Contractor to follow Construction Programme. Insofar as the carrying out of the Works affects or may affect the provision of Educational Services at any Existing School, the Contractor shall procure that the Works are carried out strictly in accordance with the Construction Programme and so as to minimise any disruption to the provision of Educational Services.
Contractor to follow Construction Programme. Insofar as the carrying out of the Works affects or may affect the provision of Educational Services at any Existing Project Facility, the Contractor shall procure that the Works are carried out in accordance with the Construction Programme and so as to minimise in so far as reasonably practicable any disruption to the provision of Educational Services. The Authority’s Representative may notify the Contractor if in his opinion at any time the actual progress of the Works does not conform in any material respect with the Construction Programme and may require (acting reasonably and if the Contractor agrees or it is determined pursuant to the Dispute Resolution Procedure that such progress does not so conform) the Contractor either:
11.1.1 to submit to the Authority’s Representative a report identifying the reasons for the delay; and
11.1.2 to produce and submit to the Authority’s Representative in accordance with the Review Procedure a revised Construction Programme showing the manner in which the Works will be carried out and (if possible) the periods necessary to ensure completion of the Works at the relevant Project Facility by the relevant Target Service Availability Date, Target External Works Availability Date or Target Grass Pitch Availability Date (as the case may be); or
Contractor to follow Construction Programme. Insofar as the carrying out of the Works affects or may affect the provision of Educational Services or the Community Education Services at any Project Facility, the Contractor shall procure that the Works are carried out generally in accordance with the Construction Programme and so as to minimise, so far as reasonably practicable, any disruption to the provision of Educational Services and the Community Education Services. The Authority’s Representative may notify the Contractor if in his opinion at any time the actual progress of the Works does not conform in any material respect with the Construction Programme and may require (acting reasonably and if the Contractor agrees or it is determined pursuant to the Dispute Resolution Procedure that such progress does not so conform) the Contractor either:
11.1.1 to submit to the Authority’s Representative a report identifying the reasons for the delay; and
11.1.2 to produce and submit to the Authority’s Representative in accordance with the Review Procedure a revised Construction Programme showing the manner in which the Works will be carried out and (if possible) the periods necessary to ensure completion of the Works at the relevant Project Facility by the relevant Target Service Availability Date, Target External Works Availability Date or Target Grass Playing Fields Availability Date, as the case may be; or
11.1.3 to produce and submit to the Authority’s Representative in accordance with the Review Procedure a revised Construction Programme showing the steps which the Contractor intends to take to eliminate or reduce any delay in reaching the relevant Target Service Availability Date, Target External Works Availability Date or Target Grass Playing Fields Availability Date, as the case may be.
Contractor to follow Construction Programme. 9.1.1 Insofar as the carrying out of the Works affects or may affect the provision of the Services, the Contractor shall procure that the Works are carried out strictly in accordance with the Construction Programme and so (where applicable) as to minimise any disruption to the provision of the Services.
9.1.2 Without prejudice to the requirement of the Contractor to notify pursuant to clause 15 (Extensions of Time), if either:-
(a) the Contractor becomes aware at any time that the actual progress of the Works may become or has been significantly delayed or has fallen behind the Construction Programme; or
(b) it appears to the Authority’s Representative at any time that the actual progress of the Works has been significantly delayed or has fallen behind the Construction Programme (and the Authority’s Representative requests the Contractor’s Representative to do so), the Contractor’s Representative shall submit to the Authority’s Representative a report identifying the reasons for the delay and (where the Authorities Representative requires the Contractor’s Representative to do so) the Contractor’s Representative shall produce and submit to the Authority’s Representative a revised Construction Programme showing the manner and the periods in which the Works will be carried out to achieve the Target Services Availability Date and/or showing the steps which are to be taken to eliminate or reduce the delay.