Monthly Progress Reports. During the Construction Period, the Concessionaire shall, no later than 7 (seven) days after the close of each month, furnish to the Authority and the Independent Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent Engineer.
Appears in 31 contracts
Samples: Concession Agreement, Draft Concession Agreement, Concession Agreement
Monthly Progress Reports. During the Construction Period, the Concessionaire Contractor shall, no later than 7 10 (seventen) days after the close of each month, furnish to the Authority and the Independent Authority’s Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent Authority’s Engineer.. The Contractor agrees that reporting under this Clause 11.7 shall continue until the date of the completion of the Works. Each report shall include:
Appears in 28 contracts
Samples: Draft Contract Agreement, Draft Contract Agreement, Contract Agreement
Monthly Progress Reports. During the Construction Period, the Concessionaire Contractor shall, no later than 7 10 (seventen) days after the close of each month, furnish to the Authority and the Independent Authority’s Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent Authority’s Engineer.
Appears in 9 contracts
Samples: Epc Agreement, And Construction), Procurement and Construction)
Monthly Progress Reports. During the Construction Period, the Concessionaire Contractor shall, no later than 7 10 (seventen) days after the close of each month, furnish to the Authority and the Independent Authority Engineer a monthly report on the progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent EngineerAuthority Engineer along with all resources deployed and all problems faced during work.
Appears in 6 contracts
Samples: And Construction Agreement, And Construction Agreement, Engineering, Procurement and Construction
Monthly Progress Reports. During the Construction Period, the Concessionaire Contractor shall, no later than 7 10 (seventen) days after the close of each month, furnish to the Authority and the Independent Authority‟s Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent Authority‟s Engineer.
Appears in 5 contracts
Samples: (Engineering Procurement and Construction, Draft Contract Agreement, Procurement and Construction Agreement
Monthly Progress Reports. During the Construction Period, the Concessionaire shall, no later than 7 (seven7(seven) days after the close of each month, furnish to the Authority and the Independent Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent Engineer.
Appears in 4 contracts
Samples: Concession Agreement, Concession Agreement, Concession Agreement
Monthly Progress Reports. During the Construction Period, the Concessionaire shall, no later than 7 (seven) days after the close of each month, furnish to the Authority and the Independent Engineer Monitor[s] a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent EngineerMonitor[s].
Appears in 4 contracts
Samples: Concession Agreement, Concession Agreement, Concession Agreement
Monthly Progress Reports. During the Construction Period, the Concessionaire Contractor shall, no later than 7 10 (seventen) days after the close of each month, furnish to the Authority and the Independent Authority Engineer a monthly report on the progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent EngineerAuthorityEngineeralong with all resources deployed and all problems faced during work.
Appears in 4 contracts
Samples: And Construction Agreement, And Construction Agreement, indianrailways.gov.in
Monthly Progress Reports. During the Construction Period, the Concessionaire Contractor shall, no later than 7 10 (seventen) days after the close of each month, furnish to the Authority Employer and the Independent Employer's Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent Employer's Engineer.
Appears in 3 contracts
Samples: Epc Agreement, Procurement and Construction, Epc Agreement
Monthly Progress Reports. During the Construction Period, the Concessionaire Contractor shall, no later than 7 10 (seventen) days after the close of each month, furnish to the Authority and the Independent Authority’s Engineer a monthly report on the progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent EngineerAuthority’s Engineer along with all resources deployed and all problems faced during work.
Appears in 3 contracts
Samples: Procurement and Construction Agreement, Procurement and Construction Agreement, Procurement and Construction Agreement
Monthly Progress Reports. During the Construction Period, the Concessionaire Contractor shall, no later than 7 10 (seventen) days after the close of each month, furnish to the Authority and the Independent Authority’s Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent Authority’s Engineer.. The Contractor agrees that reporting under this Clause 11.7 shall continue until the date of the completion of the Works. Each report shall include: Drafit Contract Agreement
Appears in 3 contracts
Samples: Draft Contract Agreement, Draft Contract Agreement, Draft Contract Agreement
Monthly Progress Reports. During the Construction Period, the Concessionaire shall, no later than 7 (seven) days after the close of each month, furnish to the Authority and the Independent Engineer Expert a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent EngineerExpert.
Appears in 3 contracts
Samples: Draft Concession Agreement, Draft Concession Agreement, Draft Concession Agreement
Monthly Progress Reports. During the Construction Period, the Concessionaire shall, no later than 7 (seven) days after the close of each month, furnish to the Authority Government and the Independent Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent Engineer.
Appears in 3 contracts
Samples: Concession Agreement, Concession Agreement, Concession Agreement
Monthly Progress Reports. During the Construction Period, the Concessionaire shall, no later than 7 (seven) days after the close of each month, furnish to the Authority MPRDC and the Independent Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent Engineer.
Appears in 3 contracts
Samples: Concession Agreement, Concession Agreement, Concession Agreement
Monthly Progress Reports. During the Construction Period, the Concessionaire Developer shall, no later than 7 (seven) days after the close of each month, furnish to the Authority Client and the Independent Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent EngineerClient.
Appears in 2 contracts
Samples: Development Agreement, Development Agreement
Monthly Progress Reports. During the Construction Period, the Concessionaire shall, no later than 7 (seven) days after the close of each month, furnish to the Authority and the Independent Engineer a monthly report on physical and financial progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent Engineer.
Appears in 2 contracts
Samples: Model Concession Agreement, Model Concession Agreement
Monthly Progress Reports. 13.1.1 During the Construction Period, the Concessionaire shall, no later than 7 (seven) days after the close of each month, furnish to the Authority Construction Supervisor and the Independent Engineer a ULBa monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent EngineerConstruction Supervisor.
Appears in 2 contracts
Monthly Progress Reports. During the Construction Periodconstruction of Project Facilities, the Concessionaire shall, no later than 7 (seven) days after the close of each month, furnish to the Authority Government and the Independent Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent Engineer.
Appears in 2 contracts
Samples: Concession Agreement, Concession Agreement
Monthly Progress Reports. During the Construction Period, the Concessionaire Contractor shall, no later than 7 10 (seventen) days after the close of each month, furnish to the Authority Employer and the Independent Employer’s Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent Employer’s Engineer.
Appears in 2 contracts
Samples: And Construction Agreement, Contract Agreement for Design and Construction
Monthly Progress Reports. During the Construction Period, the Concessionaire shall, no later than 7 10 (seventen) days after the close of each month, furnish to the Authority and the Independent Authority’s Engineer a monthly report on the progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent Authority’s Engineer.
Appears in 2 contracts
Monthly Progress Reports. During the Construction Period, the Concessionaire shall, no later than 7 (seven) days after the close of each month, furnish to the Authority Lead ULB and the Independent Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent Engineer.
Appears in 2 contracts
Samples: Model Concession Agreement, Model Concession Agreement
Monthly Progress Reports. During the Construction Period, the Concessionaire shall, submit monthly reports to the Independent Engineer (with a copy to the Authority), no later than [7 (seven) )] days after the close end of each month, furnish to which should set out the Authority and the Independent Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent Engineer.following:
Appears in 2 contracts
Samples: Concession Agreement, Concession Agreement
Monthly Progress Reports. During the Construction Period, the Concessionaire Contractor shall, no later than 7 10 (seventen) days after the close of each month, furnish to the Authority and the Independent Authority’s Engineer a monthly report re- port on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent Authority’s Engineer.
Appears in 1 contract
Samples: Draft Contract Agreement
Monthly Progress Reports. During the Construction Period, the Concessionaire shall, no later than 7 (seven) days after the close of each month, furnish to the Concessioning Authority and the Independent Engineer a monthly report on progress of the Construction Works at Project Site and shall promptly give such other relevant information as may be required by the Independent Engineer.
Appears in 1 contract
Samples: Draft Concession Agreement
Monthly Progress Reports. During the Construction Period, the Concessionaire Contractor shall, no later than 7 10 (seventen) days after the close of each month, furnish to the Authority and the Independent Authority's Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent Authority's Engineer.. The Contractor agrees that reporting under this Clause 11.7 shall continue until the date of the completion of the Works. Each report shall include:
Appears in 1 contract
Samples: Draft Contract Agreement
Monthly Progress Reports. During the Construction Period, the Concessionaire shall, no later than 7 (seven) days after the close of each month, furnish to the Authority and the Independent Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent EngineerEngineer and/or the Authority.
Appears in 1 contract
Samples: Draft Concession Agreement
Monthly Progress Reports. During the Construction Period, the Concessionaire shall, no later than 7 (seven) days after the close of each month, furnish to the Authority GOTN, HD and the Independent Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent Engineer.
Appears in 1 contract
Samples: Concession Agreement
Monthly Progress Reports. During the Construction Period, the Concessionaire shall, no later than 7 (seven) days after the close of each monthquarter, furnish to the Authority and the Independent Engineer Supervision Committee constituted under Article 23 of this Agreement, a monthly quarterly report on the progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent EngineerSupervision Committee.
Appears in 1 contract
Samples: Iii Concession Agreement
Monthly Progress Reports. During the Construction Period, the Concessionaire Contractor shall, no later than 7 10 (seventen) days after the close of each month, furnish to the Authority Employer and the Independent Employer‟s Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent Employer‟s Engineer.
Appears in 1 contract
Monthly Progress Reports. During the Construction Period, the Concessionaire shall, no later than 7 (seven) days after the close of each month, furnish to the Authority Independent Engineer, the Project Manager and the Independent Engineer a Secretary, Agriculture Supply & Prices Department, Government of Sindh and PPP Unit of Finance Department, monthly report reports on the progress of the Construction Works and shall promptly give such other relevant information as may be reasonably required by the Independent Engineer.
Appears in 1 contract
Samples: Concession Agreement
Monthly Progress Reports. During the Construction Period, the Concessionaire shall, no later than 7 (seven) days after the close of each month, furnish to the Authority and the Independent Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent EngineerAuthority.
Appears in 1 contract
Samples: Draft Concession Agreement
Monthly Progress Reports. During the Construction Period, the Concessionaire Contractor shall, no later than 7 10 (seventen) days after the close of each month, furnish to the Authority and the Independent Authority’s Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent Authority’s Engineer.. The Contractor agrees that reporting under this Clause 11.7 shall continue until the date of the completion of the Works. Each report shall include: Improvement and widening to two lane with paved shoulder of road from Km 21.100 to Km
Appears in 1 contract
Samples: Draft Contract Agreement
Monthly Progress Reports. During the Construction Period, the Concessionaire Contractor shall, no later than 7 10 (seventen) days after the close of each month, furnish to the Authority and the Independent Authority’s Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent Authority’s Engineer. The monthly progress reports shall include safety statistics, including details of any hazardous incidents and activities relating to environmental, resettlement and other obligations under Clauses 3.10 to 3.14.
Appears in 1 contract
Samples: Draft Contract Agreement
Monthly Progress Reports. During the Construction Period, the Concessionaire shall, no later than 7 10 (seventen) days after the close of each month, furnish to the Authority and the Independent Authority‟s Engineer a monthly report on the progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent Authority‟s Engineer.
Appears in 1 contract
Samples: Concession Agreement
Monthly Progress Reports. During the Construction Period, the Concessionaire shall, no later than 7 (seven) days after the close of each month, furnish to the Authority / SSNNL / FED and the Independent Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent Engineer. The Independent Engineer shall review the monthly progress report furnished by the Concessionaire and sent its comments/ observations thereon to the Authority / SSNNL / FED and the Concessionaire within 7 (seven) days of receipt of such report.
Appears in 1 contract
Samples: Concession Agreement
Monthly Progress Reports. During the Construction Period, the Concessionaire shall, no not later than 7 (seven) days after the close of each month, furnish to the Authority MPRDC and the Independent Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent Engineer.
Appears in 1 contract
Samples: Concession Agreement
Monthly Progress Reports. During the Construction Period, the Concessionaire DEVELOPER shall, no later than 7 (seven) days after the close of each month, furnish to the Authority SH&DB and the Independent Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent Engineer.
Appears in 1 contract
Samples: Agreement
Monthly Progress Reports. 13.1.1 During the Construction Period, the Concessionaire shall, no later than 7 (seven) days after the close of each month, furnish to the Authority and the Independent Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent EngineerAuthority.
Appears in 1 contract
Samples: Escrow Agreement
Monthly Progress Reports. During the Construction Period, the Concessionaire Developer shall, no later than 7 (seven) days after the close of each month, furnish to the Authority SH&DB and the Independent Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent Engineer.
Appears in 1 contract
Samples: Agreement
Monthly Progress Reports. During the Construction Period, the Concessionaire shall, no later than 7 (seven) days after the close of each month, furnish to the Authority Independent Engineer and the Independent Engineer Authority a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent Engineer.
Appears in 1 contract
Samples: Concession Agreement
Monthly Progress Reports. During the Construction Period, the Concessionaire Contractor shall, no later than 7 10 (seventen) days after the close of each month, furnish to the Authority and the Independent Authority’s Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent Engineer.Authority’sEngineer. The Contractor agrees that reporting under this Clause 11.7 shall continue until the date of the completion of the Works. Each report shall include:
Appears in 1 contract
Samples: nhidcl.com
Monthly Progress Reports. During the Construction Period, the Concessionaire Contractor shall, no later than 7 10 (seventen) days after the close of each month, furnish to the Authority and the Independent Authority’s Engineer a monthly report on the progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent Authority’s Engineer.
Appears in 1 contract