Loading Docks. 3.1 Saw cut and remove concrete in lot area for new pour in front of docks. Modify the building steel in order to install 3 dock doors. Form and pour concrete for 3 dock ramps to match existing ramps. Provide and install 3 new dock doors and levelers, with 3 dock pad sets. Fabricate and install handrails on the dock ramps. 3.2 Breakdown ● Concrete: $227,231.00 ● Steelwork: Material: $80,082.00 Labor: $84,786.00 TOTAL: $392,099.00