COP Negotiations. Upon receipt of the COP, or a request for equitable adjustment in the Contract Sum or Guaranteed Completion Date(s), or both, as provided in Articles 9 and 10, Owner may accept or reject the proposal, request further documentation, or negotiate acceptable terms with Design-Builder. Pending agreement on the terms of the Change Order, Owner may direct Design-Builder to proceed immediately with the Change Order Work. Design-Builder shall not proceed with any change in the Work until it has obtained Owner’s approval or Owner’s Field Authorization as provided in Section 8.3. All Work done pursuant to any Owner-directed change in the Work shall be executed in accordance with the Contract Documents.
Appears in 4 contracts
Samples: Design Build Agreement, Design Build Agreement, des.wa.gov
COP Negotiations. Upon receipt of the COP, or a request for equitable adjustment in the Contract Sum or Guaranteed Completion Date(s), or both, as provided in Articles 9 and 10, Owner may accept or reject the proposal, request further documentation, or negotiate acceptable terms with Design-Builder. Pending agreement on the terms of the Change Order, Owner may direct Design-Builder to proceed immediately with the Change Order Work. Design-Design- Builder shall not proceed with any change in the Work until it has obtained Owner’s approval or Owner’s Field Authorization as provided in Section 8.3. All Work done pursuant to any Owner-Owner- directed change in the Work shall be executed in accordance with the Contract Documents.
Appears in 3 contracts
Samples: Design Build Agreement, Design Build Agreement, Design Build Agreement
COP Negotiations. Upon receipt of the COPChange Order Proposal, or a request for equitable adjustment in the Contract Sum or Guaranteed Completion Date(s)Contract Time, or both, as provided in Articles 9 Sections 7.02 and 107.03, Owner may accept or reject the proposal, request further documentation, or negotiate acceptable terms with Design-BuilderContractor. Pending agreement on the terms of the Change Order, Owner may direct Design-Builder Contractor to proceed immediately with the Change Order Work. Design-Builder Contractor shall not proceed with any change in the Work until it has obtained Owner’s approval or Owner’s Field Authorization as provided in Section 8.3approval. All Work done pursuant to any Owner-directed change in the Work shall be executed in accordance with the Contract Documents.
Appears in 1 contract
Samples: www.spokanetransit.com
COP Negotiations. Upon receipt of the COPChange Order Proposal, or a request for equitable adjustment in the Contract Sum or Guaranteed Completion Date(s)Contract Time, or both, as provided in Articles 9 Sections 7.02 and 10, Owner 7.03,Owner may accept or reject the proposal, request further documentation, or negotiate acceptable terms with Design-BuilderContractor. Pending agreement on the terms of the Change Order, Owner may direct Design-Builder Contractor to proceed immediately with the Change Order Work. Design-Builder Contractor shall not proceed with any change in the Work until it has obtained Owner’s approval or Owner’s Field Authorization as provided in Section 8.3approval. All Work done pursuant to any Owner-directed change in the Work shall be executed in accordance with the Contract Documents.
Appears in 1 contract
Samples: Public Works Contract