Construction Manager's Representative. Construction Manager designates the individual listed below as its Construction Manager's Representative to provide direct interface with Owner with respect to Construction Manager's responsibilities: ▇▇▇▇▇▇▇ ▇▇▇▇▇▇, Construction Manager's, Project Manager. Exhibit C- Project Assignment Page 3 of 4 Exhibit C-1 – List of Contract Documents Page 1 of 2 Exhibit C-1 – List of Contract Documents Page 2 of 2 February 24, 2022 School Board of Brevard County 2725 Judge ▇▇▇▇ ▇▇▇▇▇▇▇▇ Way HCI Project 2204640800 PO# BPS Satellite HS Food Service Remodel Viera , FL 32940-6699 Attn: ▇▇▇▇▇ ▇▇▇▇▇ Subject: CM GMP Proposal for Satellite High School Food Service Remodel Dear ▇▇▇▇▇, At your request we are providing our proposal for Construction Management Services for the subject project. All work will be subject to terms and conditions as stipulated in the Continuing Contract for Construction Management Services between Heard Construction Inc. and the School Board of Brevard County and RZK Architects/DDC Engineering drawings and specifications dated 1/18/22 including Addendum 1 dated 2/7/22 & Addendum 2 dated 2/11/22 outlining the following scope of work: 1. Demo and remove existing walls, ceilings & flooring per plan. 2. Removal & replacement of concrete slab to accommodate new plumbing, mechanical & electrical installations. 3. Installation of new partition and exterior walls per plan. 4. Installation of new doors, frames and hardware. 5. Installation of new storefront windows and doors, including ready access windows. 6. Installation of new floor and wall finishes. 7. Installation of new acoustical & drywall ceilings. 8. Patching and painting. 9. Installation of specified accessories and corner guards. 10. Installation of new Room signs. 11. Installation of new plumbing per plan. 12. Installation of new HVAC per plan. 13. Installation of new electrical and Fire Alarm. per plan. 14. Installation of new conduit for Data Drops at Serving lines. 15. Fire sprinkler system and associated piping modified to accommodate new Plan.. HCI’s GMP to provide Construction Management Services is $1,277,418.70. We have enclosed our “SBBC GMP Estimate” detailing the costs for the project. We have included supervision for the duration of the project. A $55,000.00 Project Contingency Allowance without fee markup is included. ▇▇▇▇▇▇▇ ▇▇▇▇▇▇ will be HCI’s Project Manager and ▇▇▇▇▇ ▇▇▇▇▇▇▇ will be HCI’s full time on-site Superintendent. We will provide estimated Owner Direct Purchases (ODP’s), including sales tax, within a few days of your acceptance of this Proposal. This work will begin on receipt of your “Authorization to Proceed” and will be substantially completed during the upcoming summer recess. It is our intention to substantially complete the project by 7/31/22. The Preliminary Project Schedule is as follows: Board approval: 3/22/22 Notice To Proceed issued - 3/23/22 Start construction - 5/19/22 Substantial Completion - 7/31/22 Final Completion - 10/31/22 We acknowledge that if Substantial Completion is not attained before 7/31/22 Liquidated Damages in the amount of $1000.00 per day will be imposed. If HCI fails to attain Substantial Completion the Final Completion Date shall be reset to the ninetieth (90th) day after the date of actual Substantial Completion and Liquidated Damaged will be imposed at $500.00 per day. QUALIFICATIONS, CLARIFICATIONS AND EXCLUSIONS 1. Any Building Official requirements not specifically included in this proposal are excluded. 2. Only work described in the above scope of work is included in this project. 3. We have excluded HCI Commissioning costs.
Appears in 1 contract
Construction Manager's Representative. Construction Manager designates the individual listed below as its Construction Manager's Representative to provide direct interface with Owner with respect to Construction Manager's responsibilities: ▇▇▇▇▇▇▇ ▇▇▇▇▇▇, Construction Manager's, Project Manager. Exhibit C- Project Assignment Page 3 of 4 Exhibit C-1 – List of Contract Documents Page 1 of 2 Exhibit C-1 – List of Contract Documents Page 2 of 2 February 241 March 4, 2022 School Board of Brevard County 2725 Judge ▇▇▇▇ ▇▇▇▇▇▇▇▇ Way HCI Project 2204640800 ▇▇▇▇▇▇▇▇▇▇ PO# BPS Satellite HS MIHS Food Service Remodel Viera , FL 32940-6699 Attn: ▇▇▇▇▇ ▇▇▇▇▇ Subject: CM GMP Proposal for Satellite ▇▇▇▇▇▇▇ Island High School Food Service Remodel - Revised 2 Dear ▇▇▇▇▇, At your request we are providing our proposal for Construction Management Services for the subject project. All work will be subject to terms and conditions as stipulated in the Continuing Contract for Construction Management Services between Heard Construction Inc. and the School Board of Brevard County and RZK Architects/DDC Engineering drawings and specifications dated 1/18/22 including Addendum 1 dated 2/7/22 & Addendum 2 dated 2/11/22 1/28/22 outlining the following scope of work:
1. Demo and remove existing walls, ceilings & flooring per plan.
2. Removal & and replacement of concrete slab to accommodate new walls, plumbing, mechanical & electrical installations.
3. Installation of new partition and exterior walls per plan.
4. Installation of new doors, frames and hardwarehardware per Plan.
5. Installation of new storefront windows and doors, including ready access windows.
6. Installation of new floor and wall finishestile finishes per Plan.
7. Installation of new acoustical & drywall ceilingsceilings per Plan.
8. Patching Painting renovated area walls, soffit/ceilings, doors and paintingframes per Plan.
9. Installation of specified accessories and stainless steel corner guards.
10. Installation of 12 new Room signssigns per Plan.
11. Installation of new plumbing per plan.
12. Installation of new HVAC per plan.
13. Installation of new electrical and Fire Alarm. per plan.
14. Installation of new conduit for Data Drops at Serving lines.
15. Fire sprinkler system and associated piping modified to accommodate new Plan.. Installations. HCI’s GMP to provide Construction Management Services is $1,277,418.701,021,124.97. We have enclosed our “SBBC GMP Estimate” detailing the costs for the project. We have included supervision for the duration of the project. A $55,000.00 50,000.00 Project Contingency Allowance without fee markup is included. ▇▇▇▇▇▇▇ ▇▇▇▇▇▇ will be HCI’s Project Manager and ▇▇▇▇▇▇▇ ▇▇▇▇▇▇▇▇▇▇ will be HCI’s full time on-site Superintendent. We will provide estimated Owner Direct Purchases (ODP’s), including sales tax, within a few days of your acceptance of this Proposal. This work will begin on receipt of your “Authorization to Proceed” and will be substantially completed during the upcoming summer recess. It is our intention to substantially complete the project by 7/31/22. The Preliminary Project Schedule is as follows: Board approval: 3/22/22 Notice To Proceed issued - 3/23/22 Start construction - 5/19/22 5/31/22 Substantial Completion - 7/31/22 Final Completion - 10/31/22 We acknowledge that if Substantial Completion is not attained before 7/31/22 Liquidated Damages in the amount of $1000.00 per day will be imposed. If HCI fails to attain Substantial Completion the Final Completion Date shall be reset to the ninetieth (90th) day after the date of actual Substantial Completion and Liquidated Damaged will be imposed at $500.00 per day. QUALIFICATIONS, CLARIFICATIONS AND EXCLUSIONS
1. Any Building Official requirements not specifically included in this proposal are excluded.
2. Only work described in the above scope of work is included in this project.
3. We have excluded HCI Commissioning costs.
4. The Fire Sprinkler installation excludes raising any mains or branch lines.
5. HCI will move the existing ice machine and re-install in the new location.
6. The mop sink is not denoted on the Plumbing Fixture Schedule. HCI will install a molded stone basin with stainless steel drain.
7. We have included a $15,000.00 Allowance for the Fire Alarm work. Simplex was non responsive at Bid Time.
8. We have included a $25,000.00 allowance for BAS Controls. No pricing was received at Bid Time.
Appears in 1 contract
Construction Manager's Representative. Construction Manager designates the individual listed below as its Construction Manager's Representative to provide direct interface with Owner with respect to Construction Manager's responsibilities: ▇▇▇▇▇▇▇ ▇▇▇▇▇▇, Construction Manager's, Project Manager. Exhibit C- Project Assignment Page 3 of 4 Exhibit C-1 – List of Contract Documents Page 1 of 2 Exhibit C-1 – List of Contract Documents Page 2 of 2 1 February 248, 2022 School Board of Brevard County 2725 Judge ▇▇▇▇ ▇▇▇▇▇▇▇▇ Way HCI Project 2204640800 2204641200 PO# BPS Satellite Bayside HS Food Service Remodel Viera Elevated Walkway Structural Repairs Building ▇▇▇ ▇▇▇▇▇ ▇ ▇▇▇▇▇ , FL 32940▇▇ ▇▇▇▇▇-6699 ▇▇▇▇ Attn: ▇▇▇▇▇ ▇▇▇▇▇▇ Subject: CM GMP Proposal for Satellite High School Food Service Remodel Bayside HS Elevated Walkway Structural Repairs Building 600 Dear ▇▇▇▇▇, At your request we are providing our proposal for Construction Management Services for the subject project. All work will be subject to terms and conditions as stipulated in the Continuing Contract for Construction Management Services between Heard Construction Inc. and the School Board of Brevard County and RZK Architects/DDC Engineering based of the TLC Reported dated 12/16/2021 along with the ▇▇▇▇▇▇▇▇ ▇▇▇▇▇▇ Architecture drawings and specifications dated 1/18/22 including Addendum 1 dated 2/7/22 & Addendum 2 dated 2/11/22 01/21/2022 outlining the following scope of work:
1. Demo and remove existing walls, ceilings Maintain temporary fencing around construction site to protect students & flooring per planstaff from construction activities.
2. Removal & replacement Selective demolition to include removal of concrete slab to accommodate new plumbing, mechanical & electrical installationsfire proofing per Plan.
3. Installation of new partition and exterior walls Remove visible rust from from steel members, prime & paint per planPlan.
4. Installation of Furnish and install new doors, frames and hardware3-5/8” structural 18 gauge metal framing with 5/8” Densglass on soffits.
5. Installation of new storefront windows Provide and doors, install (▇▇▇▇▇▇ ALPRO) Powder Coated ivory ceiling panels including ready access windowssite specific shop drawings.
6. Installation of new floor Direct apply synthetic stucco to Densglass Sheating. Backstop NT Waterproofing. Finish and wall finishescolor TBD.
7. Installation of Paint back wall, columns and new acoustical & drywall ceilingsstucco areas.
8. Patching Provide and paintinginstall Stoneguard TM to 2nd Floor Walkway per Plan.
9. Installation of specified accessories Remove and corner guards.
10. Installation of new Room signs.
11. Installation of new plumbing per plan.
12. Installation of new HVAC per plan.
13. Installation of new electrical and Fire Alarm. per plan.
14. Installation of new conduit for Data Drops at Serving lines.
15. Fire sprinkler system and associated piping modified reinstall handrail to accommodate new walkway Stoneguard TM Application per Plan.. . HCI’s GMP to provide Construction Management Services is $1,277,418.70242,569.52. We have enclosed our “SBBC GMP Estimate” detailing the costs for the project. We have included supervision for the duration of the project. A $55,000.00 25,000.00 Project Contingency Allowance without fee markup is included. ▇▇▇▇▇▇▇ ▇▇▇▇▇▇ will be HCI’s Project Manager and ▇▇▇▇▇ ▇▇▇▇▇▇▇ will be HCI’s full time on-site SuperintendentSuperintendent is To Be Determined (TBD). We will provide estimated Estimated Owner Direct Purchases (ODP’s), including sales tax, within a few days of your acceptance of this Proposalwill be provided under separate cover. This work will begin on receipt of your “Authorization to Proceed” and will be substantially completed during the upcoming summer recess. It is our intention to substantially complete the project by 7/31/227/31/2022. The Preliminary Project Schedule is as follows: Board approval: 3/22/22 3/8/22 Notice To Proceed issued - 3/23/22 3/9/22 Purchase Order Issued - 4/4/22 Start construction - 5/19/22 6/1/22 Substantial Completion - 7/31/22 Final Completion - 10/31/22 We acknowledge that if Substantial Completion is not attained before 7/31/22 Liquidated Damages in the amount of $1000.00 per day will be imposed. If HCI fails to attain Substantial Completion the Final Completion Date shall be reset to the ninetieth (90th) day after the date of actual Substantial Completion and Liquidated Damaged will be imposed at $500.00 per day. QUALIFICATIONS, CLARIFICATIONS AND EXCLUSIONS
1. Any Building Official requirements not specifically included in this proposal are excluded.
2. Only work described in the above scope of work is included in this project.
3. We have excluded HCI Commissioning costs.
Appears in 1 contract
Construction Manager's Representative. Construction Manager designates the individual listed below as its Construction Manager's Representative to provide direct interface with Owner with respect to Construction Manager's responsibilities: ▇▇▇▇▇▇ ▇▇ ▇▇▇▇▇▇, Construction Manager's, Project Manager. Exhibit C- Project Assignment Page 3 of 4 Exhibit C-1 – List of Contract Documents Page 1 of 2 Exhibit C-1 – List of Contract Documents Page 2 of 2 February 24August 16, 2022 HCI Project 2204641700 PO# 12203274 School Board of Brevard County 2725 Judge ▇▇▇▇ ▇▇▇▇▇▇▇▇ Way HCI Project 2204640800 PO# BPS Satellite HS Food Service Remodel PC Cape View Playground Improvements Viera , FL 32940-6699 Attn: ▇▇▇▇▇ ▇▇▇▇▇ Subject: CM GMP Proposal for Satellite High Cape View Elementary School Food Service Remodel Playground Improvements_REV Dear ▇▇▇▇▇, At your request we are providing our proposal for Construction Management Services for the subject project. All work will be subject to terms and conditions as stipulated in the Continuing Contract for Construction Management Services between Heard Construction Inc. and the School Board of Brevard County and RZK Architects/DDC Engineering drawings and specifications EJH Landscape Architecture Drawings dated 1/18/22 including Addendum 1 dated 2/7/22 & Addendum 2 dated 2/11/22 6/16/22 outlining the following scope of workWork:
1. Demo and remove Install DOT silt fence around 2 existing walls, ceilings & flooring per plansurface inlet structures only.
2. Removal & replacement Import and install premium Command Compost to depth of concrete slab to accommodate 1” over entire new plumbing, mechanical & electrical installationssod area.
3. Installation of new partition Roto Till 2X directions Command Compost into existing soils and exterior walls per plandecaying biomass to approx. 5”-6” depth.
4. Installation of new doors, frames Compact and hardwaregrade site to direct water to 2 existing storm water inlets located within the field area.
5. Installation of Install new storefront windows and doors, including ready access windowsirrigation system per plans.
6. Installation of new floor and wall finishesFinish surface grade for smoothness in preparation for sod.
7. Installation of new acoustical & drywall ceilingsTake soil test, add necessary pre-plant nutrients.
8. Patching and painting.Install certified 419 Bermuda sprigs
9. Installation of specified accessories Execute 90 day complete grow in program for Bermuda grass turf, including top dressing, rolling, mowing, any and corner guardsall weed/pest controls, etc.
10. Installation of new Room signsSite clean up.
11. Installation of Wet Tap exiting irrigation water line . Install new plumbing per planwater meter for irrigation system.
12. Installation of a 20 AMP 240/120 Volt Circuit from existing mobile home to the new HVAC per planirrigation control panel mounted to concrete post with stainless steel brackets.
13. Installation of new electrical and Fire AlarmUnderground utility locates will be provided for this project. per plan.
14. Installation of new conduit for Data Drops at Serving lines.
15. Fire sprinkler system and associated piping modified to accommodate new Plan.. HCI’s GMP to provide Construction Management Services is $1,277,418.70127,569.00. We have shown and additive alternate of $14,785.90 to provide full rolled sod and a thirty day grow in period. We have enclosed our “SBBC GMP Estimate” detailing the costs for the this project. We have not included supervision for the duration of the project, only Project Manager site visits to monitor progress. A $55,000.00 5,000.00 Project Contingency Allowance without fee markup is included. ▇▇▇▇▇▇▇ ▇▇▇▇▇▇ will be HCI’s Project Manager and ▇▇▇▇▇ ▇▇▇▇▇▇▇ will be HCI’s full time on-site SuperintendentProject Manager for the Project. We If a waiver is required for the reclaimed water during the grow in period it is the responsibility of the School Board to obtain the waiver from the City of Cape Canaveral. HCI will provide estimated be happy to attend a kick off meeting with the City of Cape Canaveral. There will be no Owner Direct Purchases (ODP’s), including sales tax, within a few days of your acceptance of ) for this ProposalProject. This work will begin on receipt of your “Authorization to Proceed” and will be substantially completed during the upcoming summer recess. It is our intention to substantially complete the project by 7/31/2212/31/22. The Preliminary Project Schedule is as follows: Board approval: 3/22/22 9/8/2022 Notice To Proceed issued - 3/23/22 9/9/2022 Start construction - 5/19/22 9/15/2022 Substantial Completion - 7/31/22 12//31/22 Final Completion - 10/31/22 1/31/23 We acknowledge that if Substantial Completion is not attained before 7/31/22 12/31/222 Liquidated Damages in the amount of $1000.00 per day will be imposed. If HCI fails to attain Substantial Completion the Final Completion Date shall be reset to the ninetieth (90th) day sixty days after the date of actual Substantial Completion and Liquidated Damaged will be imposed at $500.00 per day. QUALIFICATIONS, CLARIFICATIONS AND EXCLUSIONS
1. Any Building Official requirements not specifically included in this proposal are excluded.
2. Only work described in the above scope of work is included in this project.
3. We have All costs associated with the removal of hazardous materials, if encountered, is excluded.
4. A&E Fees are excluded HCI Commissioning costs5. Installation of any silt fence around the property as none was specified. Silt fence will be installed around both existing concrete inlets only.
Appears in 1 contract
Sources: Guaranteed Maximum Price Agreement
Construction Manager's Representative. Construction Manager designates the individual listed below as its Construction Manager's Representative to provide direct interface with Owner with respect to Construction Manager's responsibilities: ▇▇▇▇▇▇▇ ▇▇▇▇▇▇, Construction Manager's, 's Project Manager. Exhibit C- Project Assignment Page 3 of 4 Exhibit C-1 – List of Contract Documents Page 1 of 2 Exhibit C-1 – List of Contract Documents Page 2 of 2 February 24March 25, 2022 2019 School Board of Brevard County 2725 2700 Judge ▇▇▇▇ ▇▇▇▇▇▇▇▇ Way HCI Project 2204640800 1904640100 PO# BPS Satellite Eau Gallie HS Food Service Remodel Kitchen Renovation Viera , FL 32940-6699 Attn: ▇▇▇▇ ▇▇ ▇▇▇▇▇ Subject: CM GMP Proposal for Satellite High School Food Service Remodel Eau Gallie HS Cafeteria & Kitchen Renovation - Rev.3 Dear ▇▇▇▇▇, At your request we are providing our proposal for Construction Management Services for the subject project. All work will be subject to terms and conditions as stipulated in the Continuing Contract for Construction Management Services between Heard Construction Inc. and the School Board of Brevard County and RZK ArchitectsTsark Architecture/DDC Engineering Engineering, Inc. drawings and specifications dated 1/18/22 including Addendum 1 dated 2/7/22 2/1/2019 & Addendum 2 dated 2/11/22 2/8/2019 outlining the following scope of work:
1. Demo and remove existing walls, ceilings & flooring per plan.
2. Removal & and replacement of concrete slab to accommodate new walls, plumbing, mechanical & electrical installations.
3. Installation of new partition and exterior walls per plan.
4. Installation of new doors, frames and hardware.
5. Installation of new storefront windows and doors, including ready access windows.
6. Installation of new floor and wall finishes. Porcelain floor tile is excluded in the north and south Dining Rooms.
76. Installation of new acoustical & drywall ceilings.
87. Patching and painting.
98. Installation of specified accessories and corner guards.
9. Completion of new serving line handrails and overhead roll-up security gates.
10. Installation of new Room signsdoor signage.
11. Installation of new plumbing per plan.
12. Installation of new HVAC per plan.
13. Installation of new electrical and Fire Alarm. per plan.
14. Installation of new conduit for Data Drops at Serving lines.
15. Allowance for Fire sprinkler system and associated piping modified to accommodate new Plan.. piping, riser and back-flow preventer.
16. Allowance for Build out of Offices in room 14-105 17. HCI’s detailed Guaranteed Maximum Price Proposal will be provided under separate cover. HCI’s GMP to provide Construction Management Services is $1,277,418.701,429,766.573. We have enclosed our “SBBC GMP Estimate” detailing the costs for the project. We have included supervision for the duration of the project. A $55,000.00 50,000.00 Project Contingency Allowance without fee markup is included. ▇▇▇▇▇▇▇ ▇▇▇▇▇▇ will be HCI’s Project Manager and ▇▇▇▇▇ ▇▇▇▇▇▇▇ will be HCI’s full time on-site Superintendent. We will provide estimated Owner Direct Purchases (ODP’s), including sales tax, within a few days of your acceptance of this Proposal. This work will begin on receipt of your “Authorization to Proceed” and will be substantially completed during the upcoming summer recess. It is our intention to substantially complete the project by 7/31/228/9/19. The Preliminary Project Schedule is as follows: Board approval: 3/22/22 4/9/10 Notice To Proceed issued - 3/23/22 4/10/19 Purchase Order Issued - 4/17/19 Start construction - 5/19/22 5/1/19 Substantial Completion - 7/31/22 Final Completion - 10/31/22 8/9/19 We acknowledge that if Substantial Completion is not attained before 7/31/22 8/9/19 Liquidated Damages in the amount of $1000.00 per day will be imposed. If HCI fails to attain Substantial Completion the Final Completion Date shall be reset to the ninetieth (90th) day after the date of actual Substantial Completion and Liquidated Damaged will be imposed at $500.00 per day. QUALIFICATIONS, CLARIFICATIONS AND EXCLUSIONS
1. Any Building Official requirements not specifically included in this proposal are excluded.
2. Only work described in the above scope of work is included in this project.
3. We have excluded HCI Commissioning costs. We thank you for this opportunity and look forward to your approval to proceed with this project. If you have any questions please give me a call at (▇▇▇) ▇▇▇-▇▇▇▇ at your earliest convenience. Sincerely, ▇▇▇▇▇ ▇▇▇▇ Heard Construction, Inc. Project Executive 80 hrs 93.91 7,512.80 Project Manager 200 hrs 70.25 14,050.00 Project Accountant 60 hrs 51.97 3,118.20 Project Clerk 60 hrs 20.86 1,251.60 Project Estimator 16 hrs 43.53 696.48 General Superintendent 16 hrs 68.05 1,088.80 Project Superintendent 696 hrs 57.55 40,054.80 Safety Coordinator 16 hrs 69.19 1,107.04 General Laborer 348 hrs 30.02 10,446.96 Project Executive Vehicle .5 month(s) 391.93 195.97 Project Manager Vehicle 1 month(s) 391.93 391.93 General Superintendent Vehicle .1 month(s) 391.93 39.19 Project Superintendent Vehicle 4 month(s) 391.93 1,567.72 Vehicle Fuel 4 month(s) 250.00 1,000.00 Project Executive Phone .5 month(s) 49.00 24.50 Project Manager Phone 1 month(s) 49.00 49.00 Project Superintendent Phone 4 month(s) 49.00 196.00 Postage 4 month(s) 100.00 400.00 Document Reproduction 1 allowance 750.00 750.00 Project Superintendent Overtime 120 hrs 78.28 9,393.60 CSI Division 0 - General Conditions Total 93,334.59 CSI Division 1 - General Requirements Subcontractor Bonds 1 allowance 4,500.00 4,500.00 Builders Risk Insurance 1 allowance 7,500.00 7,500.00 Photographic Documentation 1 allowance 250.00 250.00 Progress Schedule 1 allowance 750.00 750.00 Submittals 1 allowance 750.00 750.00 Personnel Protective Equipment 1 allowance 150.00 150.00 Background/Security Clearance 1 allowance 800.00 800.00 Testing & Inspection Services 1 allowance 1,500.00 1,500.00 Water, Cups and Ice 13 week(s) 50.00 650.00 Field Office - Computer/Printer 1 ls 250.00 250.00 Field Office - Data/Internet 4 month(s) 50.00 200.00 Portable Toilet 4 month(s) 125.00 500.00 Temporary Dust Barriers 1 allowance 750.00 750.00 Temporary Fencing & barricades 1 allowance 6,500.00 6,500.00 Temporary Project Signage 1 each 500.00 500.00 Utility Locates 1 allowance 1,600.00 1,600.00 Furniture Moving Kitchen equipment move out to conex boxes and back into kitchen 1 allowance 6,400.00 6,400.00 Dumpster 10 allowance 400.00 4,000.00 Final Cleaning 1 allowance 3,500.00 3,500.00 As-Built Documents/Drawings 1 allowance 500.00 500.00 Operation/Maintenance Data 1 allowance 500.00 500.00 Conex box rental for kitchen equipment storage 1 allowance 2,800.00 2,800.00 Get firm Quote from Mobile Mini including insurance, delivery & return for 3 each 40’ conex boxes CSI Division 1 - General Requirements Total 44,850.00 Demolition Subcontractor 1 ls 63,950.00 Demolition of interior ceilings, flooring and interior walls, door systems, slab cutting and removal per plumbing plan, etc. 63,950.00 Demolition Subcontractor 1 allowance 1,500.00 Support for mechanical contractor - cutting openings, etc. 1,500.00 ▇▇▇▇-▇▇-▇▇▇▇▇ Concrete Subcontractor 1 allowance 7,200.00 Pour back demolished concrete at new U.G. Pumbing and electrical (600 sf) 7,200.00 Cast-in-Place Concrete Subcontractor 1 allowance 650.00 Concrete pad for compressor for walk-in-cooler 650.00 Miscellaneous Metals Subcontractor 1 allowance 5,500.00 Tube steel columns and framing for security grills 5,500.00 Miscellaneous Metals Subcontractor 180 allowance 43.00 Handrail at serving lines 7,740.00 Rough Carpentry 1 allowance 1,200.00 Backing in partition walls 1,200.00 Membrane Roofing Subcontractor 1 allowance 2,500.00 For roof penetration 2,500.00 Coiling security grills Includes installation 1 ls 23,285.00 23,285.00 Window Subcontractor Operable windows and fixed glass 1 allowance 16,000.00 16,000.00 Doors, Frames and Hardware Subcontractor Double doors 3 each 4,200.00 12,600.00 Doors, Frames and Hardware Subcontractor Single 3.0x7.0 doors 9 each 2,000.00 18,000.00 Plaster and Gypsum Board Subcontractor 1 ls 145,080.00 Interior drywall/metal stud partition walls, includes patch & repair cafeteria perimeter walls ready for paint/includes stucco 145,080.00 Ceilings Subcontractor 1 ls 41,982.00 41,982.00 Acoustical ceilings Painting and Coatings Subcontractor 1 ls 21,500.00 21,500.00 Paint celing/soffit, dining room, wash room, staff lounge, dry storage, electric room and new exterior partition wall Tile Subcontractor (In Acousti Proposal) 1 ls 272,000.00 Porcelain floor tile & base in Dining areas (8500 sf) (550 lf) - Quarry floor tile kitchen floors/CWT wall tile 272,000.00 Stucco Subcontractor (In Acousti Proposal) New exterior stucco wall finish 610 sf 0.00 0.00 Tile Subcontractor (In Acousti Proposal) Kitchen wall tile 0 0 0.00 0.00 General Works Contractor Preparation of walk-in area for walk-in cooler 1 allowance 1,500.00 1,500.00 Floor Coatings (In Acousti Proposal) Epoxy paint - electrical room floor 60 sf 0.00 0.00 Tile Subcontractor (In Acousti Proposal) Quarry tile & base - Serving Line & Kitchen 0 0 0.00 0.00 Corner guards (In Acousti Proposal) 0 0 0.00 0.00 Toilet, Bath, and Laundry Accessories 1 allowance 1,800.00 1,800.00 Fire Extinguishers and cabinets 5 recessed cabinets and 3 wall mounts 1 allowance 1,600.00 1,600.00 CSI Division 10 - Specialties Total 3,400.00 Food Service Equipment 1 ls 8,636.00 8,636.00 Walk in cooler installation, does not include electrical, concrete pad for compressor and prep of walk in area CSI Division 11 - Equipment Total 8,636.00 Countertops 1 allowance 10,000.00 10,000.00 Plumbing Subcontractor 1 ls 37,600.00 37,600.00 Plumbing Subcontractor 1 allowance 2,500.00 Remove existing water lines serving kitchen and serving lines 2,500.00 HVAC Subcontractor 1 ls 166,812.00 Includes T&B of existing AHU’s and kitchen hood 166,812.00 Electrical Subcontractor 1 ls 229,100.00 Includes demolition and safe off/Includes new led lighting per plan 229,100.00 Communications Subcontractor 1 allowance 2,500.00 Data drops/outlets 2,500.00 Conex box rental for kitchen equipment storage -1 allowance 2,800.00 Deduct - Move equipment to dining room instead of conex boxes -2,800.00 Move kitchen equipment to dining area and return -1 ls 3,040.00 -3,040.00 Deduct o move to dining room instead of Connex Boxes (leaves $3,360 to move to dining room and back) Demolition Subcontractor -1 allowance 1,500.00 Deduct demolition necessary to support mechanical contractor in dining room soffits -1,500.00 Acoustical Treatment Subcontractor Deduct acoustical ceilings in dining areas only -1 ls 19,348.00 -19,348.00 Painting and Coatings Subcontractor Add painting of existing ceilings in dining area 1 ls 12,348.00 12,348.00 Flooring Subcontractor Deduct tile floor in dining area -1 ls 66,848.00 -66,848.00 Flooring Subcontractor Strip and polish terrazzo floors in dining areas 1 allowance 2,500.00 2,500.00 CSI Division 9 - Finishes Total -71,348.00 HVAC Subcontractor Deduct HVAC Mods in dining areas -1 ls 21,500.00 -21,500.00 Conex box rental for kitchen equipment storage 1 allowance 2,800.00 2,800.00 Move kitchen equipment to dining area and return 1 ls 3,040.00 3,040.00 Demolition Subcontractor 1 allowance 1,500.00 Demolition necessary to support mechanical contractor in dining room soffits 1,500.00 Acoustical Treatment Subcontractor 1 ls 19,348.00 New acoustical ceilings in dining areas only 19,348.00 Painting and Coatings Subcontractor -1 ls 12,348.00 Delete added painting of existing ceilings in dining area -12,348.00 Fire Suppression Subcontractor 1 allowance 45,500.00 13,000 square feet at $3.50 per sf 45,500.00 Fire Suppression Subcontractor 1 allowance 2,000.00 Fire riser 2,000.00 HVAC Subcontractor 1 ls 21,500.00 HVAC Mods in dining areas 21,500.00 CSI Division 33 - Utilities Directional Boring Subcontractor 1 allowance 10,000.00 10,000.00 Backflow preventer Directional Boring Subcontractor 900 feet @ $40.00 per square foot 1 allowance 36,000.00 36,000.00 Directional Boring Subcontractor Directional bore turns 2 allowance 2,000.00 4,000.00 Directional Boring Subcontractor Wet tap 6x4 1 allowance 5,000.00 5,000.00 Office Build Out 14-105 1 allowance 15,000.00 Allowance to build offices in room 14-105 15,000.00 March 25, 2019 School Board of Brevard County 2700 Judge ▇▇▇▇ ▇▇▇▇▇▇▇▇ ▇▇▇ ▇▇▇▇▇, FL 32940-6699 Attn.: ▇▇▇▇ ▇▇▇▇▇▇, Project Manager Phone ▇▇▇-▇▇▇-▇▇▇▇ Subject: Eau Gallie HS Kitchen Renovation, GMP, Revision Number 3 Please find attached the subject matter. This Guaranteed Maximum Price for Eau Gallie HS Kitchen Renovation is being submitted for your review and approval. HCI Project Team members are as follows: ▇▇▇▇▇▇▇ ▇▇▇▇▇▇ ▇▇▇▇▇ ▇▇▇▇▇▇▇ Project Manager Project Superintendent Should you have any questions regarding this proposal, please direct them to ▇. ▇▇▇▇. We look forward to working with you in successful completion of this project. Sincerely, ▇▇▇▇▇ ▇▇▇▇ Heard Construction, Inc. Description Section GMP Summary (1 Page) 1 List of Documents (6 Pages) 2 Description of Work 3 Specification Listing (NA - Specs on drawings) Qualifications and Assumptions (1 Page) Exclusions (1 Page) Add Alternate Schedule (1 Page) ODP Schedule (1 Page) GMP Cost Summary (5 Pages) 4 Milestone Dates (1 Page) 5 Sketch 1 Flooring Plan is attached (1 Page) A brief general summary of the scope of work, alternates, etc., is as follows: Provide Construction Management Services to complete the Cafeteria and Kitchen Renovation project in accordance with the terms and conditions as stipulated in the Continuing Contract for Construction Management Services between Heard Construction Inc. and the School Board of Brevard County and Tsark Architecture/DDC Engineering, Inc. drawings and specifications dated 2/1/2019 & 2/8/2019 respectively, outlining the following scope of work:
1. Demo and remove existing walls, ceilings & flooring per plan.
2. Removal and replacement of concrete slab to accommodate plumbing & electrical installations.
3. Installation of new partition and exterior walls per plan.
4. Installation of new doors, frames and hardware.
5. Installation of new floor and wall finishes (see qualifications and assumptions for floor tile changes).
6. Installation of new acoustical & drywall ceilings per plan (see qualifications and assumptions for acoustical ceiling changes).
7. Patching and painting.
8. Installation of specified accessories and corner guards.
9. Completion of new serving line handrails and overhead roll-up security gates.
10. Installation of new door signage.
11. Installation of new plumbing per plan.
12. Installation of new HVAC per plan (see qualifications and assumptions for HVAC changes).
13. Installation of new electrical and Fire Alarm per plan (see qualifications and assumptions for electrical changes).
14. Installation of new conduit for Data Drops at Serving lines. Also included is an allowance for a fire sprinkler system. This is a requirement of the Building Official and has yet to be design. Once the design is complete the system will be bid and firm costs will be determined at that time. Additionally included is an allowance for the office build out in room 14-105. Once the design is complete the firm costs will be determined at that time. Document No Document Description Document Date Revision No Revision Date G101 Title Page 02/01/19 G102 General Requirements, Schedule of Finishes 02/01/19 D101 First floor demolition plan 02/01/19 D301 Ceiling demolition plan 02/01/19 A101 First floor reference plan/Life Safety Plan 02/01/19 A102 First floor dimension plan 02/01/19 A201 Ground floor plan 02/01/19 A202 Finish floor plan 02/01/19 A203 Partition types 02/01/19 A301 Reflected ceiling plan and details 02/01/19 A501 Sections and details 02/01/19 A701 Interior elevations 02/01/19 A702 Interior elevations 02/01/19 A703 Enlarged kitchen and restroom 02/01/19 A901 Schedule of openings, opening types, frame types 02/01/19 A902 Door hardware 02/01/19 M1 Mechanical legend and abbreviations 02/08/19 M2 Mechanical demolition - mezzanine 02/08/19 M3 Mechanical plan - mezzanine 02/08/19 M4 Mechanical demolition plan 02/08/19 M5 Mechanical plan 02/08/19 M6 Mechanical details and schedules 02/08/19 M7 Mechanical controls - air side 02/08/19 P1 Plumbing details, legend & specs 02/08/19 P2 Plumbing plans 02/08/19 P3 Plumbing plan 02/08/19 P4 Plumbing demolition plan - water 02/08/19 P5 Plumbing plan - water 02/08/19 E1 Electrical legend and specifications 02/08/19 E2 Electrical demolition power plan 02/08/19 E3 Electrical demolition lighting plan 02/08/19 E4 Electrical power plan 02/08/19 E5 Elecrical lighting plan 02/08/19 E6 Electrical schedules 02/08/19 Eau Gallie HS Kitchen Renovation Page 1 Specification Listing (including exclusions, substitutions, modifications, etc.) is as follows:
Appears in 1 contract
Construction Manager's Representative. Construction Manager designates the individual listed below as its Construction Manager's Representative to provide direct interface with Owner with respect to Construction Manager's responsibilities: ▇▇▇▇ ▇▇▇▇ ▇▇▇▇▇▇▇, Construction Manager's, Project Manager. Exhibit C- Project Assignment Page 3 of 4 Exhibit C-1 – List of Contract Documents Page 1 of 2 Exhibit C-1 – List of Contract Documents Page 2 of 2 February 2421, 2022 2023 School Board of Brevard County 2725 Judge ▇▇▇▇ ▇▇▇▇▇ ▇▇▇▇ ▇▇▇▇▇▇▇▇ Way ▇▇▇ HCI Project 2204640800 2304640300 PO# BPS Satellite HS Food Service Remodel Discovery Canopy Refubishment Viera , FL 32940-6699 Attn: ▇▇▇▇▇ ▇▇▇▇▇ Subject: CM GMP Services Proposal for Satellite High School Food Service Remodel - Discovery ES Canopy Refurbishment Dear ▇▇▇▇▇, At your request we are providing our proposal for Construction Management Services for the subject project. All work will be subject to terms and conditions as stipulated in the Continuing Contract for Construction Management Services between Heard Construction Inc. and the School Board of Brevard County and RZK Architects/DDC TLC Engineering drawings Solutions Canopy Evaluation dated 5/23/2022 and specifications subsequent TLC Structural Drawings dated 1/18/22 including Addendum 1 dated 2/7/22 & Addendum 2 dated 2/11/22 12/7/2022 outlining the following scope Scope of workWork:
1. Demo Demolition and remove removal of existing walls, ceilings rusted purlins at the drop off canopy & flooring courtyard canopy per planPlan.
2. Removal & replacement of concrete slab to accommodate new plumbing, mechanical & electrical installationsStructural steel repairs as per TLC Canopy Repair Drawings.
3. Installation of new partition Prepare, corrosion control and exterior walls per planpaint entry pavilion, commons pavilion and barrel canopies.
4. Installation of new doors, frames Pressure wash entry and hardwarecommons pavilion at Spring Break and again prior to painting.
5. Installation of new storefront windows and doors, including ready access windowsRemove latex paint from barrel canopies.
6. Installation of new floor and wall finishesPaint commons & entry pavilion roof underside.
7. Installation of new acoustical & drywall ceilingsPaint barrel canopy soffit.
8. Patching Paint system: Spot prime, intermediate coat and paintingtwo topcoats.
9. Installation of specified accessories and corner guards.Apply Uniflex 44-300 to barrel canopy roofs (not including sides/soffit)
10. Installation of new Room signsRemove soffit and dome roofing to support duct insulation replacement.
11. Installation of new plumbing per planDemo & remove supply & return duct insulation on one (1) crossover canopy from mechanical room to adjacent classroom building. Provide 1” Armaflex insulation on supply duct from mechanical room to classroom building.
12. Installation of new HVAC per planPrep & repaint light fixtures at entry canopy and courtyard canopy.
13. Installation Demolition of new electrical and Fire Alarm. per planexisting Delaminating Stucco & Ceramic Tiles on Concrete Radius Columns in twelve (12) locations Only.
14. Installation of new conduit for Data Drops at Serving linesInstall repair grout where necessary to fill in voids following demolition.
15. Fire sprinkler system and associated piping modified Create 3/4" Slope at Top of Radius Columns to accommodate eliminate ponding for water intrusion.
16. Install Bonding Agent on demo'ed areas of columns Only.
17. All existing Concrete Column bases will be coated with integral layer of 4.3oz mesh fully encapsulated in cementitious base coat with hand trowel application.
18. Install New EIFS Finish Coat over all base coated Columns with Dryvit Sandpebble Fine finish coat texture with hand trowel application to match new Plan.. paint color. HCI’s GMP to provide Construction Management Services is $1,277,418.70. 600,074.53 We have enclosed our “SBBC GMP Estimate” detailing the costs for the this project. We have included supervision for the duration of the project. A $55,000.00 25,000.00 Project Contingency Allowance without fee markup is included. ▇▇▇▇▇▇▇ ▇▇▇▇▇▇ will be HCI’s Project Manager and ▇▇▇▇▇ ▇▇▇▇▇▇▇ will be HCI’s Project Manager and HCI’s full time on-site SuperintendentSuperintendent is To Be Determined (TBD). We There will provide estimated be no Owner Direct Purchases (ODP’s), including sales tax, within a few days of your acceptance of ) for this ProposalProject. This work will begin on receipt of your “Authorization to Proceed” and will be substantially completed during the upcoming summer recess. It is our intention to substantially complete the project by 7/31/221/4/2024. The Preliminary Project Schedule is as follows: Board approval: 3/22/22 3/7/2023 Notice To Proceed issued - 3/23/22 3/8/2023 Pressure Wash Spring Break - 3/13/2023 - 3/17/2023 Start construction Construction - 5/19/22 5/29/2023 Substantial Completion - 7/31/22 1/4/2024 Final Completion - 10/31/22 4/3/2024 We acknowledge that if Substantial Completion is not attained before 7/31/22 1/4/2024 Liquidated Damages in the amount of $1000.00 per day will be imposed. If HCI fails to attain Substantial Completion the Final Completion Date shall be reset to the ninetieth (90th) day after the date of actual Substantial Completion and Liquidated Damaged will be imposed at $500.00 per day. QUALIFICATIONS, CLARIFICATIONS AND EXCLUSIONS
1. Any Building Official requirements not specifically included in this proposal are excluded.
2. Only work described in the above scope of work is included in this project.
3. We have excluded HCI Commissioning costsAll costs associated with the removal of hazardous materials, if encountered, is excluded.
4. A&E Fees are excluded.
Appears in 1 contract
Sources: Guaranteed Maximum Price Agreement
Construction Manager's Representative. Construction Manager designates the individual listed below as its Construction Manager's Representative to provide direct interface with Owner with respect to Construction Manager's responsibilities: ▇▇▇▇▇▇▇ ▇▇▇▇▇▇, Construction Manager's, 's Project Manager. Exhibit C- Project Assignment Page 3 of 4 Exhibit C-1 – List of Contract Documents Page 1 of 2 Exhibit C-1 – List of Contract Documents Page 2 of 2 February 24May 27, 2022 2021 School Board of Brevard County 2725 Judge ▇▇▇▇ ▇▇▇▇▇ ▇▇▇▇ ▇▇▇▇▇▇▇▇ Way HCI Project 2204640800 2104641200 PO# BPS Satellite HS Food Service Remodel EGHS ▇▇▇ ▇▇▇▇▇▇ Room Restroom Improvements Viera , FL 32940-6699 Attn: ▇▇▇▇ ▇▇ ▇▇▇▇▇ Subject: CM GMP Proposal for Satellite High School Food Service Remodel EGHS ▇▇▇ ▇▇▇▇▇▇ Room Restroom Improvements Dear ▇▇▇▇▇, At your request we are providing our proposal for Construction Management Services for the subject project. All work will be subject to terms and conditions as stipulated in the Continuing Contract for Construction Management Services between Heard Construction Inc. and the School Board of Brevard County and RZK Architects/DDC Tsark Architecture /CEG Engineering drawings and specifications Drawings dated 1/18/22 including Addendum 1 dated 2/7/22 & Addendum 2 dated 2/11/22 5/7/2021 outlining the following scope of work:
1. Demo Demolition of existing toilet fixtures, accessories, partitions, floors,walls and remove existing walls, ceilings & flooring per planPlan.
2. Removal & replacement of concrete slab to accommodate Provide and install new plumbingtoilet fixtures, mechanical & electrical installationsaccessories and partitions per Plan.
3. Installation of Provide and install new partition floor and exterior walls wall tile per planPlan. Includes Add Alternate for additional floor tile.
4. Installation of new doors, frames Patch & paint ceilings and hardwarewalls above floor tile per Plan.
5. Installation of new storefront windows and doors, including ready Relocate ceiling access windowsdoor.
6. Installation of Provide new floor and wall finishespartition walls per Plan.
7. Installation Complete new Plumbing work per Plan and Specifications. Includes installation of new acoustical 16 Owner supplied Faucets, installation of 16 SS braided supply lines, replacement of 16 P traps & drywall ceilings16 grid drains, installation of 32 Owner Supplied cock hole cover plates, replacement of 16 angle stops and installation of 16 escutcheons.
8. Patching Provide Electrical demolition, power and painting.
9lighting per Plan and Specifications. Installation of specified accessories and corner guards.
10. Installation of new Room signs.
11. Installation of new plumbing per plan.
12. Installation of new HVAC per plan.
13. Installation of new electrical and Fire Alarm. per plan.
14. Installation of new conduit for Data Drops at Serving lines.
15. Fire sprinkler system and associated piping modified to accommodate new Plan.. HCI’s GMP to provide Construction Management Services is $1,277,418.70145,070.83. We have enclosed our “SBBC GMP Estimate” detailing the costs for the project. We have included supervision for the duration of the project. A $55,000.00 10,000.00 Project Contingency Allowance without fee markup is included. ▇▇▇▇▇▇▇ ▇▇▇▇▇▇ will be HCI’s Project Manager and HCI’s full time on-site Superintendent is ▇▇▇▇▇ ▇▇▇▇▇▇▇ will be HCI’s full time on-site Superintendent. We will provide estimated ▇.. There are no Owner Direct Purchases (ODP’s), including sales tax, within a few days of your acceptance of included in this ProposalProject. This work will begin on receipt of your “Authorization to Proceed” and will be substantially completed during the upcoming summer recess. It is our intention to substantially complete the project by 7/31/228/22/21. The Preliminary Project Schedule is as follows: Board approval: 3/22/22 6/22/2021 Notice To Proceed issued - 3/23/22 6/23/2021 Start construction Construction - 5/19/22 6/23/2021 Substantial Completion - 7/31/22 8/22/21 Final Completion - 10/31/22 11/21/2021 We acknowledge that if Substantial Completion is not attained before 7/31/22 8/22/2021 Liquidated Damages in the amount of $1000.00 per day will be imposed. If HCI fails to attain Substantial Completion the Final Completion Date shall be reset to the ninetieth (90th) day after the date of actual Substantial Completion and Liquidated Damaged will be imposed at $500.00 per day. QUALIFICATIONS, CLARIFICATIONS AND EXCLUSIONS
1. Any Building Official requirements not specifically included in this proposal are excluded.
2. Only work described in the above scope of work is included in this project.
3. We have excluded HCI Commissioning costsAll costs associated with the removal of hazardous materials, if encountered, is excluded.
4. A&E Fees are excluded.
Appears in 1 contract