Common use of Days by Written Agreement Clause in Contracts

Days by Written Agreement. A written request detailing the specific reasons for a submission later than 35 days due to complexity of design, or non-critical path status of the Submittal shall be submitted at the time the Baseline Schedule is submitted. The Baseline Schedule shall not include a delayed Submittal until written agreement is provided. In addition to the request for providing a Submittal after the thirty-five (35) day period, a copy of the Contract with the Subcontractor who shall be performing the Submittal, a written statement from the Subcontractor verifying that work has commenced on the Submittal and providing Subcontractor’s own schedule of milestones and completion dates, and a corresponding Submittal designation in the Schedule as required under Article 9

Appears in 6 contracts

Samples: Construction Services Agreement, Construction Services Agreement, Construction Services Agreement

AutoNDA by SimpleDocs
Time is Money Join Law Insider Premium to draft better contracts faster.