Delay of the Substantial Completion of the Leased Premises Sample Clauses
Delay of the Substantial Completion of the Leased Premises. Except as provided in this Section 5.3, the Commencement Date shall occur as set forth in the Lease. If there shall be a delay or there are delays in the Substantial Completion of the Leased Premises or in the occurrence of any of the other conditions precedent to the Commencement Date, as set forth in the Lease, as a direct or total result of (each to the extent they actually cause a delay in Substantial Completion, a ‘‘Tenant Delay”):
5.3.1 Tenant’s failure to comply with the Time Deadlines (except to the extent such failure is caused by Landlord or its agents or contractors);
5.3.2 Tenant’s failure to respond, with disapproval or approval, of any matter requiring Tenant’s approval within timeframe specified at the time of execution of the Lease, or, if none, within six (6) business days;
5.3.3 A breach by Tenant of the terms of this Tenant Work Letter or the Lease;
5.3.4 Tenant’s requirement for materials, components, finishes or improvements which are not available in a commercially reasonable time given the anticipated date of Substantial Completion of the Leased Premises, as set forth in the Lease, or which are different from, or not included in, the Standard Improvement Package; or
5.3.5 Any other acts or omissions of Tenant, or its agents, or employees; then, notwithstanding anything to the contrary set forth in the Lease or this Work Letter, as Landlord’s sole and exclusive remedy, all deadlines for Landlord’s performance shall be extended by one (1) day for each day of delay by Tenant. In no event shall Landlord be entitled to claim any such extension unless Landlord has notified Tenant within ten (10) business days after any event of purported delay by Tenant or due to any of the other of the foregoing reasons of Landlord’s intention to claim such extension and stating the number of days of each such extension claimed. In any event, if the Tenant delay is greater than ninety (90) days, payment of the Base Rent shall commence on the first day of the first month following the ninety (90) day delay.
Delay of the Substantial Completion of the Leased Premises. Except as provided in this Section 5.2, the Commencement Date shall occur as set forth in the Lease. If there are delays in the Substantial Completion of the Tenant Improvements or in the occurrence of any of the other conditions precedent to the Commencement Date, as set forth in the Lease, as a result of:
5.2.1 Tenant’s failure to comply with the Time Deadlines;
5.2.2 Time elapsed in excess of three (3) days for Tenant’s approval or disapproval of any matter hereunder other than the approvals set forth in the Time Deadlines;
5.2.3 A breach by Tenant of the terms of this Work Letter or the Lease;