Common use of Delayed Tests Clause in Contracts

Delayed Tests. If the Contractor incurs Cost as a result of any unreasonable delay by the Employer to the Tests after Completion, the Contractor shall (i) give notice to the Engineer and (ii) be entitled subject to Sub-Clause 20.1 [Contractor's Claims] to payment of any such Cost plus reasonable profit, which shall be included in the Contract Price. After receiving this notice, the Engineer shall proceed in accordance with Sub-Clause

Appears in 4 contracts

Samples: Contract Agreement, Contract Agreement, Contract Agreement