IRREGULAR PROPOSALS. (June 20, 2017 APWA GSP) 1. A Proposal will be considered irregular and will be rejected if: a. The Bidder is not prequalified when so required; b. The authorized Proposal form furnished by the Contracting Agency is not used or is altered; c. The completed Proposal form contains any unauthorized additions, deletions, alternate Bids, or conditions; d. The Bidder adds provisions reserving the right to reject or accept the award, or enter into the Contract; e. A price per unit cannot be determined from the Bid Proposal; f. The Proposal form is not properly executed; g. The Bidder fails to submit or properly complete a Subcontractor list, if applicable, as required in Section 1-02.6; h. The Bidder fails to submit or properly complete an Underutilized Disadvantaged Business Enterprise Certification, if applicable, as required in Section 1-02.6; i. The Bidder fails to submit written confirmation from each UDBE firm listed on the Bidder’s completed UDBE Utilization Certification that they are in agreement with the bidder’s UDBE participation commitment, if applicable, as required in Section 1-02.6, or if the written confirmation that is submitted fails to meet the requirements of the Special Provisions; j The Bidder fails to submit UDBE Good Faith Effort documentation, if applicable, as required in Section 1-02.6, or if the documentation that is submitted fails to demonstrate that a Good Faith Effort to meet the Condition of Award was made;
Appears in 1 contract
Sources: Small Works Roster Contract
IRREGULAR PROPOSALS. (June 20January 4, 2017 2016 APWA GSP)
1. A Proposal proposal will be considered irregular and will be rejected if:
a. The Bidder is not prequalified when so required;
b. The authorized Proposal proposal form furnished by the Contracting Agency is not used or is altered;
c. The completed Proposal proposal form contains any unauthorized additions, deletions, alternate Bids, or conditions;
d. The Bidder adds provisions reserving the right to reject or accept the award, or enter into the Contract;
e. A price per unit cannot be determined from the Bid Proposal;
f. The Proposal form is not properly executed;
g. The Bidder fails to submit or properly complete a Subcontractor list, if applicable, as required in Section 1-02.6;
h. The Bidder fails to submit or properly complete an Underutilized a Disadvantaged Business Enterprise Certification, if applicable, as required in Section 1-02.6;
i. The Bidder fails to submit written confirmation from each UDBE DBE firm listed on the Bidder’s completed UDBE DBE Utilization Certification that they are in agreement with the bidder’s UDBE bidders DBE participation commitment, if applicable, as required in Section 1-02.6, or if the written confirmation that is submitted fails to meet the requirements of the Special Provisions; j The Bidder fails to submit UDBE DBE Good Faith Effort documentation, if applicable, as required in Section 1-02.6, or if the documentation that is submitted fails to demonstrate that a Good Faith Effort to meet the Condition of Award was made;
Appears in 1 contract
Sources: Amendment to Standard Specifications