Draw Request. At such time as Borrower shall desire to obtain an Advance for a particular Project, in addition to satisfying the conditions set forth in Article 12 hereof on a Project-by-Project basis, and providing to Agent and Lenders the items set forth in Section 12.5 hereof on a Project-by-Project basis, Borrower shall complete, execute and deliver to Agent, Borrower's Requisition for Advance in the form of Exhibit B attached hereto and by this reference incorporated herein (hereinafter referred to as "Borrower's Requisition for Advance"). Each Borrower's Requisition for Advance shall be accompanied by the following items in form reasonably acceptable to Agent: 3.1.1 If Borrower's Requisition for Advance includes Direct Costs to be paid to a Contractor under the applicable Construction Contract, a completed and fully itemized Application and Certificate for Payment (AIA Document G702 and G703) containing the certification of Borrower, such Contractor and the applicable Architect as to the accuracy of same, and a payment requisition and lien affidavit signed by such Contractor and Borrower, respectively, in the forms of Exhibits D and E attached hereto and by this reference incorporated herein; 3.1.2 If Borrower's Requisition for Advance includes payments for Indirect Costs in excess of the amount described in Section 2.10.1 above, a completed Indirect Cost statement executed by Borrower; 3.1.3 A Draw Request Summary for each applicable Project; 3.1.4 If Borrower's Requisition for Advance includes Project Costs under subparagraphs (b) or (c) of the definition of "Borrowing Base", a current Borrowing Base Report; 3.1.5 An affidavit and partial waiver of lien in the form of Exhibit F attached hereto and by this reference incorporated herein from the applicable Contractor and such laborers, subcontractors and materialmen for work done and materials supplied by them since the previous Draw Request; 3.1.6 An inspection report and certification from Construction Inspector, at Borrower's expense; and 3.1.7 Such other information, documentation and certification as Agent and Lenders (acting through Agent) shall reasonably request.
Appears in 2 contracts
Sources: Revolving Credit Construction Loan Agreement (Wci Communities Inc), Revolving Credit Construction Loan Agreement (Wci Communities Inc)
Draw Request. At such time as the Borrower shall desire to obtain an Advance for a particular ProjectAdvance, in addition to satisfying the conditions set forth in Article 12 hereof on a Project-by-Project basis, and providing to Agent and Lenders the items set forth in Section 12.5 hereof on a Project-by-Project basis, Borrower shall complete, execute and deliver to Agent, the Lender the Borrower's Requisition for Advance and the Funding Request Documents in the form of Exhibit B “G” attached hereto and by this reference incorporated herein (hereinafter referred to as "BorrowerBorrower's Requisition for AdvanceRequisition"). Each Borrower's Requisition shall be accompanied by:
(a) If the Borrower's Requisition includes payments for Advance Direct Costs, it shall be accompanied by a completed and itemized Direct Cost Statement in the following form of Schedule I of Exhibit “G” attached hereto, executed by the Borrower, together with invoices for all items in form reasonably acceptable to Agent:of Direct Cost covered thereby; .
3.1.1 (b) If the Borrower's Requisition for Advance includes Direct Costs amounts to be paid to a the Contractor under the applicable Construction Contract, it shall be accompanied by: (i) a completed and fully itemized Application and Certificate for Payment (AIA Document G702 and G703or similar form approved by the Lender) containing the certification of Borrower, such the Contractor and the applicable Borrower's Architect as to the accuracy of same, and a payment requisition showing all subcontractors and lien affidavit signed materialmen by such Contractor name and Borrowertrade or job, respectivelythe total amount of each subcontract or purchase order, in the forms of Exhibits D and E attached hereto and by this reference incorporated herein;
3.1.2 If Borrower's Requisition for Advance includes payments for Indirect Costs in excess amount theretofore paid to each subcontractor or materialman as of the date of such application, and the amount described in Section 2.10.1 above, a completed Indirect Cost statement executed by Borrower;
3.1.3 A Draw Request Summary for each applicable Project;
3.1.4 If Borrower's Requisition for Advance includes Project Costs under subparagraphs (b) or (c) to be paid from the proceeds of the definition Advance to each subcontractor and materialman; (ii) a certificate of "Borrowing Base", a current Borrowing Base Report;
3.1.5 An affidavit and partial waiver of lien the Contractor in the form of Exhibit F “H” attached hereto hereto; (iii) a certificate of the Borrower's Architect in the form of Exhibit “I” attached hereto; and (iv) copies of requisitions and invoices from subcontractors and materialmen supporting all items of cost covered by this reference incorporated herein such application;
(c) If the Borrower's Requisition includes payments for Indirect Costs, it shall be accompanied by a completed and itemized Indirect Cost Statement in the form of Schedule II of Exhibit “G” attached hereto, executed by the Borrower, together with invoices for all items of Indirect Costs covered thereby;
(d) written lien waivers from the applicable Contractor and such laborers, subcontractors and materialmen for work done and materials supplied by them since which were paid for pursuant to the previous next preceding Draw Request;
3.1.6 An (e) a written request of the Borrower for any necessary changes in the Plans and Specifications, the Project Budget, the Disbursement Schedule or the Construction Schedule;
(f) copies of all change orders and construction change directives, accompanied by a change order summary prepared by and executed by the Borrower, copies of all subcontracts, and, to the extent requested by the Lender, of all inspection report or test reports and certification from other documents relating to the construction of the Improvements, not previously delivered to the Lender;
(g) copy of the Construction Inspector, at Borrower's expenseInspection Report; and
3.1.7 Such (h) such other information, documentation and certification certification as Agent and Lenders (acting through Agent) the Lender shall reasonably request.
Appears in 2 contracts
Sources: Construction Loan and Security Agreement (Griffin Land & Nurseries Inc), Construction Loan and Security Agreement (Griffin Land & Nurseries Inc)
Draw Request. At such time as the Borrower shall desire to obtain an Advance for a particular ProjectAdvance, in addition to satisfying the conditions set forth in Article 12 hereof on a Project-by-Project basis, and providing to Agent and Lenders the items set forth in Section 12.5 hereof on a Project-by-Project basis, Borrower shall complete, execute and deliver to Agent, the Agent the Borrower's Requisition for Advance in the form of Exhibit B E attached hereto and by this reference incorporated herein (hereinafter referred to as "Borrower's Requisition for AdvanceRequisition"). Each Borrower's Requisition shall be accompanied by:
(a) a written notice of the Borrower specifying (i) the requested Type of Advance comprising such Advance, (ii) in the case of an Advance comprised of a LIBOR Advance, the initial Interest Period; and (iii) the amount of each Type of Advance; provided, however, that each LIBOR Advance shall be in an amount of $100,000.00 or integral multiple of $1,000.00 in excess thereof;
(b) If the Borrower's Requisition includes payments for Advance Direct Costs, it shall be accompanied by the following items a completed and itemized Direct Cost Statement in form reasonably acceptable satisfactory to the Agent:, executed by the Borrower, together with copies of invoices for all items of Direct Cost covered thereby;
3.1.1 (c) If the Borrower's Requisition for Advance includes Direct Costs amounts to be paid to a the Contractor under the applicable Construction Contract, it shall be accompanied by: (i) a completed and fully itemized Application and Certificate for Payment (AIA Document G702 and G703or similar form approved by the Agent) containing the certification of Borrower, such the Contractor and the applicable Borrower's Architect or other licensed design professional acceptable to Agent as to the accuracy of same, and a payment requisition showing all subcontractors and lien affidavit signed materialmen by such Contractor name and Borrowertrade or job, respectivelythe total amount of each subcontract or purchase order, in the forms of Exhibits D and E attached hereto and by this reference incorporated herein;
3.1.2 If Borrower's Requisition for Advance includes payments for Indirect Costs in excess amount theretofore paid to each subcontractor or materialman as of the date of such application, and the amount described in Section 2.10.1 above, a completed Indirect Cost statement executed by Borrower;
3.1.3 A Draw Request Summary for each applicable Project;
3.1.4 If Borrower's Requisition for Advance includes Project Costs under subparagraphs (b) or (c) to be paid from the proceeds of the definition Advance to each subcontractor and materialman; (ii) a certificate of "Borrowing Base", a current Borrowing Base Report;
3.1.5 An affidavit and partial waiver of lien the Contractor in the form of Exhibit F attached hereto; (iii) a certificate of the Borrower's Architect or other licensed design professional acceptable to Agent in the form of Exhibit G attached hereto or such other form as the Agent may approve; and (iv) copies of requisitions and invoices from subcontractors and materialmen supporting all items of cost covered by this reference incorporated herein from such application;
(d) If the applicable Borrower's Requisition includes payments for Indirect Costs, it shall be accompanied by a completed and itemized Indirect Cost Statement in form satisfactory to the Agent, executed by the Borrower, together with copies of invoices for all items of Indirect Costs covered thereby;
(e) written lien waivers executed by the Contractor and such laborers, subcontractors and materialmen whose contract(s) for the provision of services or materials for construction of the Project requires payment in excess of $50,000.00, for work done and materials supplied by them since such Person which were paid for pursuant to the previous next preceding Draw RequestRequest in form acceptable to Agent, which form shall, to the extent permitted by applicable law, contain lien subordinations from the Contractor and each such laborer, subcontractor and materialman;
3.1.6 An (f) a written request of the Borrower for any necessary changes in the Plans and Specifications, the Project Budget, the Disbursement Schedule or the Construction Schedule;
(g) copies of all change orders and construction change directives, accompanied by a change order summary prepared by and executed by the Borrower, copies of all subcontracts involving work in the amount of $100,000.00 or more (if requested by the Agent), and, to the extent requested by the Agent or the Majority Banks, of all inspection report or test reports and certification from Construction Inspectorother documents relating to the construction of the Improvements, at Borrower's expensenot previously delivered to the Agent; and
3.1.7 Such (h) If the Borrower's Requisition includes payment for Stored Materials, it shall be accompanied by evidence as to the satisfaction of the requirements set forth in Section 2.8 hereof; and
(i) such other information, documentation and certification as the Agent and Lenders (acting through Agent) or the Majority Banks shall reasonably request. Each Draw Request shall constitute a representation and warranty by the Borrower that all of the conditions set forth in this Agreement to such Advance, including, without limitation, Section 11, have been satisfied on the date of such Draw Request.
Appears in 2 contracts
Sources: Construction Loan Agreement (Walden Residential Properties Inc), Construction Loan Agreement (Walden Residential Properties Inc)
Draw Request. At such time as Borrower shall desire to obtain an Advance for a particular Project, in addition to satisfying the conditions set forth in Article 12 hereof on a Project-by-Project basis, and providing to Agent and Lenders the items set forth in Section 12.5 hereof on a Project-by-Project basisAdvance, Borrower shall complete, execute and deliver to Agent, Agent “Borrower's Requisition for Advance ’s Requisition” in the form of Exhibit B D attached hereto hereto. Advances shall be in minimum increments of at least $500,000.00, except for the initial Advance made on the date of this Agreement and by the final Advance made pursuant to the terms of this reference incorporated herein (hereinafter referred to as "Borrower's Requisition for Advance")Agreement, each of which may be in a lesser amount. Each Borrower's ’s Requisition for Advance shall be accompanied by the following items in form reasonably acceptable to Agentby:
3.1.1 (a) If Borrower's ’s Requisition includes payments for Advance Direct Costs, a completed and itemized Direct Cost Statement in the form of Schedule I of Exhibit D attached hereto, executed by Borrower, together with invoices for all items of Direct Cost covered thereby;
(b) If Borrower’s Requisition includes Direct Costs amounts to be paid to a Contractor the applicable Person under the applicable Construction Contract, Construction-Related Contracts: (i) a completed and fully itemized Application and Certificate for Payment (AIA Document G702 and G703or similar form approved by Lender) containing the certification of Borrower, such the Contractor and the applicable Architect as to the accuracy of same, and ; (ii) a payment requisition and lien affidavit signed by such Contractor and Borrower, respectively, in the forms of Exhibits D and E attached hereto and by this reference incorporated herein;
3.1.2 If Borrower's Requisition for Advance includes payments for Indirect Costs in excess certificate of the amount described in Section 2.10.1 above, a completed Indirect Cost statement executed by Borrower;
3.1.3 A Draw Request Summary for each applicable Project;
3.1.4 If Borrower's Requisition for Advance includes Project Costs under subparagraphs (b) or (c) of the definition of "Borrowing Base", a current Borrowing Base Report;
3.1.5 An affidavit and partial waiver of lien Contractor in the form of Exhibit F E attached hereto hereto; and by this reference incorporated herein (iii) copies of requisitions and invoices from the applicable Contractor and such laborers, subcontractors and materialmen for work done and materials supplied supporting all items of cost covered by them since the previous Draw Requestsuch application;
3.1.6 An (c) If Borrower’s Requisition includes payments for Indirect Costs, it shall be accompanied by a completed and itemized Indirect Cost Statement in the form of Schedule II of Exhibit D attached hereto, executed by Borrower, together with invoices for all items of Indirect Costs covered thereby; provided that, with respect to Advances for the payment of interest due under the Loan, Borrower hereby requests that Agent and Lenders make an Advance for such amount on each date such payment is due, and provided there is no Default or Event of Default, each Lender shall make such Advance to Agent for the payment of interest due under the Loan. The provisions of this Section 3.1(c) shall not limit Borrower’s absolute and unconditional obligation to pay such interest regardless of whether Loan proceeds are available or advanced therefor.
(d) If requested by Agent, an accurately completed and valid partial waiver and subordination of lien (hereinafter, the “Lien Form”) in the form required by applicable law, executed by the applicable Contractor, subcontractors, laborers and materialmen such Lien Form to provide that subject to the payment of the amount set forth in Borrower’s Requisition, the Contractor waives any and all lien rights for labor and materials, or rental equipment, appliances or tools, performed or furnished through the last day of the period ending on the date designated in the Lien Form (hereinafter, the “Payment Period Date”), except for Retainage, unpaid agreed or pending change orders, and disputed claims as stated in the Lien Form;
(e) Copies of all change orders and construction change directives, accompanied by a change order summary prepared by and executed by Borrower, copies of all subcontracts, and, to the extent requested by Agent, of all inspection report or test reports and certification from Construction Inspectorother documents relating to the construction of the Improvements, at not previously delivered to Agent;
(f) If Borrower's expense’s Requisition includes payment for Stored Materials, it shall be accompanied by evidence as to the satisfaction of the requirements set forth in Section 2.7 hereof; and
3.1.7 (g) Such other information, documentation and certification as Agent and Lenders (acting through Agent) shall reasonably request. Each Draw Request shall constitute a representation and warranty by Borrower as of the date of such Draw Request that all of the conditions set forth in this Agreement to such Advance, including, without limitation, as applicable, Section 13, have been in all material respects satisfied on the date of such Draw Request.
Appears in 1 contract
Sources: Construction Loan Agreement (CNL Growth Properties, Inc.)
Draw Request. At such time as the Borrower shall desire to obtain an Advance for a particular ProjectAdvance, in addition to satisfying the conditions set forth in Article 12 hereof on a Project-by-Project basis, and providing to Agent and Lenders the items set forth in Section 12.5 hereof on a Project-by-Project basis, Borrower shall complete, execute and deliver to Agent, the Lender the Borrower's ’s Requisition for Advance and the Funding Request Documents in the form of Exhibit B “G” attached hereto and by this reference incorporated herein (hereinafter referred to as "“Borrower's Requisition for Advance"’s Requisition”). Each Borrower's ’s Requisition shall be accompanied by:
(a) If the Borrower’s Requisition includes payments for Advance Direct Costs, it shall be accompanied by a completed and itemized Direct Cost Statement in the following form of Schedule I of Exhibit “G” attached hereto, executed by the Borrower, together with invoices for all items in form reasonably acceptable to Agent:of Direct Cost covered thereby; .
3.1.1 (b) If the Borrower's ’s Requisition for Advance includes Direct Costs amounts to be paid to a the Contractor under the applicable Construction Contract, it shall be accompanied by: (i) a completed and fully itemized Application and Certificate for Payment (AIA Document G702 and G703or similar form approved by the Lender) containing the certification of Borrower, such the Contractor and the applicable Borrower’s Architect as to the accuracy of same, and a payment requisition showing all subcontractors and lien affidavit signed materialmen by such Contractor name and Borrowertrade or job, respectivelythe total amount of each subcontract or purchase order, in the forms of Exhibits D and E attached hereto and by this reference incorporated herein;
3.1.2 If Borrower's Requisition for Advance includes payments for Indirect Costs in excess amount theretofore paid to each subcontractor or materialman as of the date of such application, and the amount described in Section 2.10.1 above, a completed Indirect Cost statement executed by Borrower;
3.1.3 A Draw Request Summary for each applicable Project;
3.1.4 If Borrower's Requisition for Advance includes Project Costs under subparagraphs (b) or (c) to be paid from the proceeds of the definition Advance to each subcontractor and materialman; (ii) a certificate of "Borrowing Base", a current Borrowing Base Report;
3.1.5 An affidavit and partial waiver of lien the Contractor in the form of Exhibit F “H” attached hereto hereto; (iii) a certificate of the Borrower’s Architect in the form of Exhibit “I” attached hereto; and (iv) copies of requisitions and invoices from subcontractors and materialmen supporting all items of cost covered by this reference incorporated herein such application;
(c) If the Borrower’s Requisition includes payments for Indirect Costs, it shall be accompanied by a completed and itemized Indirect Cost Statement in the form of Schedule II of Exhibit “G” attached hereto, executed by the Borrower, together with invoices for all items of Indirect Costs covered thereby;
(d) written lien waivers from the applicable Contractor and such laborers, subcontractors and materialmen for work done and materials supplied by them since which were paid for pursuant to the previous next preceding Draw Request;
3.1.6 An (e) a written request of the Borrower for any necessary changes in the Plans and Specifications, the Project Budget, the Disbursement Schedule or the Construction Schedule;
(f) copies of all change orders and construction change directives, accompanied by a change order summary prepared by and executed by the Borrower, copies of all subcontracts, and, to the extent requested by the Lender, of all inspection report or test reports and certification from other documents relating to the construction of the Improvements, not previously delivered to the Lender;
(g) copy of the Construction Inspector, at Borrower's expenseInspection Report; and
3.1.7 Such (h) such other information, documentation and certification as Agent and Lenders (acting through Agent) the Lender shall reasonably request.
Appears in 1 contract
Sources: Construction Loan and Security Agreement (Griffin Land & Nurseries Inc)
Draw Request. At such time as the Borrower shall desire to obtain an Advance for a particular ProjectAdvance, in addition to satisfying the conditions set forth in Article 12 hereof on a Project-by-Project basis, and providing to Agent and Lenders the items set forth in Section 12.5 hereof on a Project-by-Project basis, Borrower shall complete, execute and deliver to Agent, the Lender a Borrower's Requisition for Advance in the form of Exhibit B G attached hereto and by this reference incorporated herein (hereinafter referred to as "hereto. Such Borrower's Requisition shall show the Requisition Amount for Advance"the Project Costs in question and the portion thereof being funded from Borrower's Required Equity Funds ($2,152,886). The amount of the requested Advance shall be 50% thereof until Borrower's Required Equity Funds shall have been exhausted, and thereafter, 100%. Each Borrower's Requisition for Advance shall be accompanied by the following items in form reasonably acceptable to Agentby:
3.1.1 (a) If the Borrower's Requisition includes payments for Advance Direct Costs, a completed and itemized Direct Cost Statement in the form of Schedule I of Exhibit G attached hereto, executed by the Borrower, together with invoices for all items of Direct Cost covered thereby;
(b) If the Borrower's Requisition includes Direct Costs amounts to be paid to a the Contractor under the applicable Construction Contract, : (i) a completed and fully itemized Application and Certificate for Payment (AIA Document G702 and G703or similar form approved by the Lender) containing the certification of Borrower, such the Contractor and the applicable Borrower's Architect as to the accuracy of same, and ; (ii) a payment requisition and lien affidavit signed by such Contractor and Borrower, respectively, in the forms of Exhibits D and E attached hereto and by this reference incorporated herein;
3.1.2 If Borrower's Requisition for Advance includes payments for Indirect Costs in excess certificate of the amount described in Section 2.10.1 above, a completed Indirect Cost statement executed by Borrower;
3.1.3 A Draw Request Summary for each applicable Project;
3.1.4 If Borrower's Requisition for Advance includes Project Costs under subparagraphs (b) or (c) of the definition of "Borrowing Base", a current Borrowing Base Report;
3.1.5 An affidavit and partial waiver of lien Contractor in the form of Exhibit F H attached hereto (with such changes therein as the Contractor may reasonably request, subject to the approval of the Lender which approval will not be unreasonably delayed or denied); (iii) a certificate of the Borrower's Architect in the form of Exhibit I attached hereto (with such changes therein as the Borrower's Architect may reasonably request, subject to the approval of the Lender which approval will not be unreasonably delayed or denied); and (iv) copies of requisitions and invoices from subcontractors and materialmen supporting all items of cost covered by this reference incorporated herein from such application;
(c) If the applicable Borrower's Requisition includes payments for Indirect Costs, it shall be accompanied by a completed and itemized Indirect Cost Statement in the form of Schedule II of Exhibit G attached hereto, executed by the Borrower, together with invoices for all items of Indirect Costs covered thereby;
(d) If the Borrower's Requisition includes payments for tenant improvements, it shall be accompanied by a completed and itemized Tenant Improvements Summary in the form of Exhibit J attached hereto, executed by the Borrower;
(e) If requested by the Lender or if a Section 2 Lien has been filed, an accurately completed and valid Partial Waiver and Subordination of Lien (hereinafter, the "Lien Form") in the form set forth in Chapter 254 of the Massachusetts General Laws, as amended (hereinafter, the "Mechanic's Lien Law") and as annexed hereto as Exhibit K, executed by the Contractor, such Lien Form to provide that subject to the payment of the amount set forth in the Borrower's Requisition, the Contractor waives any and such laborersall lien rights for labor and materials, subcontractors or rental equipment, appliances or tools, performed or furnished through the last day of the period ending on the date designated in the Lien Form (hereinafter, the "Payment Period Date"), except for Retainage, unpaid agreed or pending change orders, and disputed claims as stated in the Lien Form;
(f) Lien waivers in form acceptable to the Lender executed by all contractors, subcontractors, laborers and materialmen for work done and materials supplied by them since which were paid for pursuant to the previous next preceding Draw Request;
3.1.6 An (g) Copies of all change orders and construction change directives, accompanied by a change order summary prepared by and executed by the Borrower, copies of all subcontracts, and, to the extent requested by the Lender, of all inspection report or test reports and certification from Construction Inspectorother documents relating to the construction of the Improvements, at not previously delivered to the Lender;
(h) If the Borrower's expenseRequisition includes payment for Stored Materials, it shall be accompanied by evidence as to the satisfaction of the requirements set forth in ss.2.7 hereof; and
3.1.7 Such (i) such other information, documentation and certification as Agent and Lenders (acting through Agent) the Lender shall reasonably request. Each Draw Request shall constitute a representation and warranty by the Borrower that all of the conditions set forth in this Agreement to such Advance, including, without limitation, ss.12, have been satisfied on the date of such Draw Request.
Appears in 1 contract
Sources: Loan Agreement (Sepracor Inc /De/)
Draw Request. At such time as the Borrower shall desire to obtain an Advance for a particular ProjectAdvance, in addition to satisfying the conditions set forth in Article 12 hereof on a Project-by-Project basis, and providing to Agent and Lenders the items set forth in Section 12.5 hereof on a Project-by-Project basis, Borrower shall complete, execute and deliver to Agent, the Lender the Borrower's Requisition for Advance in the form of Exhibit B E attached hereto and by this reference incorporated herein (hereinafter referred to as "Borrower's Requisition for AdvanceRequisition"). Each Borrower's Requisition for Advance shall be , accompanied by the following items in form reasonably acceptable to Agentby:
3.1.1 If Borrower's Requisition for Advance includes Direct Costs to be paid to a Contractor under the applicable Construction Contract, (a) a completed and fully itemized Application and Certificate for Payment (AIA Document G702 and G703or similar form approved by the Lender) containing the certification of Borrower, such the Contractor and either the applicable Borrower's Architect or the Construction Inspector as to the accuracy of same, and a payment requisition and lien affidavit signed by such Contractor and Borrower, respectively, in the forms of Exhibits D and E attached hereto and by this reference incorporated herein;,
3.1.2 If Borrower's Requisition for Advance includes payments for Indirect Costs in excess of the amount described in Section 2.10.1 above, a completed Indirect Cost statement executed by Borrower;
3.1.3 A Draw Request Summary for each applicable Project;
3.1.4 If Borrower's Requisition for Advance includes Project Costs under subparagraphs (b) or copies of requisitions and invoices from subcontractors and materialmen supporting all items of cost covered by such application;
(c) of the definition of "Borrowing Base", a current Borrowing Base Report;
3.1.5 An affidavit and partial waiver of written lien in the form of Exhibit F attached hereto and by this reference incorporated herein waivers from the applicable Contractor and for the current Draw Request and, upon request from Lender from such laborers, subcontractors and materialmen for work done and materials supplied by them since which were paid for pursuant to the previous next preceding Draw RequestRequest in an amount in excess of $5,000.00;
3.1.6 An (d) a written request of the Borrower for any necessary changes in the Plans and Specifications, the Project Budget, the Disbursement Schedule or the Construction Schedule;
(e) copies of all change orders and construction change directives, accompanied by a change order summary prepared by and executed by the Borrower, copies of all material subcontracts, and, to the extent requested by the Lender, of all material inspection report or test reports and certification from Construction Inspectorother documents relating to the construction of the Improvements, at Borrower's expensenot previously delivered to the Lender; and
3.1.7 Such (f) If the Borrower's Requisition includes payment for Stored Materials it shall be accompanied by evidence as to the satisfaction of the requirements set forth in SECTION 2.7 hereof;
(g) such other information, documentation and certification as Agent and Lenders (acting through Agent) the Lender shall reasonably request.
Appears in 1 contract
Sources: Construction Loan Agreement (American Skiing Co /Me)
Draw Request. At such time as As a condition to any disbursement of Loan proceeds, Borrower shall desire fully complete, sign, and deliver to obtain Lender a Draw Request. At a minimum, the Draw Request shall contain the following: the amount of Loan proceeds requested; satisfactory substantiation for the amount requested; the percentage completion of the Work; Borrower’s certification that the undisbursed portion of the Loan plus the undisbursed portions of the Senior Loan (excluding any amounts from the loans allocated to an Advance operating deficit reserve pursuant to the Budget)* plus undisbursed Construction Equity are sufficient to complete the Work in accordance with the Plans and Specifications and this Agreement. The amount sought for a particular Project, hard costs in addition the Draw Request may not exceed the lesser of the actual hard costs incurred by ▇▇▇▇▇▇▇▇ as of the date of the Draw Request or an amount equal to satisfying all budgeted hard costs for the conditions Work times the percentage of completion of the Work less amounts previously advanced for hard costs and retainage. Lender will only advance Loan proceeds for costs contained in the Budget (not exceeding the amount set forth in Article 12 hereof on a Project-by-Project basisthe Budget for each item or category of work), actual, direct costs of the General Contractor for work required by the Construction Contract*, the cost of stored materials, and providing performance of the general conditions under the Construction Contract. Any Draw Request seeking payment for the General Contractor must include a requisition for payment, showing all subcontractors by name and trade, the total amount of each subcontract, and the amount previously paid to Agent each subcontractor as of the date of the requisition, and Lenders the items set forth in Section 12.5 hereof on a Project-by-Project basis, Borrower shall complete, execute and deliver to Agent, Borrower's Requisition for Advance in the form of Exhibit B attached hereto and by this reference incorporated herein (hereinafter referred to as "Borrower's Requisition for Advance"). Each Borrower's Requisition for Advance shall be accompanied by all invoices relating to the following items requisition and the costs in form reasonably acceptable to Agent:
3.1.1 If Borrower's Requisition for Advance includes Direct Costs to be paid to a Contractor under it and partial mechanic’s lien releases from the applicable Construction Contract, a completed and fully itemized Application and Certificate for Payment (AIA Document G702 and G703) containing the certification of Borrower, such General Contractor and subcontractors or other satisfactory evidence of payment to subcontractors. The General Contractor must certify in writing on the applicable Architect as to requisition the accuracy of sameall information in and with it; that there is no person who has or may have any mechanic’s or materialmen’s liens against the Premises as a result of performance of part of the Construction Contract; and the extent of the completion of the Work. Any Draw Request seeking payment for something other than amounts owed under the Construction Contract must state the purpose for the advance and must include invoices for the amount requested or other satisfactory substantiation. In its sole discretion, as a condition of disbursement, Lender may require that: (1) the Architect or a construction inspector satisfactory to Lender certify the Draw Request, including the extent of completion of the Work and Borrower’s and the General Contractor’s compliance with the Plans and Specifications and the Construction Contract; (2) it receive an updated survey (provided, however, Lender will not request an updated survey in connection with an interim Draw Request unless it is needed to resolve an issue or dispute raised by the Draw Request); (3) it receive an endorsement to Lender’s title insurance policy, increasing the amount of the coverage to the amount advanced by Lender (unless the policy provides for such an increase automatically), extending the effective date of the policy to the date of disbursement, and a payment requisition indicating that, since the effective date of the policy or the last endorsement, there has been no change in the status of title to the Premises and lien affidavit signed by such Contractor no new title exceptions; and Borrower, respectively(4) it receive an inspection report from an independent inspector satisfactory to Lender, in which the forms inspector has covered those items specified by ▇▇▇▇▇▇. Borrower may not submit the first Draw Request sooner than 20 days after Closing and subsequent Draw Requests no more frequently than once per month. After disbursement of Exhibits D Loan proceeds pursuant to a Draw Request, Lender may request canceled checks and E attached hereto and by this reference incorporated herein;
3.1.2 If Borrower's Requisition for Advance includes payments for Indirect Costs in excess paid invoices, evidencing payment of the amount described in Section 2.10.1 above, a completed Indirect Cost statement executed hard and soft costs covered by Borrower;
3.1.3 A any such Draw Request. Each Draw Request Summary for each applicable Project;
3.1.4 If shall constitute Borrower's Requisition for Advance includes Project Costs under subparagraphs (b) or (c) ’s affirmation that the representations and warranties in this Agreement remain true and correct as of the definition date of "Borrowing Base"the Draw Request and, a current Borrowing Base Report;
3.1.5 An affidavit unless Lender is notified in writing to the contrary before the disbursement of the requested advance, will be true and partial waiver correct on the date of lien in the form of Exhibit F attached hereto and by this reference incorporated herein from the applicable Contractor and such laborers, subcontractors and materialmen for work done and materials supplied by them since the previous Draw Request;
3.1.6 An inspection report and certification from Construction Inspector, at Borrower's expense; and
3.1.7 Such other information, documentation and certification as Agent and Lenders (acting through Agent) shall reasonably requestdisbursement.
Appears in 1 contract
Sources: Construction Loan Agreement
Draw Request. At Except in connection with the initial Advance of $18.4 million (which shall be funded by Lender at Closing in accordance with Section 10 below) (the “Initial Advance”), at such time as the Borrower shall desire to obtain an Advance for a particular Projectsubsequent Advance, in addition to satisfying the conditions set forth in Article 12 hereof on a Project-by-Project basis, and providing to Agent and Lenders the items set forth in Section 12.5 hereof on a Project-by-Project basis, Borrower shall complete, execute and deliver to Agent, the Lender the Borrower's ’s Requisition for Advance in the form of Exhibit B A attached hereto and by this reference incorporated herein (hereinafter referred to as "Borrower's Requisition for Advance")hereto. Each Borrower's ’s Requisition for Advance shall be accompanied by the following items in form reasonably acceptable to Agentby:
3.1.1 (a) If the Borrower's ’s Requisition for Advance includes Direct Costs amounts to be paid to a the Contractor under the applicable Construction Contract, : (i) a completed and fully itemized Application and Certificate for Payment (AIA Document G702 and G703or similar form approved by the Lender) containing the certification of Borrower, such the Contractor and the applicable Architect Engineer as to the accuracy of same, ; and a payment requisition (ii) copies of requisitions and lien affidavit signed invoices from subcontractors and materialmen supporting all items of Direct Cost covered by such Contractor and Borrower, respectively, in the forms of Exhibits D and E attached hereto and by this reference incorporated hereinapplication;
3.1.2 (b) If the Borrower's ’s Requisition for Advance includes payments for Indirect Costs, it shall be accompanied by invoices for all items of Indirect Costs in excess of the amount described in Section 2.10.1 above, a completed Indirect Cost statement executed by Borrowercovered thereby;
3.1.3 A Draw Request Summary for each applicable Project;
3.1.4 If Borrower's Requisition for Advance includes Project Costs under subparagraphs (b) or (c) of If requested by the definition of "Borrowing Base"Lender or if a mechanics or materialmen lien has been filed, a current Borrowing Base Report;
3.1.5 An affidavit an accurately completed and partial valid lien waiver of lien with respect to work performed to date for which payment has been received (hereinafter, the “Lien Waiver”) in the form of Exhibit F attached hereto and as Exhibit B shall be executed by this reference incorporated herein from the Contractor or the applicable Contractor and such laborerssubcontractor, subcontractors and materialmen for work done and materials supplied by them since the previous Draw Request;
3.1.6 An inspection report and certification from Construction Inspectorlaborer, at Borrower's expenseor materialmen; and
3.1.7 (d) Copies of all change orders and construction change directives, accompanied by a change order summary prepared by and executed by the Borrower, and, to the extent requested by the Lender within three (3) Business Days of receipt of Borrower’s Requisition, of all inspection or test reports and other documents relating to the construction of the Improvements, which are in existence and not previously delivered to the Lender;
(e) If the Borrower’s Requisition includes payment for Stored Materials, it shall be accompanied by evidence as to the satisfaction of the requirements set forth in §2.7 hereof; and
(f) Such other information, documentation and certification which is in existence as Agent and Lenders (acting through Agent) the Lender shall reasonably requestrequest within three (3) Business Days of receipt of Borrower’s Requisition. Each Draw Request shall constitute a certification by the Borrower that to its knowledge all of the conditions set forth in this Agreement to such Advance, including, without limitation, §11, have been satisfied on the date of such Draw Request. Lender shall advance more for one particular category or line item than is reflected in the Project Budget for such category or line item and less for another category or line item than is reflected in the Project Budget for such category or line item so long as the total amount of the Project Budget does not change as a result in accordance with § 2.5(b) hereof.
Appears in 1 contract
Sources: Construction Loan Agreement (OneBeacon Insurance Group, Ltd.)
Draw Request. At such time as the Borrower shall desire to obtain an Advance for a particular ProjectAdvance, in addition to satisfying the conditions set forth in Article 12 hereof on a Project-by-Project basis, and providing to Agent and Lenders the items set forth in Section 12.5 hereof on a Project-by-Project basis, Borrower shall complete, execute and deliver to Agent, the Lender the Borrower's Requisition for Advance in the form of Exhibit B G attached hereto and by this reference incorporated herein (hereinafter referred to as "Borrower's Requisition for Advance")hereto. Each Borrower's Requisition for Advance shall be accompanied by the following items in form reasonably acceptable to Agentby:
3.1.1 (a) If the Borrower's Requisition includes payments for Advance Direct Costs, a completed and itemized Direct Cost Statement in the form of Schedule I of Exhibit G attached hereto, executed by the Borrower, together with invoices for all items of Direct Cost covered thereby;
(b) If the Borrower's Requisition includes Direct Costs amounts to be paid to a the Contractor under the applicable Construction Contract, : (i) a completed and fully itemized Application and Certificate for Payment (AIA Document G702 and G703or similar form approved by the Lender) containing the certification of Borrower, such the Contractor and the applicable Borrower's Architect as to the accuracy of same, and ; (ii) a payment requisition and lien affidavit signed by such Contractor and Borrower, respectively, in the forms of Exhibits D and E attached hereto and by this reference incorporated herein;
3.1.2 If Borrower's Requisition for Advance includes payments for Indirect Costs in excess certificate of the amount described in Section 2.10.1 above, a completed Indirect Cost statement executed by Borrower;
3.1.3 A Draw Request Summary for each applicable Project;
3.1.4 If Borrower's Requisition for Advance includes Project Costs under subparagraphs (b) or (c) of the definition of "Borrowing Base", a current Borrowing Base Report;
3.1.5 An affidavit and partial waiver of lien Contractor in the form of Exhibit F H attached hereto (with such changes therein as the Contractor may reasonably request, subject to the approval of the Lender which approval will not be unreasonably delayed or denied); (iii) a certificate of the Borrower's Architect in the form of Exhibit I attached hereto (with such changes therein as the Borrower's Architect may reasonably request, subject to the approval of the Lender which approval will not be unreasonably delayed or denied); and (iv) copies of requisitions and invoices from subcontractors and materialmen supporting all items of cost covered by this reference incorporated herein from such application;
(c) If the applicable Borrower's Requisition includes payments for Indirect Costs, it shall be accompanied by a completed and itemized Indirect Cost Statement in the form of Schedule II of Exhibit G attached hereto, executed by the Borrower, together with invoices for all items of Indirect Costs covered thereby;
(d) If the Borrower's Requisition includes payments for tenant improvements, it shall be accompanied by a completed and itemized Tenant Improvements Summary in the form of Exhibit J attached hereto, executed by the Borrower;
(e) If requested by the Lender or if a Section 2 Lien has been filed, an accurately completed and valid Partial Waiver and Subordination of Lien (hereinafter, the "Lien Form") in the form set forth in Chapter 254 of the Massachusetts General Laws, as amended (hereinafter, the "Mechanic's Lien Law") and as annexed hereto as Exhibit K, executed by the Contractor, such Lien Form to provide that subject to the payment of the amount set forth in the Borrower's Requisition, the Contractor waives any and such laborersall lien rights for labor and materials, subcontractors or rental equipment, appliances or tools, performed or furnished through the last day of the period ending on the date designated in the Lien Form (hereinafter, the "Payment Period Date"), except for Retainage, unpaid agreed or pending change orders, and disputed claims as stated in the Lien Form;
(f) Lien waivers in form acceptable to the Lender executed by all contractors, subcontractors, laborers and materialmen for work done and materials supplied by them since which were paid for pursuant to the previous next preceding Draw Request;
3.1.6 An (g) Copies of all change orders and construction change directives, accompanied by a change order summary prepared by and executed by the Borrower, copies of all subcontracts, and, to the extent requested by the Lender, of all inspection report or test reports and certification from Construction Inspectorother documents relating to the construction of the Improvements, at not previously delivered to the Lender;
(h) If the Borrower's expenseRequisition includes payment for Stored Materials, it shall be accompanied by evidence as to the satisfaction of the requirements set forth in ss.2.7 hereof; and
3.1.7 Such (i) such other information, documentation and certification as Agent and Lenders (acting through Agent) the Lender shall reasonably request. Each Draw Request shall constitute a representation and warranty by the Borrower that all of the conditions set forth in this Agreement to such Advance, including, without limitation, ss.12, have been satisfied on the date of such Draw Request.
Appears in 1 contract
Sources: Loan Agreement (Sepracor Inc /De/)
Draw Request. At such time as Borrower Borrowers shall desire to obtain an Advance for a particular Project, in addition to satisfying the conditions set forth in Article 12 hereof on a Project-by-Project basis, and providing to Agent and Lenders the items set forth in Section 12.5 hereof on a Project-by-Project basis, Borrower shall complete, execute and deliver have submitted to Agent, Borrower's Requisition a written request for such Phase Zero Renovation Advance in or PIP Advance, delivered not less than ten (10) Business Days prior to the form requested date of Exhibit B attached hereto funding (each, a “Draw Request”) and by this reference incorporated herein (hereinafter referred to as "Borrower's Requisition for Advance"). Each Borrower's Requisition for Advance shall be accompanied by (A) an Officer’s Certificate from Borrowers stating and certifying that: (1) the following items in form reasonably acceptable to Agent:
3.1.1 If Borrower's Requisition for Advance includes Direct Costs to be paid to a Contractor under funded by the applicable Construction Contract, a completed and fully itemized Application and Certificate for Payment (AIA Document G702 and G703) containing the certification of Borrower, such Contractor and the applicable Architect as to the accuracy of samerequested Phase Zero Renovation Advance and/or PIP Advance are Approved Renovation/PIP Expenses, and a payment requisition description thereof, (2) the work related to such Approved Renovation/PIP Expenses to be funded by the requested Phase Zero Renovation Advance and/or PIP Advance (or the relevant portion thereof as to which such request for funds relates) has been completed in a good and lien affidavit signed by such Contractor workmanlike manner and Borrowerin accordance with all applicable Legal Requirements in all material respects, respectively(3) the Approved Renovation/PIP Expenses (or the relevant portions thereof) to be funded from the Phase Zero Renovation Advance and/or PIP Advance in question have not been the subject of a previous Phase Zero Renovation Advance and/or PIP Advance, (4) all previous disbursements of Phase Zero Renovation Advances and/or PIP Advances have been used to pay the previously identified Approved Renovation/PIP Expenses and have been paid in the forms of Exhibits D full and E attached hereto and by this reference incorporated herein;
3.1.2 If Borrower's Requisition for Advance includes payments for Indirect Costs in excess (5) Borrowers have paid or has provided Agent with evidence reasonably satisfactory to Agent that Borrowers are paying Borrowers’ Share of the Approved Renovation/PIP Expenses that are the subject of the Phase Zero Renovation Advance and/or PIP Advance in question prior to or simultaneously with funding of the applicable Phase Zero Renovation Advance and/or PIP Advance; (B) copies of all licenses, permits and other approvals by any Governmental Authority required in connection with the work related to such Approved Renovation/PIP Expenses and not previously delivered to Agent; (C) copies of all invoices with respect to which such Phase Zero Renovation Advance and/or PIP Advance is being requested; and (D) such other evidence as Agent shall reasonably request to demonstrate that any work to be funded by the requested Phase Zero Renovation Advance and/or PIP Advance is paid for or will be paid upon such disbursement to Borrowers (or the portion thereof as to which such request for disbursement has been submitted has been completed and is paid for (other than any retention amount described in Section 2.10.1 above, which is not a completed Indirect Cost statement executed by Borrower;
3.1.3 A Draw Request Summary for each applicable Project;
3.1.4 If Borrower's Requisition for Advance includes Project Costs under subparagraphs (bpart of such disbursement request) or (c) will be paid upon such disbursement to Borrowers), and that Borrowers have paid Borrowers’ Share of the definition Approved Renovation/PIP Expenses that are the subject of "Borrowing Base", a current Borrowing Base Report;
3.1.5 An affidavit and partial waiver the Phase Zero Renovation Advance and/or PIP Advance or such amounts will be paid simultaneously with disbursement of lien in the form of Exhibit F attached hereto and by this reference incorporated herein from the applicable Contractor and such laborers, subcontractors and materialmen for work done and materials supplied by them since the previous Draw Request;
3.1.6 An inspection report and certification from Construction Inspector, at Borrower's expense; and
3.1.7 Such other information, documentation and certification as Agent and Lenders (acting through Agent) shall reasonably requestPhase Zero Renovation Advance and/or PIP Advance.
Appears in 1 contract
Sources: Loan Agreement (Creative Media & Community Trust Corp)
Draw Request. At such time as Borrower shall desire to obtain an Advance for a particular Project, in addition to satisfying the conditions set forth in Article 12 hereof on a Project-by-Project basis, and providing to Agent and Lenders the items set forth in Section 12.5 hereof on a Project-by-Project basis, Borrower shall complete, execute and deliver to Agent, Borrower's ’s Requisition for Advance in the form of Exhibit B attached hereto and by this reference incorporated herein (hereinafter referred to as "“Borrower's ’s Requisition for Advance"”). Each Borrower's ’s Requisition for Advance shall be accompanied by the following items in form reasonably acceptable to Agent:
3.1.1 If Borrower's ’s Requisition for Advance includes Direct Costs to be paid to a Contractor under the applicable Construction Contract, a completed and fully itemized Application and Certificate for Payment (AIA Document G702 and G703) containing the certification of Borrower, such Contractor and the applicable Architect as to the accuracy of same, and a payment requisition and lien affidavit signed by such Contractor and Borrower, respectively, in the forms form of Exhibits D and E Exhibit 3 attached hereto and by this reference incorporated hereinto Exhibit B hereto;
3.1.2 If Borrower's ’s Requisition for Advance includes payments for Indirect Costs in excess of the amount described in Section 2.10.1 above, a completed Indirect Cost statement executed by Borrower;
3.1.3 A Draw Request Summary for each applicable Project;
3.1.4 If Borrower's ’s Requisition for Advance includes Project Costs under subparagraphs (b) or (c) of the definition of "“Borrowing Base"”, a current Borrowing Base Report;
3.1.5 An affidavit and partial waiver of lien in the form of Exhibit F 4 attached to Exhibit B hereto and by this reference incorporated herein from the applicable Contractor and such laborers, subcontractors and materialmen for work done and materials supplied by them since the previous Draw Request;
3.1.6 An inspection report and certification from Construction Inspector, at Borrower's ’s expense; and
3.1.7 Such other information, documentation and certification as Agent and Lenders (acting through Agent) shall reasonably request.
Appears in 1 contract
Sources: Revolving Credit Construction Loan Agreement (Wci Communities Inc)