CONTRACT TIME AND TIME EXTENSIONS Clause Samples

The "Contract Time and Time Extensions" clause defines the period within which the contracted work must be completed and outlines the procedures for extending this timeframe if necessary. Typically, it specifies the start and end dates for the project and details the circumstances under which the contractor may request additional time, such as delays caused by unforeseen events or changes in project scope. This clause ensures that both parties have a clear understanding of the project schedule and provides a formal mechanism to address delays, thereby minimizing disputes and maintaining project momentum.
CONTRACT TIME AND TIME EXTENSIONS. 9.1 Contractor shall diligently pursue the completion of the Work and coordinate the Work being done on the Project by its subcontractors and material-men, as well as coordinating its Work with all work of others at the Project Site, so that its Work or the work of others shall not be delayed or impaired by any act or omission by Contractor. Contractor shall be solely responsible for all construction means, methods, techniques, sequences, and procedures, as well as coordination of all portions of the Work under the Contract Documents, and the coordination of Owner's suppliers and contractors as set forth in Paragraph 12.2. herein. 9.2 Should Contractor be obstructed or delayed in the prosecution of or completion of the Work as a result of unforeseeable causes beyond the control of Contractor, and not due to its fault or neglect, including but not restricted to acts of Nature or of the public enemy, acts of government, fires, floods, epidemics, quarantine regulation, strikes or lockouts, Contractor shall notify the Owner in writing within forty-eight (48) hours after the commencement of such delay, stating the cause or causes thereof, or be deemed to have waived any right which Contractor may have had to request a time extension. 9.3 No interruption, interference, inefficiency, suspension or delay in the commencement or progress of the Work from any cause whatever, including those for which Owner may be responsible, in whole or in part, shall relieve Contractor of its duty to perform or give rise to any right to damages or additional compensation from Owner. Contractor expressly acknowledges and agrees that it shall receive no damages for delay. Contractor's sole remedy, if any, against Owner will be the right to seek an extension to the Contract Time; provided, however, the granting of any such time extension shall not be a condition precedent to the aforementioned "No Damage For Delay" provision. This paragraph shall expressly apply to claims for early completion, as well as to claims based on late completion. 9.4 In no event shall any approval by Owner authorizing Contractor to continue performing Work under this Agreement or any payment issued by Owner to Contractor be deemed a waiver of any right or claim Owner may have against Contractor for delay damages hereunder.
CONTRACT TIME AND TIME EXTENSIONS. 11.1 Construction Contractor shall diligently pursue the completion of the Work and coordinate the Work being done on the Project by its subcontractors and materialmen, as well as coordinating its Work with all work of others at the Project site, so that its Work or the work of others shall not be delayed or impaired by any act or omission by Construction Contractor or anyone for whom Construction Contractor is responsible or liable. Unless expressly noted otherwise in the Contract Documents, Construction Contractor shall be solely responsible for all construction means, methods, techniques, sequences, and procedures, as well as coordination of all portions of the Work under the Contract Documents, coordination of trades and subcontractors, coordination of drawings to existing as-built conditions and site conditions, and the coordination of Owner’s suppliers and contractors as set forth in Section 14 of these General Terms and Conditions. 11.2 Should Construction Contractor actually be obstructed or delayed in the critical path of the prosecution of, or completion of, the Work as a result of unforeseeable causes: (a) beyond the control of Construction Contractor, (b) not due to Construction Contractor’s fault or neglect, and (c) which could not be avoided by the exercise of reasonable diligence, including: (i) acts of God or of the public enemy, (ii) acts of government, (iii) fires, (iv) floods, (v) epidemics,
CONTRACT TIME AND TIME EXTENSIONS. 11.1 Construction Contractor shall diligently pursue the completion of the Work and coordinate the Work being done on the Project by its subcontractors and materialmen, as well as coordinating its Work with all work of others at the Project site, so that its Work or the work of others shall not be delayed or impaired by any act or omission by Construction Contractor or anyone for whom Construction Contractor is liable. Unless expressly noted otherwise in the Contract Documents, Construction Contractor shall be solely responsible for all construction means, methods, techniques, sequences, and procedures, as well as coordination of all portions of the Work under the Contract Documents, and the coordination of Owner’s suppliers and contractors as set forth in Section 14 herein. 11.2 Should Construction Contractor be obstructed or delayed in the prosecution of or completion of the Work as a result of unforeseeable causes beyond the control of Construction Contractor, and not due to its fault or neglect, including but not restricted to acts of God or of the public enemy, acts of government, fires, floods, epidemics, quarantine regulation, strikes, lockouts, unusually severe weather conditions by comparison with the ten- year Orange County, Florida, average not reasonably anticipatable, Construction Contractor shall notify Owner and Design Professional in writing within seven (7) calendar days after the commencement of such delay, stating the cause or causes thereof, or be deemed to have waived any right which Construction Contractor may have had to request a time extension. 11.2.1 Owner shall have the right, at any time, whether or not Construction Contractor is behind schedule, to order Construction Contractor to accelerate its Work. In the event that Owner orders Construction Contractor to accelerate its Work and Construction Contractor (i) is not behind schedule and (ii) believes that acceleration will increase the cost of performance, Construction Contractor, shall be required to submit a Claim for increase pursuant to Section 13 of this Agreement. Any such claim shall be based exclusively and solely on actual and direct increased field costs associated with the acceleration. 11.3 If Construction Contractor encounters on the Project site any materials reasonably believed by Construction Contractor to be petroleum or petroleum related products or other hazardous or toxic substances which have not been rendered harmless, Construction Contractor immediately sh...
CONTRACT TIME AND TIME EXTENSIONS. 11.1 CONTRACTOR must diligently pursue the completion of the Work and coordinate the Work being done on the Project by its subcontractors and materialmen, as well as coordinating its Work with all work of others at the Project site, so that its Work or the work of others must not be delayed or impaired by any act or omission by CONTRACTOR or anyone for whom CONTRACTOR is liable. Unless expressly noted otherwise in the Contract Documents, CONTRACTOR must be solely responsible for all construction means, methods, techniques, sequences, and procedures, as well as coordination of all portions of the Work under the Contract Documents, and the coordination of OWNER'S suppliers and CONTRACTORS as set forth in Paragraph 14 below. 11.2 Should CONTRACTOR be obstructed or delayed in the prosecution of or completion of the Work as a result of unforeseeable causes beyond the control of CONTRACTOR, and not due to its fault or neglect, including but not restricted to acts of God or of the public enemy, acts of government, fires, floods, epidemics, quarantine regulation, strikes, lockouts, unusually severe weather conditions by comparison with the ten-year Marion County, Florida average, ground subsurface conditions not reasonably anticipated and not indicated by the most recent ground subsurface conditions reports of the project site, not reasonably anticipatable, CONTRACTOR must notify OWNER and DESIGN PROFESSIONAL in writing within forty-eight (48) hours after the commencement of such delay, stating the cause or causes thereof, or be deemed to have waived any right which CONTRACTOR may have had to request a time extension. 11.2.1 OWNER must have the right, at any time, whether or not CONTRACTOR is behind schedule, to order CONTRACTOR to accelerate its Work. In the event that OWNER orders CONTRACTOR to accelerate its Work and CONTRACTOR (i) is not behind schedule and (ii) believes that acceleration will increase the cost of performance, CONTRACTOR, must be required to submit a Claim for increase pursuant to Paragraph 13 below. Any such Claim must be based exclusively and solely on actual and direct net increased field costs, if any, associated with the acceleration. 11.3 If CONTRACTOR encounters on the Project site any materials reasonably believed by CONTRACTOR to be hazardous or toxic substances which have not been rendered harmless, CONTRACTOR immediately must (i) stop Work in the area affected and (ii) report the condition to OWNER in writing. If the Work is so stop...
CONTRACT TIME AND TIME EXTENSIONS. 15.1 CONSTRUCTION MANAGER shall diligently pursue the completion of the Work and coordinate the Work being done on the Project by its subcontractors and materialmen, as well as coordinating its Work with all work of others at the Project site, so that its Work or the work of others shall not be delayed or impaired by any act or omission by CONSTRUCTION MANAGER or anyone for whom CONSTRUCTION MANAGER is liable. Unless expressly noted otherwise in the Contract Documents, CONSTRUCTION MANAGER shall be solely responsible for all construction means, methods, techniques, sequences, and procedures, as well as coordination of all portions of the Work under the Contract Documents, and the coordination of OWNER’S suppliers and contractors. 15.2 Should CONSTRUCTION MANAGER be obstructed or delayed in the prosecution of, or completion of, the Work as a result of unforeseeable causes beyond the control of CONSTRUCTION MANAGER, and not due to its fault or neglect, including but not restricted to acts of God or of the public enemy, acts of government, fires, floods, epidemics, quarantine regulation, strikes, lockouts, unusually severe weather conditions by comparison with the ten‐year ▇▇▇ County, Florida, average (“Excusable Delays”), CONSTRUCTION MANAGER shall notify OWNER and Design Professional in writing within three (3) calendar days after the commencement of such delay, stating the cause or causes thereof, or be deemed to have waived any right which CONSTRUCTION MANAGER may have had to request a time extension. The CONSTRUCTION MANAGER shall not be entitled to an extension of the contract time or CONSTRUCTION MANAGER’S onsite General Conditions due to adverse weather conditions until the CONSTRUCTION MANAGER shall have demonstrated the loss of fifteen (15) calendar days affecting the critical path of the Work. The CONSTRUCTION MANAGER shall submit claims for the loss of days due to adverse weather conditions (both for the 15 calendar days described above and for all subsequent claims for lost days) within three (3) calendar days of the adverse weather conditions causing the claim, or the same shall be deemed waived. Any days for which delays due to adverse weather conditions have been claimed will not be approved unless the National Weather Service has indicated that severe weather was present. To the extent CONSTRUCTION MANAGER properly demonstrates in the manner described above the loss of more than fifteen (15) calendar days, CONSTRUCTION MANAGER shall be entitl...
CONTRACT TIME AND TIME EXTENSIONS. 11.1 Construction Contractor shall diligently pursue the completion of the Work and coordinate the Work being done on the Project by its subcontractors and materialmen, as well as coordinating its Work with all work of others at the Project site, so that its Work or the work of others shall not be delayed or impaired by any act or omission by Construction Contractor or anyone for whom Construction Contractor is responsible or liable. Unless expressly noted otherwise in the Contract Documents, Construction Contractor shall be solely responsible for all construction means, methods, techniques, sequences, and procedures, as well as coordination of all portions of the Work under the Contract Documents, coordination of trades and subcontractors, coordination of drawings to existing as-built conditions and site conditions, and the coordination of Owner’s suppliers and contractors as set forth in Section 14 of these General Terms and Conditions. 11.2 Should Construction Contractor actually be obstructed or delayed in the critical path of the prosecution of, or completion of, the Work as a result of unforeseeable causes: (i) acts of God or of the public enemy, (ii) acts of government, (iii) fires, (iv) floods, (v) epidemics, (vi) quarantine regulation, (vii) strikes, (viii) lockouts, or (ix) weather conditions abnormal for the period of time (as defined below) which exceed the aggregate number of days allotted for adverse weather conditions in Construction Contractor’s schedule approved by Owner, Construction Contractor shall notify Owner and Design Professional in writing within forty-eight (48) hours after the commencement of such delay (which time period shall control over any conflicting time periods specified elsewhere herein) stating the cause or causes thereof, or be deemed to have waived any right which Construction Contractor may have had to request a time extension therefor. “Abnormal for the period of time” for purposes of this Section means rain or bad weather (e.g. named tropical storms or hurricanes), only when such rain or bad weather is in excess of the ten
CONTRACT TIME AND TIME EXTENSIONS. In the event that the Contractor is obstructed or delayed in the prosecution of or in the completion of the
CONTRACT TIME AND TIME EXTENSIONS. 9.1. Contractor shall diligently pursue the completion of the Work and coordinate the Work being done on the Project by its subcontractors and material men, as well as coordinating its Work with all work of others at the Project Site, so that its Work or the work of others shall not be delayed or impaired by any act or omission of Contractor. Contractor shall be solely responsible for all construction means, methods, techniques, sequences, and procedures, as well as coordination of all portions of the Work under the Contract Documents. 9.2. Should Contractor be obstructed or delayed in the prosecution of or completion of the Work as a result of unforeseeable causes beyond the control of Contractor, and not due to its fault or neglect, including but not restricted to acts of God or of the public enemy, acts of government, fires, floods, epidemics, quarantine regulations, strikes or lockouts, Contractor shall notify the County in writing within forty-eight (48) hours after the commencement of such delay. Written supporting data with specific details of Contractor operations, which were delayed, shall be submitted to the County within fifteen (15) calendar days after the occurrence of the delay, unless the County grants additional time in writing for such submittals, or else the Contractor shall be deemed to have waived any right which Contractor may have had to request a time extension. 9.3. No interruption, interference, inefficiency, suspension or delay in the commencement or 9.4. Requests for delays due to adverse weather conditions shall meet all of the following conditions: 9.4.1. Contractor notified the County in writing within forty-eight (48) hours of the delay. 9.4.2. The weather was unusual as documented by supporting data. 9.4.3. The weather did have an adverse impact on the contractor’s schedule (critical path only). 9.4.4. The Contractor and inspector’s daily logs corroborate the adverse impact. Where a conflict exists between the weather data and the daily reports, the daily reports will take precedence.

Related to CONTRACT TIME AND TIME EXTENSIONS

  • Contract Time The period of time established for completion of the Project by the Contract Documents. Contract Time commences upon the date specified in the Proceed Order and ends upon the Material Completion and Occupancy Date, as it may be amended.

  • Contract Times The number of days or the dates stated in the Agreement to: (i) achieve Substantial Completion; and (ii) complete the Work so that it is ready for final payment as evidenced by Architect's or Owner’s representative’s written recommendation of final payment.

  • Time Extensions 2.03.1 If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).

  • TIME OF COMMENCEMENT AND COMPLETION 2.1 The Contractor shall commence the Work upon the date established in the Notice to Proceed. 2.2 The Contractor shall achieve Final Completion, as defined in Section 105.01, Contract Time, Notice of Contract Execution and Notice to Proceed of the Loudoun County Revisions to the ▇▇▇▇ ▇▇▇▇ ▇▇▇▇ & Bridge Specifications, Division I - General Provisions, within one hundred and eighty (180) calendar days from the date specified in the Notice to Proceed. This time period shall be designated the Contract Time. The Notice to proceed will be issued approximately than thirty (30) days after the execution of this agreement. The Contractor agrees that the time for completion of the Work as described in the Contract Documents shall govern unless specifically amended in writing by the County, and that no claims for early completion are allowed to be presented by the Contractor to the County. 2.3 The County specifies that time is of the essence under this Contract. Time being of the essence, it is essential to the County that Contract work will be completed within the Contract Time. The County and the Contractor agree that damages for failure to complete the work within the Contract Time are not susceptible to exact determination but that $600 per day is in proportion to the actual loss that the County would suffer from such delay. Therefore, the Contractor will pay the County on demand $600 per day for each and every day beyond the one hundred and eighty (180) calendar days, or modified date of completion, that the County determines that work is not complete, as damages caused by such delay and not as a penalty. The County shall be entitled to offset liquidated damages against any sum owed by the County to the Contractor under this Contract. 2.4 The amount of liquidated damages set forth in Articles 2.3 above shall be assessed cumulatively. This provision for liquidated damages does not bar County's right to enforce other rights and remedies against Contractor, which are otherwise legally enforceable, including but not limited to, specific performance or injunctive relief. 2.5 The Contractor hereby waives any defense as to the validity of any liquidated damages stated in this Agreement as they may appear on grounds that such liquidated damages are void as penalties or are not reasonably related to actual damages.