Final Commissioning Program Clause Samples
Final Commissioning Program. (a) Project Co shall prepare a draft of the Final Commissioning Program in respect of the Project Co Commissioning and the CTC Commissioning and shall provide a copy thereof to the Independent Certifier, the CTC Commissioning Consultant and the CTC Representative not less than 365 days prior to the Scheduled Substantial Completion Date.
(b) The Final Commissioning Program shall, at a minimum:
(i) describe the requirements, and the timing and sequence of such requirements, necessary in order that the Project Co Commissioning shall be completed to achieve:
(A) Substantial Completion on or before the Scheduled Substantial Completion Date; and
(B) Final Completion on or before the Scheduled Final Completion Date;
(ii) describe the requirements, and the timing and sequence of such requirements, of the CTC Commissioning activities;
(iii) comply with all requirements of the Outline Commissioning Program and include all details, including for all appendices, required to be completed in the Outline Commissioning Program;
(iv) be consistent with the Outline Commissioning Program and impose no greater or more onerous obligations on the CTC than those set out in the Outline Commissioning Program, unless otherwise agreed to by the CTC;
(v) include the names of the individuals or companies proposed to perform all Project Co Commissioning;
(vi) include a schedule of each of the Project Co Commissioning Tests and the CTC Commissioning Tests proposed to be performed and the timeframe for completion, with start and end dates;
(vii) include a schedule of meetings to be held between the Parties to coordinate the performance of the Project Co Commissioning and the CTC Commissioning;
(viii) provide for the re-verification of systems following the CTC Commissioning; and
(ix) list the approvals required from any Governmental Authority, manufacturer or other person that are necessary to meet the requirements of the Final Commissioning Program or Applicable Law.
(c) The CTC shall provide Project Co with comments on the draft Final Commissioning Program in accordance with the procedures contemplated by Section 4.1 of Schedule 10 – Review Procedure, and Project Co shall revise the draft Final Commissioning Program to the extent contemplated by Schedule 10 – Review Procedure within 30 days of receipt of any comments from the CTC.
(d) When agreed by the Parties, the Final Commissioning Program shall replace the Outline Commissioning Program.
Final Commissioning Program. Project Co shall prepare a draft of the Final Commissioning Program in respect to the Project Co Commissioning and the Hospital Commissioning and shall provide a copy thereof to the Independent Certifier, the WCH Commissioning Agent and the WCH Representative not less than 365 days prior to the Scheduled Substantial Completion Date.
Final Commissioning Program. (a) Project Co shall prepare a draft of the Final Commissioning Program and shall provide a copy thereof to the Independent Certifier, the IO Commissioning Agent and the IO Representative not less than 365 days prior to the Scheduled Substantial Completion Date.
(b) The Final Commissioning Program shall:
(i) describe the requirements, and the timing and sequence of such requirements, necessary in order that the Project Co Commissioning shall be completed to achieve:
(A) Substantial Completion on or before the Scheduled Substantial Completion Date; and
(B) Final Completion on or before the Scheduled Final Completion Date;
(ii) describe the requirements, and the timing and sequence of such requirements, of the IO Commissioning activities;
(iii) comply with all requirements of the Outline Commissioning Program and include all details, including for all appendices, required to be completed in the Outline Commissioning Program;
Final Commissioning Program. (a) Project Co shall prepare a draft of the Final Commissioning Program in respect of the Project Co Commissioning and the College Commissioning and shall provide a copy thereof to the Independent Certifier, the College Commissioning Consultant and the College Representative not less than 540 days prior to the Scheduled Substantial Completion Date with a view to finalizing the Final Commissioning Program pursuant to the provisions of this Section 24.2 not less than 365 days prior to the Scheduled Substantial Completion Date.
(b) The Final Commissioning Program shall, at a minimum:
(i) describe the requirements, and the timing and sequence of such requirements, necessary in order that the Project Co Commissioning shall be completed to achieve:
(A) Substantial Completion on or before the Scheduled Substantial Completion Date; and
(B) Final Completion on or before the Scheduled Final Completion Date;
(ii) describe the requirements, and the timing and sequence of such requirements, of the College Commissioning activities;
(iii) comply with all requirements of the Outline Commissioning Program and include all details, including for all appendices, required to be completed in the Outline Commissioning Program;
Final Commissioning Program. (a) Project Co shall prepare a draft of the Final Commissioning Program in respect of the Project Co Commissioning and the HMQ Commissioning and shall provide a copy thereof to the Independent Certifier, the HMQ Commissioning Agent and the HMQ Representative not less than 365 days prior to the Scheduled Substantial Completion Date.
(b) The Final Commissioning Program shall:
(i) describe the requirements, and the timing and sequence of such requirements, necessary in order that the Project Co Commissioning shall be completed to achieve:
(A) Substantial Completion on or before the Scheduled Substantial Completion Date; and
(B) Final Completion on or before the Scheduled Final Completion Date;
(ii) describe the requirements, and the timing and sequence of such requirements, of the HMQ Commissioning activities;
(iii) comply with all requirements of the Outline Commissioning Program and include all details, including for all appendices, required to be completed in the Outline Commissioning Program;
Final Commissioning Program. (a) Project Co shall prepare a draft of the Final Commissioning Program in respect of the Project Co Commissioning and the College Commissioning and shall provide a copy thereof to the Independent Certifier, the College Commissioning Consultant and the College Representative not less than 540 days prior to the Scheduled Substantial Completion Date with a view to finalizing the Final Commissioning Program pursuant to the provisions of this Section 24.2 not less than 365 days prior to the Scheduled Substantial Completion Date.
(b) The Final Commissioning Program shall, at a minimum:
(i) describe the requirements, and the timing and sequence of such requirements, necessary in order that the Project Co Commissioning shall be completed to achieve:
(A) Substantial Completion on or before the Scheduled Substantial Completion Date; and
(B) Final Completion on or before the Scheduled Final Completion Date;
(ii) describe the requirements, and the timing and sequence of such requirements, of the College Commissioning activities;
(iii) comply with all requirements of the Outline Commissioning Program and include all details, including for all appendices, required to be completed in the Outline Commissioning Program;