Common use of Delay in Completion Clause in Contracts

Delay in Completion. If a delay in the performance of the Work occurs (a) because Lessee does not timely approve the Working Drawings; (b) because of any change by Lessee to the Working Drawings, (c) because of any specification by Lessee of materials or installations in addition to or other than Lessor’s Building Standard materials, or (d) if Lessee, any contractor or subcontractor, or Lessee’s agents otherwise delay completion of the Work, and the obtaining of a temporary or final certificate of occupancy, then, notwithstanding any provision to the contrary in this Lease, ▇▇▇▇▇▇’s obligation to pay rent and additional charges as set forth in the Lease shall commence on the Commencement Date of the Lease.

Appears in 1 contract

Sources: Modified Industrial Gross Lease (Excelligence Learning Corp)

Delay in Completion. If a delay in the performance of the Work occurs (a) because Lessee does not timely approve the Working Drawings; (b) because of any substantial change by Lessee to the Working Drawings, (c) because of any specification by Lessee of materials or installations in addition to or other than Lessor’s Building Standard the agreed-upon materials, or (d) if Lessee, any contractor or subcontractor, or Lessee’s agents otherwise materially delay completion of the Work, and the obtaining of a temporary or final certificate of occupancy, then, notwithstanding any provision to the contrary in this Lease, ▇▇▇▇▇▇Lessee’s obligation to pay rent and additional charges as set forth in the Lease shall commence on the Commencement Date of the Lease.

Appears in 1 contract

Sources: Net Lease Agreement (InfuSystem Holdings, Inc)

Delay in Completion. If a delay in the performance of the Work occurs (a) because Lessee does not timely promptly respond to Lessor or approve the Working Drawings; (b) because of any change by Lessee to the Working Drawings, (c) because of any specification by Lessee of materials or installations in addition to or other than Lessor’s 's Building Standard materials, or (d) if Lessee, any contractor or subcontractor, or Lessee’s 's agents otherwise delay completion of the Work, and the obtaining of a temporary or final certificate of occupancy, then, notwithstanding any provision to the contrary in this Lease, ▇▇▇▇▇▇’s Lessee's obligation to pay rent and additional charges Additional Charges as set forth in the Lease shall commence on the Commencement Date of the Lease.

Appears in 1 contract

Sources: Lease Agreement (CyDex Pharmaceuticals, Inc.)

Delay in Completion. If a delay in the performance of the Work occurs (a) because Lessee does not timely approve deliver the Working Drawings; (b) because of any change by Lessee to the Working Drawings, (c) because of any specification by Lessee of materials or installations in addition to or other than Lessor’s Building Standard materials, or (d) if Lessee, any contractor or subcontractor, or Lessee’s agents otherwise delay completion of the Work, and the obtaining of a temporary or final certificate of occupancy, then, notwithstanding any provision to the contrary in this Lease, ▇▇▇▇▇▇Lessee’s obligation to pay rent and additional charges as set forth in the Lease shall commence on the Commencement Date of the Lease.

Appears in 1 contract

Sources: Standard Office Lease (Wageworks, Inc.)