H4 Consequences of Expiry or Termination. H4.1 Where the Authority terminates the Contract under clause H2 (Termination on Default) and then makes other arrangements for the supply of Services, the Authority may recover from the Contractor the cost reasonably incurred of making those other arrangements and any additional expenditure incurred by the Authority throughout the remainder of the Contract Period. The Authority shall take all reasonable steps to mitigate such additional expenditure. Where the Contract is terminated under clause H2 (Termination on Default), no further payments shall be payable by the Authority to the Contractor until the Authority has established the final cost of making those other arrangements.
Appears in 15 contracts
Samples: Agreement, Final Contract, Contract Document
H4 Consequences of Expiry or Termination. H4.1 Where the Authority terminates the Contract under clause H2 (Termination on Default) and then makes other arrangements for the supply of Services, the Authority may recover from the Contractor Provider the cost reasonably incurred of making those other arrangements and any additional expenditure incurred by the Authority throughout the remainder of the Contract Period. The Authority shall take all reasonable steps to mitigate such additional expenditure. Where the Contract is terminated under clause H2 (Termination on Default), no further payments shall be payable by the Authority to the Contractor Provider until the Authority has established the final cost of making those other arrangements.
Appears in 14 contracts
Samples: data.gov.uk, data.gov.uk, data.gov.uk
H4 Consequences of Expiry or Termination. H4.1 Where the Authority terminates the Contract under clause H2 (Termination on Default) and then makes other arrangements for the supply of Services, the Authority may recover from the Contractor the cost reasonably incurred of making those other arrangements and any additional expenditure incurred by the Authority throughout the remainder of the Contract Period. The Authority shall take all reasonable steps to mitigate such additional expenditure. Where the Contract is terminated under clause H2 (Termination on Default)H2, no further payments shall be payable by the Authority to the Contractor until the Authority has established the final cost of making those other arrangements.
Appears in 1 contract
Samples: Contract
H4 Consequences of Expiry or Termination. H4.1 Where the Authority terminates the Contract under clause H2 (Termination on Default) and then makes other arrangements for the supply of Services, the Authority may recover from the Contractor the cost reasonably incurred of making those other arrangements and any additional expenditure incurred by the Authority throughout the remainder of the Contract Period. The Authority shall take all reasonable steps to mitigate such additional expenditure. Where the Contract is terminated under clause H2 (Termination on Default)H2, no further payments shall be payable by the Authority to the Contractor (for Services supplied by the Contractor prior to termination and in accordance with the Contract but where the payment has yet to be made by the Authority), until the Authority has established the final cost of making those the other arrangementsarrangements envisaged under this clause.
Appears in 1 contract
Samples: Non Disclosure Agreement