Progress Reports Sample Clauses

Progress Reports. The Recipient shall submit to the OPWC, at the OPWC's request, summary reports detailing the progress of the Project pursuant to this Agreement and any additional reports containing such information as the OPWC may reasonably require.
Progress Reports. 5. Within 30 days after the end of each calendar quarter following the date of this Agreement, the board of directors shall submit to the Reserve Bank written progress reports detailing the form and manner of all actions taken to secure compliance with the provisions of this Agreement and the results thereof, and a parent company only balance sheet, income statement, and, as applicable, report of changes in stockholders’ equity.
Progress Reports. The Contractor shall submit progress reports to the State upon request. The report shall be oral, unless the State, upon receipt of the oral report, should deem it necessary to have it in written form. The progress reports shall serve the purpose of assuring the State that work is progressing in line with the schedule, and that completion can be reasonably assured on the scheduled date.
Progress Reports. The Recipient shall submit to the Director, at the Director’s request, summary reports detailing the progress of the Project pursuant to this Agreement and any additional reports containing such information as the Director may reasonably require
Progress Reports. As directed by the JBE, Contractor must deliver progress reports or meet with JBE personnel on a regular basis to allow: (i) the JBE to determine whether the Contractor is on the right track and the project is on schedule, (ii) communication of interim findings, and (iii) opportunities for airing difficulties or special problems encountered so that remedies can be developed quickly.
Progress Reports. A progress report must be submitted with each monthly pay request indicating the percentage of design tasks completed to date. This report will serve as support for payment to Consulting Engineer/Architect.
Progress Reports. At the end of each calendar quarter after the Effective Date and until the Commercial Operation Date, Seller shall provide Buyer with a progress report regarding Critical Milestones not yet achieved, including projected time to completion of the Facility, in accordance with the form attached hereto as Exhibit C, and shall provide supporting documents and detail regarding the same upon Buyer’s request. Seller shall permit Buyer and its advisors and consultants to review and discuss with Seller and its advisors and consultants such progress reports during business hours and upon reasonable notice to Seller.
Progress Reports. 16. Within 30 days after the end of each calendar quarter following the date of this Agreement, the Bank shall submit to the Reserve Bank and the Department written progress reports detailing the form and manner of all actions taken to secure compliance with the provisions of this Agreement and the results thereof.
Progress Reports. At monthly intervals after approval of the Program chart, the contractor is to submit to the Engineer and the purchaser written detailed progress reports in triplicate in an approved form, indicating the stage reached in the design, ordering of material, manufacture and delivery of all components of the material. The reports should include details of any delays and the remedial action proposed. These reports are to be forwarded promptly so that on receipt by the engineer the information contained therein is not more than seven days out of date.
Progress Reports. The Subrecipient shall submit regular Progress Reports to the Grantee in the form, content and frequency as required by the Grantee.