Common use of Lien Claims Clause in Contracts

Lien Claims. Obtain from the General Contractor the negotiation of settlements with all material mechanics, materialmen and subcontractors, and if any mechanic’s, materialman’s or similar lien and/or stop notices are filed with respect to the Project, take such action (short of instituting legal proceedings) which is within the power of Development Manager, or cause the General Contractor to take such lawful action, as is appropriate to contest or settle and discharge such lien or liens and/or stop notices and to remove the same by bonding or otherwise within thirty (30) days after receiving notice of the filing thereof.

Appears in 4 contracts

Samples: Lease Agreement (Skechers Usa Inc), Development Management Agreement (Skechers Usa Inc), Limited Liability Company Agreement (Skechers Usa Inc)

AutoNDA by SimpleDocs
Time is Money Join Law Insider Premium to draft better contracts faster.