Completion test obligation. 8.1.1 The contractor's general obligations
(1) Completion test scheme The counterparts and time of submission of completion test scheme: 7 counterparts, 10 days before project start. One electric copy (shall be modifiable format including but not limited to CAD, WORD and EXCEL) for each of the above documents submission shall be provided
Completion test obligation. 8.1.1 The contractor's obligations
(1) Before start of the project completion test, the contractor shall accomplish the construction operation of relevant project; and before start of the completion test, shall accomplish examination, inspection, test and experiment that shall be conducted according to the contract provisions.
(2) Before start of the completion test, the contractor shall submit relevant quality inspection materials and its completion materials to the contract letting party according to the provisions of concealed project and midway inspection and acceptance parts as set forth in Article 7.6 hereof.
(3) According to the provisions on post-completion test as set forth in Article 10 hereof, the contractor shall guide the contract letting party to conduct post-completion test, the contractor shall accomplish the training for operators and maintenance persons according to the provisions as set forth in Article 5.4 and submit the operation and maintenance manual as set forth in Article 5.2.2 before post-completion test.
(4) Completion test scheme. Within 20 days before the completion test conditions are satisfied, the contractor shall submit the completion test scheme to the contract letting party. The contract letting party shall raise suggestions and opinions within 10 days, the contractor shall at its own expenses amend the completion test scheme according to the suggestions and comments raised by the contract letting party. After the completion test scheme is acknowledged by the contract letting party as appendix hereto, it shall be implemented by the contractor. The counterparts and time of submission of completion test scheme are stipulated in the special provisions. The scheme shall include:
1) The basis and principles based upon which the completion test scheme is formulated;
2) Establishment and responsibility division of the organizational framework;
3) Test procedures and test conditions of completion test for the project;
4) Test procedures and test conditions of single, individual and joint test for the project;
5) Types, performance standards, test, inspection & acceptance format of the equipment, materials and components subject to completion test;
6) The quality and quantity requirements on the water, electricity and power conditions etc.;
7) Safe procedures, safe measures and protection facilities;
8) Progress plan, measures and schemes, human resource as well as machine and tool plan and arrangement of completion test;