FORCE ACCOUNT WORK Sample Clauses

FORCE ACCOUNT WORK. Work, ordered in writing by Metro, for which Contractor must report its actual costs in accordance with Section 8.4 of the General Conditions.
FORCE ACCOUNT WORK. 8.4.1 If Contractor does not respond to Metro's Request for Proposal with a cost breakdown within the fourteen (14)-day period as required above, or if Metro determines that Contractor's breakdown of costs is unreasonable in consideration of the Work proposed to be added or deleted, or if Metro determines that the proposed Work must be commenced promptly to avoid delay to the Project, Metro may issue an order for Force Account Work and Contractor shall promptly perform or delete the Work described in such order. Change, if any, in the Contract Amount due to such Force Account Work shall be the sum total of the following items:
FORCE ACCOUNT WORK. A Force Account may be used at the County’s discretion and only when either 1) agreement on the valuation of a change cannot be made using the methods described in the preceding paragraph, County Ordered Changes in the Work, or 2) the County cannot firmly establish an applicable and acceptable estimate for the cost of the work because the level of effort necessary to perform and complete the work cannot be reasonably estimated or anticipated but can only be determined by performing the work. Because of the significant burden on the County to monitor and control the work, Force Account work is not a preferred method, and it shall be the responsibility of the Contractor to provide all necessary documentation and justification of costs. The rates for labor, equipment and materials to be used in cases of work performed on a force account basis will be compensated as documented below. No costs other than those explicitly listed below shall be allowed:
FORCE ACCOUNT WORK. 7.13.1 If no agreement can be reached on Changes in the Work and adjustment of the Contract Price or Contract Time, or the Design-Builder refuses to accept a Change Notice, Change Order, or Time and Material Change Order, the City shall have the right to have the work in question done by Persons other than the Design-Builder.
FORCE ACCOUNT WORK. 14.3 If an order to change Work, deletes Work which is to be performed hereunder and such deletion results in a substantial reduction, in the opinion of Company, in the labor or materials to be furnished by Contractor hereunder then such reduction in Work shall be considered "Omitted Work" and Company shall be entitled to a reduction in the compensation to be paid Contractor as provided in Article 18.
FORCE ACCOUNT WORK. When the Contractor is required to perform work as a result of or alleged by the Contractor to be an addition or change to the contract for which there are no applicable unit prices in the contract, MSA and Contractor shall attempt to agree upon a price for the performance of such work. If an agreement cannot be reached, MSA may require the Contractor to do such work on a force account basis to be compensated as follows:
AutoNDA by SimpleDocs
FORCE ACCOUNT WORK. The term “Force Account Work” means Change Order Work for Time & Material (T&M) that occurs when the entire cost of the proposed change cannot be estimated. In this case, Design Build Entity is to track its time spent working on the change, as well as any costs associated with needed materials or equipment.
FORCE ACCOUNT WORK. The Contractor’s attention is directed to the City of Durham Water and Sewer Construction Specifications for information on the method of payment for the performance of extra work on City contracts. Prior to starting work, the Contractor shall submit information on labor wage rates and equipment rates for all labor and equipment to be used in the performance of the Work in accordance with the Water and Sewer Construction Specifications. These rates shall be used to compensate the Contractor for all force account work on the project. The Contractor shall only be compensated for labor and equipment used in the performance of extra work for force account work at the labor wage rates and equipment rates submitted. There shall be no adjustments to the rates submitted and no compensation for idle equipment in accordance with the Construction Specifications.
FORCE ACCOUNT WORK. Xxxxxx negotiated and agreed upon by the Authority and the Contractor under this Section 111.3.2 may be added to the Schedule of Values by Change Order if it is reasonably foreseeable that the Work will be of a recurring nature and such Work shall thereafter be deemed as Pre-Priced Work subject to the provisions of Section 111.3.1 of these General Provisions.