Completion of Minimum Work Obligations - Staatsolie Verification. 5.11.1 If Staatsolie does not dispute in writing, within thirty (30) Days of Contractor’s notice pursuant to Sub-article 5.10, that Contractor has fulfilled its Minimum Work Obligations with respect to such phase, Contractor shall be deemed to have completed its Minimum Work Obligations with respect to the relevant phase.
Appears in 3 contracts
Samples: www.sec.gov, Production Sharing Contract (Kosmos Energy Ltd.), Kosmos Energy Ltd.
Completion of Minimum Work Obligations - Staatsolie Verification. 5.11.1 5.9.1 If Staatsolie does not dispute in writing, within thirty (30) Days of receipt of Contractor’s notice pursuant to Sub-article 5.10Article 5.8, that Contractor has fulfilled its Minimum Work Obligations with respect to such phase, Contractor shall be deemed to have completed its Minimum Work Obligations with respect to the relevant phase.
Appears in 1 contract
Samples: Sharing Contract