MATERIALS AND TESTS. 12.1 Further to the requirements of Article 3.3 of this Contract, all materials, plant and workmanship shall be: a.- of the respective kinds described in the Contract; and b.- subjected to tests as detailed in the Technical Specification. 12.2 UNICEF may request additional tests at anytime. Such tests may be performed on site, at the place of manufacture or at such other place as may be specified or agreed by UNICEF. The Contractor shall provide all necessary assistance for obtaining the samples for testing, and shall provide the samples and carry out the testing at his own cost. UNICEF may at its own discretion take samples and carry out tests in addition to those done by the Contractor.
Appears in 2 contracts
Sources: Construction Contract, Contract for Construction Works
MATERIALS AND TESTS. 12.1 Further to the requirements of Article 3.3 of this Contract, all materials, plant and workmanship shall be: a.- :
a. of the respective kinds described in the Contract; and b.- and
b. subjected to tests as detailed in the Technical Specification.
12.2 UNICEF may request additional tests at anytime. Such tests may be performed on site, at the place of manufacture or at such other place as may be specified or agreed by UNICEF. The Contractor shall provide all necessary assistance for obtaining the samples for testing, and shall provide the samples and carry out the testing at his own cost. UNICEF may at its own discretion take samples and carry out tests in addition to those done by the Contractor.
Appears in 1 contract
Sources: Contract for Construction Works