Common use of Logic Clause in Contracts

Logic. Schedule shall use retained logic during the development and updating of the schedule. Any function that would cause the retained logic of the logic network to be overridden is prohibited unless approved, in writing and in advance, by the Architect and Owner. Schedule shall include date of Notice to Proceed, date of Substantial Completion, and date of Final Completion in accordance with Contract Documents. Critical path shall be clearly indicated on Schedule. Not more than twenty (20) percent of the progress activities shall be on the critical path at any one time. Not more than five (5) percent of the total individual activities may exceed $25,000 or 14 calendar days (per activity) without prior approval of Architect and Owner.

Appears in 5 contracts

Samples: Flexible Services Contract, Flexible Services Contract, Flexible Services Contract

AutoNDA by SimpleDocs
Time is Money Join Law Insider Premium to draft better contracts faster.