Common use of Design Development Documents Phase Clause in Contracts

Design Development Documents Phase. During design development, the [Project Development Team] shall meet weekly to review the Drawings and Specifications and discuss any material modifications from those previously issued. Design Professional shall deliver to Construction Manager Design Development Documents on or before the dates set forth in the Project Schedule. Within fourteen (14) Days after Construction Manager receives Design Development Documents, Construction Manager shall deliver, with supporting data, and meet with Owner Parties to discuss, its revised cost estimate incorporating the applicable Design Development Document information, and updating and refining, the applicable reconciled Schematic Design Document cost estimate (from Section

Appears in 3 contracts

Sources: Construction Manager at Risk and General Contractor Agreement, Construction Manager at Risk and General Contractor Agreement, Construction Manager at Risk and General Contractor Agreement