Common use of DAF Construction Clause in Contracts

DAF Construction. The DAF shall be designed and constructed in accordance with Good Utility Practice. Within one hundred twenty (120) Calendar Days after the Commercial Operation Date, unless the Interconnection Customer and Transmission Owner agree on another mutually acceptable deadline, the Interconnection Customer shall deliver to the Transmission Owner and NYISO “as-built” drawings, information and documents for the DAF, such as: a one-line diagram, a site plan showing the Large Generating Facility and the DAF, plan

Appears in 6 contracts

Sources: Large Generator Interconnection Agreement, Large Generator Interconnection Agreement, Large Generator Interconnection Agreement

DAF Construction. The DAF shall be designed and constructed in accordance with Good Utility Practice. Within one hundred twenty (120) Calendar Days after the Commercial Operation Date, unless the Interconnection Customer Developer and Transmission Owner agree on another mutually acceptable deadline, the Interconnection Customer Developer shall deliver to the Transmission Owner and NYISO “as-built” drawings, information and documents for the DAF, such as: a one-one- line diagram, a site plan showing the Large Generating Facility and the DAF, planplan and elevation drawings

Appears in 3 contracts

Sources: Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement, Interconnection Agreement

DAF Construction. The DAF shall be designed and constructed in accordance with Good Utility Practice. Within one hundred twenty (120) Calendar Days after the Commercial Operation Date, unless the Interconnection Customer Developer and Connecting Transmission Owner agree on another mutually acceptable deadline, the Interconnection Customer Developer shall deliver to the Connecting Transmission Owner and NYISO “as-as- built” drawings, information and documents for the DAF, such as: a one-line diagram, a site plan showing the Large Generating Facility and the DAF, planplan and elevation drawings showing the

Appears in 2 contracts

Sources: Large Generator Interconnection Agreement, Interconnection Agreement

DAF Construction. The DAF shall be designed and constructed in accordance with Good Utility Practice. Within one hundred twenty (120) Calendar Days after the Commercial Operation Date, unless the Interconnection Customer Developer and Transmission Owner agree on another mutually acceptable deadline, the Interconnection Customer Developer shall deliver to the Transmission Owner and NYISO “as-built” drawings, information and documents for the DAF, such as: a one-one- line diagram, a site plan showing sho wing the Large Generating Facility and the DAF, planplan and elevation drawings

Appears in 1 contract

Sources: Standard Large Generator Interconnection Agreement