Liquidated Damage Amounts. A. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty dollars ($250.00) for each Day that expires after the time specified herein for Contractor to achieve Substantial Completion of the entire Work, until achieved.
Appears in 2 contracts
Samples: Document 00 5200 Agreement, Document 00 5200 Construction Agreement
Liquidated Damage Amounts. A. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty dollars ($250.00) for each Day that expires after the time specified herein for Contractor to achieve Substantial Completion of the entire Work, until achieved.achieved.
Appears in 2 contracts
Samples: Construction Agreement Document 00 5200, Laney College Doors Upgrade
Liquidated Damage Amounts. A. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty five hundred dollars ($250.00500.00) for each Day that expires after the time specified herein for Contractor to achieve Substantial Completion of the entire Work, until achieved.
Appears in 2 contracts
Samples: 5200 Agreement, Document 00 5200 Agreement
Liquidated Damage Amounts. A. 4.1.1. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty dollars One Thousand Dollars ($250.001000.00) for each Day that expires after the time specified herein for Contractor to achieve Substantial Completion of the entire Work, until achieved.
Appears in 2 contracts
Samples: Document 00520, Document 00520
Liquidated Damage Amounts. A. 4.1.1. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty dollars Two Thousand Dollars ($250.002000) for each Day that expires after the time specified herein for Contractor to achieve Substantial Completion of the entire Work, until achieved.
Appears in 1 contract
Samples: Construction Agreement
Liquidated Damage Amounts. A. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty One thousand nine hundred dollars ($250.001,900.00) for each Day that expires after the time specified herein for Contractor to achieve Substantial Final Completion of the entire Work, until achieved.
Appears in 1 contract
Samples: Document 00 5200 Agreement
Liquidated Damage Amounts. A. 4.1.1. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty dollars Two Hundred Fifty Dollars ($250.00250) for each Day that expires after the time specified herein for Contractor to achieve Substantial Completion of the entire Work, until achieved.
Appears in 1 contract
Samples: Construction Agreement
Liquidated Damage Amounts. A. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty one thousand dollars ($250.001,000.00) for each Day that expires after the time specified herein for Contractor to achieve Substantial Completion of the entire Work, until achieved.achieved.
Appears in 1 contract
Samples: Agreement
Liquidated Damage Amounts. A. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty five thousand dollars ($250.005,000.00) for each Day day that expires after the time specified herein for Contractor to achieve Substantial Completion of the entire Work, until achieved.
Appears in 1 contract
Samples: Document 00 52 00 Agreement
Liquidated Damage Amounts. A. 4.1.1. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty dollars One Thousand Dollars ($250.001000.00) for each Day that expires after the time specified herein for Contractor to achieve Substantial Completion of the entire Work, until achieved.achieved.
Appears in 1 contract
Samples: Document 00520
Liquidated Damage Amounts. A. 4.1.1. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty dollars Five Hundred Dollars ($250.00500) for each Day that expires after the time specified herein for Contractor to achieve Substantial Completion of the entire Work, until achieved.
Appears in 1 contract
Samples: Document 00520
Liquidated Damage Amounts. A. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty five hundred dollars ($250.00500.00) for each Day that expires after the time specified herein for Contractor to achieve Substantial Final Completion of the entire Work, until achieved.
Appears in 1 contract
Samples: Document 00 5200 Agreement
Liquidated Damage Amounts. A. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty Five Hundred dollars ($250.00500.00) for each Day that expires after the time specified herein for Contractor to achieve Substantial Final Completion of the entire Work, until achieved.
Appears in 1 contract
Samples: Construction Services Agreement
Liquidated Damage Amounts. A. As liquidated damages for delay Contractor shall pay Owner two five hundred-fifty dollars ($250.00500.00) for each Day that expires after the time specified herein for Contractor to achieve Substantial Completion of the entire Work, until achieved.
Appears in 1 contract
Samples: Construction Agreement
Liquidated Damage Amounts. A. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty Five Hundred dollars ($250.00500.00) for each Day that expires after the time specified herein for Contractor to achieve Substantial Completion of the entire Work, until achieved.
Appears in 1 contract
Samples: Construction Services Agreement
Liquidated Damage Amounts. A. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty hundred dollars ($250.00200.00) for each Day that expires after the time specified herein for Contractor to achieve Substantial Completion of the entire Work, until achieved.
Appears in 1 contract
Samples: Construction Services Agreement