– Functional and Performance Testing. Upon completion of Installation Testing, Consultant will coordinate with the ▇▇▇▇ and STMWRF Operations personnel to perform control system functional testing of the new improvements. The first phase of Functional Testing will be to test the control and monitoring of equipment in Local control mode. Once this step is completed, the new unit processes/equipment will be placed into Remote Auto mode for Performance Testing. Performance Testing will consist of Consultant working with Plant Operations personnel to demonstrate that unit process monitoring and control is consistent with the Loop Descriptions before it is deemed fully functional. Fine tuning of loops and adjustments of unit process displays and controls should be expected during this period. Consultant has budgeted for 4 days on-site to complete the functional testing and performance testing of Consultant-developed programming logic.