Construction Supervision. 6.4.1 Unless waived by the Contracting Authority in writing, the DB shall provide continuous supervision at the Site by a competent superintendent when any Work is being performed and the DB’s superintendent shall not be involved with any work other than the Project. 6.4.2 The DB’s project manager and superintendent shall each have the responsibility and authority to act on behalf of the DB. All communications to the DB’s project manager or superintendent shall be binding as if given directly to the DB. 6.4.3 For all Subcontracts in excess of $200,000, the DB shall submit an outline of the qualifications and experience of the Subcontractor’s proposed project manager and proposed superintendent, including references, to the Contracting Authority no less than 10 days before the Subcontractor is scheduled to begin Work on the Site. For all other Subcontracts, upon receiving a request from the Contracting Authority, the DB shall submit an outline of the qualifications and experience of the Subcontractor’s proposed project manager and proposed superintendent, including references, to the Contracting Authority. 6.4.3.1 The Contracting Authority may reject the Subcontractor’s proposed project manager or proposed superintendent. If the Contracting Authority does not notify the DB of the rejection within 30 days after receiving the required information, it shall indicate that the Contracting Authority has no objection, but does not affect the Contracting Authority’s rights under Section 6.11.2 or any other provision relative to that project manager or superintendent. 6.4.3.2 If the Contracting Authority rejects the Subcontractor’s proposed project manager or proposed superintendent, the DB shall cause the Subcontractor to replace the project manager or superintendent (as appropriate) with someone acceptable to the Contracting Authority at no additional cost. 6.4.4 The DB and its Subcontractors subject to Section 6.4.3 shall not replace their respective project managers or superintendents without prior written approval of the Contracting Authority. 6.4.4.1 If the DB or a Subcontractor subject to Section 6.4.3 proposes to change its project manager or superintendent, the DB shall submit written justification for the change to the Contracting Authority, along with the name and qualifications of the proposed replacement. 6.4.4.2 The procedure provided in Section 6.4.3 shall be conducted to evaluate the DB or Subcontractor’s (as applicable) proposed replacement project manager or superintendent.
Appears in 2 contracts
Sources: Professional Services, Professional Services
Construction Supervision. 6.4.1 Unless waived by the Contracting Authority in writing, the DB CM shall provide continuous supervision at the Site by a competent superintendent when any Work is being performed performed, and the DBCM’s superintendent shall not be involved with any work other than the Project.
6.4.2 The DBCM’s project manager and superintendent shall each have the responsibility and authority to act on behalf of the DBCM. All communications to the DBCM’s project manager or superintendent shall be binding as if given directly to the DBCM.
6.4.3 For all Subcontracts in excess of $200,000, the DB CM shall submit an outline of the qualifications and experience of the Subcontractor’s proposed project manager and proposed superintendent, including references, to the Contracting Authority no less than 10 ten days before the Subcontractor is scheduled to begin Work on the Site. For all other Subcontracts, upon receiving a request from the Contracting Authority, the DB CM shall submit an outline of the qualifications and experience of the Subcontractor’s proposed project manager and proposed superintendent, including references, to the Contracting Authority.
6.4.3.1 The Contracting Authority may reject the Subcontractor’s proposed project manager or proposed superintendent. If the Contracting Authority does not notify the DB CM of the rejection within 30 days after receiving the required information, it shall indicate that the Contracting Authority has no objection, but does not affect the Contracting Authority’s rights under Section 6.11.2 6.10.2 or any other provision relative to that project manager or superintendent.
6.4.3.2 If the Contracting Authority rejects the Subcontractor’s proposed project manager or proposed superintendent, the DB CM shall cause the Subcontractor to replace the project manager or superintendent (as appropriate) with someone acceptable to the Contracting Authority at no additional cost.
6.4.4 The DB CM and its Subcontractors subject to Section 6.4.3 shall not replace their respective project managers or superintendents without prior written approval of the Contracting Authority.
6.4.4.1 If the DB CM or a Subcontractor subject to Section 6.4.3 proposes to change its project manager or superintendent, the DB CM shall submit written justification for the change to the Contracting Authority, along with the name and qualifications of the proposed replacement.
6.4.4.2 The procedure provided in Section 6.4.3 shall be conducted to evaluate the DB CM or Subcontractor’s (as applicable) proposed replacement project manager or superintendent.
Appears in 2 contracts
Sources: Construction Manager at Risk Agreement, Professional Services
Construction Supervision. 6.4.1 Unless waived by the Contracting Authority in writing, the DB Contractor shall provide continuous supervision at the Site by a competent superintendent when any Work is being performed and the DBContractor’s superintendent shall not be involved with any work other than the Project.
6.4.2 The DBContractor’s project manager and superintendent shall each have the responsibility and authority to act on behalf of the DBContractor. All communications to the DBContractor’s project manager or superintendent shall be binding as if given directly to the DBContractor.
6.4.3 The Contractor shall submit an outline of the qualifications and experience of the Contractor’s proposed project manager and proposed superintendent, including references, to the Contracting Authority no less than 10 days of the Notice to Proceed. For all Subcontracts in excess of $200,000, and for all other Subcontracts on request from the DB Contracting Authority, the Contractor shall submit an outline of the qualifications and experience of the Subcontractor’s proposed project manager and proposed superintendent, including references, to the Contracting Authority no less than 10 days before the Subcontractor is scheduled to begin Work on the Site. For all other Subcontracts, upon receiving a request from the Contracting Authority, the DB shall submit an outline of the qualifications and experience of the Subcontractor’s proposed project manager and proposed superintendent, including references, to the Contracting Authority.
6.4.3.1 The Contracting Authority may reject the Contractor’sContractor or the Subcontractor’s proposed project manager or proposed superintendent. If the Contracting Authority does not notify the DB Contractor of the rejection within 30 days after receiving the required information, it shall indicate that the Contracting Authority has no objection, but does not affect the Contracting Authority’s rights under Section 6.11.2 6.12.2 or any other provision relative to that project manager or superintendent.
6.4.3.2 If the Contracting Authority rejects the Contractor’sContractor or the Subcontractor’s proposed project manager or proposed superintendent, the DB Contractor shall replace, or cause the Subcontractor to replace the project manager or superintendent (as appropriate) with someone acceptable to the Contracting Authority at no additional cost.
6.4.4 The DB Contractor and its Subcontractors subject to Section 6.4.3 shall not replace their respective project managers or superintendents without prior written approval of the Contracting Authority.
6.4.4.1 If the DB Contractor or a Subcontractor subject to Section 6.4.3 proposes to change its project manager or superintendent, the DB Contractor shall submit written justification for the change to the Contracting Authority, along with the name and qualifications of the proposed replacement.
6.4.4.2 The procedure provided in Section 6.4.3 shall be conducted to evaluate the DB Contractor's or Subcontractor’sContractor or Subcontractor’s (as applicable) proposed replacement project manager or superintendent.
Appears in 2 contracts
Sources: General Contracting Agreement, Standard Requirements for Public Facility Construction
Construction Supervision. 6.4.1 Unless waived by the Contracting Authority in writing, the DB Contractor shall provide continuous supervision at the Site by a competent superintendent when any Work is being performed and the DBContractor’s superintendent shall not be involved with any work other than the Project.
6.4.2 The DBContractor’s project manager and superintendent shall each have the responsibility and authority to act on behalf of the DBContractor. All communications to the DBContractor’s project manager or superintendent shall be binding as if given directly to the DBContractor.
6.4.3 The Contractor shall submit an outline of the qualifications and experience of the Contractor’s proposed project manager and proposed superintendent, including references, to the Contracting Authority no less than 10 days of the Notice to Proceed. For all Subcontracts in excess of $200,000, and for all other Subcontracts on request from the DB Contracting Authority, the Contractor shall submit an outline of the qualifications and experience of the Subcontractor’s proposed project manager and proposed superintendent, including references, to the Contracting Authority no less than 10 days before the Subcontractor is scheduled to begin Work on the Site. For all other Subcontracts, upon receiving a request from the Contracting Authority, the DB shall submit an outline of the qualifications and experience of the Subcontractor’s proposed project manager and proposed superintendent, including references, to the Contracting Authority.
6.4.3.1 The Contracting Authority may reject the Contractor or Subcontractor’s proposed project manager or proposed superintendent. If the Contracting Authority does not notify the DB Contractor of the rejection within 30 days after receiving the required information, it shall indicate that the Contracting Authority has no objection, but does not affect the Contracting Authority’s rights under Section 6.11.2 6.12.2 or any other provision relative to that project manager or superintendent.
6.4.3.2 If the Contracting Authority rejects the Contractor or Subcontractor’s proposed project manager or proposed superintendent, the DB Contractor shall replace, or cause the Subcontractor to replace the project manager or superintendent (as appropriate) with someone acceptable to the Contracting Authority at no additional cost.
6.4.4 The DB Contractor and its Subcontractors subject to Section 6.4.3 shall not replace their respective project managers or superintendents without prior written approval of the Contracting Authority.
6.4.4.1 If the DB Contractor or a Subcontractor subject to Section 6.4.3 proposes to change its project manager or superintendent, the DB Contractor shall submit written justification for the change to the Contracting Authority, along with the name and qualifications of the proposed replacement.
6.4.4.2 The procedure provided in Section 6.4.3 shall be conducted to evaluate the DB Contractor or Subcontractor’s (as applicable) proposed replacement project manager or superintendent.
Appears in 1 contract
Sources: Standard Requirements for Public Facility Construction
Construction Supervision. 6.4.1 Unless waived by the Contracting Authority in writing, the DB CM shall provide continuous supervision at the Site by a competent superintendent when any Work is being performed and the DBCM’s superintendent shall not be involved with any work other than the Project.
6.4.2 The DBCM’s project manager and superintendent shall each have the responsibility and authority to act on behalf of the DBCM. All communications to the DBCM’s project manager or superintendent shall be binding as if given directly to the DBCM.
6.4.3 For all Subcontracts in excess of $200,000, the DB CM shall submit an outline of the qualifications and experience of the Subcontractor’s proposed project manager and proposed superintendent, including references, to the Contracting Authority no less than 10 days before the Subcontractor is scheduled to begin Work on the Site. For all other Subcontracts, upon receiving a request from the Contracting Authority, the DB CM shall submit an outline of the qualifications and experience of the Subcontractor’s proposed project manager and proposed superintendent, including references, to the Contracting Authority.
6.4.3.1 The Contracting Authority may reject the Subcontractor’s proposed project manager or proposed superintendent. If the Contracting Authority does not notify the DB CM of the rejection within 30 days after receiving the required information, it shall indicate that the Contracting Authority has no objection, but does not affect the Contracting Authority’s rights under Section 6.11.2 6.12.2 or any other provision relative to that project manager or superintendent.
6.4.3.2 If the Contracting Authority rejects the Subcontractor’s proposed project manager or proposed superintendent, the DB CM shall cause the Subcontractor to replace the project manager or superintendent (as appropriate) with someone acceptable to the Contracting Authority at no additional cost.
6.4.4 The DB CM and its Subcontractors subject to Section 6.4.3 shall not replace their respective project managers or superintendents without prior written approval of the Contracting Authority.
6.4.4.1 If the DB CM or a Subcontractor subject to Section 6.4.3 proposes to change its project manager or superintendent, the DB CM shall submit written justification for the change to the Contracting Authority, along with the name and qualifications of the proposed replacement.
6.4.4.2 The procedure provided in Section 6.4.3 shall be conducted to evaluate the DB CM’s or Subcontractor’sCM or Subcontractor’s (as applicable) proposed replacement project manager or superintendent.
Appears in 1 contract
Sources: Cm at Risk Contract