’s Engineer a monthly report on progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s Engineer. Contract AgreementPage 75 of 159The Contractor agrees that reporting under this Clause 11.7 shall continue until the

Appears in 1 contract

Sources: Contract Agreement