Information regarding InterconnectionFacilities Clause Samples
Information regarding InterconnectionFacilities. 4.2.1 The SPD shall be required to obtain all information from the concerned authority with regard to the Interconnection Facilities as is reasonably necessary to enable it to design, install and operate all interconnection plant and apparatus on the SPD’s side of the Delivery Point to enable delivery of electricity at the Delivery Point. The transmission of power up to the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his owncost.
4.2.2 Penalties, fines and charges imposed by the NODAL RAILWAY under any statute or regulation in relation to delay in commissioning of Project shall be payable by the SPD to the extent the delay is attributable to theSPD.
4.2.3 The responsibility of getting connectivity with the transmission system up to the Interconnection Point, will lie with the SPD.The transmission of power upto the point of interconnection where the metering is done for energy accounting shall be the responsibility of the SPD at his own cost. The maintenance of Transmission system up to the designated point as per the applicable terms and conditions shall be the responsibility of the SPD. All costs and charges including but not