Disputed Directives. Pending a Change Order, or absent a Change Order and pending final determination of the total cost of the Construction Change Directive, the DB Contractor may submit Applications for Payment in respect of changed Work ordered and completed pursuant to a Construction Change Directive in order to be compensated for the Increased Cost of such Work, plus a percentage markup for overhead and profit, determined in accordance with Subsection 13.4.3 (Increased Cost-Plus Fee Method) and subject to the limitations set forth in Subsection 13.4.4 (Additional Conditions of Payment for Changed Work) and Sections 13.5 (Markups for Additional Work) and 13.6 (