Implementation Documents. (a) The Borrower has, through MIDES and MINSA, adopted a Project operational manual dated April 19, 2007, satisfactory to the Bank, therein setting forth rules, methods, guidelines, standard documents and procedures for the carrying out of the relevant parts of the Project, including the following: (i) (A) the detailed description of Project implementation activities, their sequencing and the prospective timetable and benchmarks in relation thereto; and (B) the detailed institutional arrangements in respect thereof; (ii) the Project administrative, accounting, auditing, reporting, financial, procurement and disbursement procedures, including all pertinent standard documents and model contracts in relation thereto; the EMP and the IPP for the Project; the plan for the training and capacity building activities under the Project;
Appears in 1 contract
Sources: Loan Agreement
Implementation Documents. (a) The Borrower hasBorrower, through MIDES and MINSA, adopted shall adopt, not later than the Effective Date, a Project operational manual dated April 19, 2007, satisfactory to the Bank, therein setting forth rules, methods, guidelines, standard documents and procedures for the carrying out of the relevant parts of the Project, including the following:
(i) (A) the detailed description of Project implementation activities, their sequencing and the prospective timetable and benchmarks in relation thereto; and (B) the detailed institutional arrangements in respect thereof;
(ii) the Project administrative, accounting, auditing, reporting, financial, procurement and disbursement procedures, including all pertinent standard documents and model contracts in relation thereto; ;
(iii) the EMP EMF, the RPF and the IPP for the Project; the plan for the training and capacity building activities under the Project;
Appears in 1 contract
Sources: Loan Agreement
Implementation Documents. (a) The Borrower hasBorrower, through MIDES and MINSA, adopted shall adopt, not later than the Effective Date, a Project operational manual dated April 19, 2007, satisfactory to the Bank, therein setting forth rules, methods, guidelines, standard documents and procedures for the carrying out of the relevant parts of the Project, including the following:
(i) (A) the detailed description of Project implementation activities, their sequencing and the prospective timetable and benchmarks in relation thereto; and (B) the detailed institutional arrangements in respect thereof;
(ii) the Project administrative, accounting, auditing, reporting, financial, procurement and disbursement procedures, including all pertinent standard documents and model contracts in relation thereto; ;
(iii) the EMP EMF, the RPF and the IPP for the Project; ;
(iv) the plan for the training and capacity building activities under the Project;
Appears in 1 contract
Sources: Loan Agreement