Construction Completion Certificate. a. The construction and development work in this Concession Agreement shall not be considered to be completed until the Construction Completion Certificate has been signed by the Independent Engineer and delivered to the Authority and the Concessionaire, stating that the Concessionaire has completed its construction obligations under the Concession Agreement to the Independent Engineer's satisfaction. b. The Construction Completion Certificate shall be given by the Independent Engineer within 28 (twenty-eight) days after: (i) The Concessionaire has provided all the Construction Documents (including completion drawings) for the Works; (ii) The Concessionaire has remedied any defects in the Works; (iii) The Concessionaire has completed and tested all the Works, as specified by the Independent Engineer; (iv) The Works as an integrated structure is in conformity with the Technical Requirements; and (v) The Concessionaire has submitted “Structural Safety Certificate”. c. The Independent Engineer would be required to issue the Construction Completion Certificate after the construction of the project has been completed in all respect and is ready to use. However, the required documents as stated in Article 14.1 (b) shall be submitted by the Concessionaire and also, comply with all the obligations, wherein mentioned in the Concession Agreement, required to be met before and after the issuance of the Construction Completion Certificate.
Appears in 1 contract
Sources: Concession Agreement
Construction Completion Certificate. a. The construction and development work in this Concession Agreement shall not be considered to be completed until the Construction Completion Certificate has been signed by the Independent Engineer and delivered to the Authority and the Concessionaire, stating that the Concessionaire has completed its construction obligations under the Concession Agreement to the Independent Engineer's satisfaction.
b. The Construction Completion Certificate shall be given by the Independent Engineer within 28 (twenty-eight) days after:
(i) The Concessionaire has provided all the Construction Documents (including completion drawings) for the Works;
(ii) The Concessionaire has remedied any defects in the Works;
(iii) The Concessionaire has completed and tested all the Works, as specified by the Independent Engineer;
(iv) The Works as an integrated structure is in conformity with the Technical Requirements; and
(v) The Concessionaire has submitted “Structural Safety Certificate”.
c. The Independent Engineer would be required to issue the Construction Completion Certificate after the construction of the project Circuit House has been completed in all respect and is ready to use. However, the required documents as stated in Article 14.1 (b) shall be submitted by the Concessionaire and also, comply with all the obligations, wherein mentioned in the Concession Agreement, required to be met before and after the issuance of the Construction Completion Certificate.
Appears in 1 contract
Sources: Concession Agreement