Common use of EVACUATION FACILITIES Clause in Contracts

EVACUATION FACILITIES. 4.4.1 Not later than 30 days prior to the scheduled commercial operation date of the Generation Facility, the generator under supervision of MSEDCL/MSETCL shall ensure that the construction and operation of the transmission line is completed to commence the supply of power to the Generation Facilities. MSEDCL/MSETCL when requested by the Generator shall supply power to the Generator during the following periods:

Appears in 4 contracts

Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement