Compensation Event. (a) If Sections 15.2(a) and 15.2(b) require Project Co to perform any alteration, addition, demolition, extension or variation in the Work or to suspend or delay performance of the Work as a result of such discovery and which would not otherwise be required under this Project Agreement, then any such alteration, addition, demolition, extension or variation in the Work, or suspension or delay in the performance of the Work, shall, subject to and in accordance with Article 22, be treated as a Delay Event and, subject to and in accordance with Article 23, be treated as a Compensation Event, provided however that the foregoing shall not apply to the extent that any item referred to in Section 15.1(a) was disclosed in or properly inferable, readily apparent or readily discoverable from the Site Information or would have been properly inferable, readily apparent or readily discoverable from inspections of the Site carried out by Project Co or by any Project Co Party during the Request for Proposals process prior to the Submission Date.

Appears in 10 contracts

Samples: Project Agreement, Project Agreement, Project Agreement

AutoNDA by SimpleDocs

Compensation Event. (a) If Sections 15.2(a) and 15.2(b) require Project Co to perform any alteration, addition, demolition, extension or variation in the Work or to suspend or delay performance of the Work as a result of such discovery and which would not otherwise be required under this Project Agreement, then any such alteration, addition, demolition, extension or variation in the Work, or suspension or delay in the performance of the Work, shall, subject to and in accordance with Article 22, be treated as a Delay Event and, subject to and in accordance with Article 23, be treated as a Compensation Event, provided however that the foregoing shall not apply to the extent that any item referred to in Section 15.1(a) was disclosed in or properly inferable, readily apparent or readily discoverable from the Site Information or would have been properly inferable, readily apparent or readily discoverable from inspections of the Site carried out by Project Co or by any Project Co Party during the Request for Proposals process prior to the Submission Date.

Appears in 2 contracts

Samples: Project Agreement, Project Agreement

AutoNDA by SimpleDocs

Compensation Event. (a) If Sections 15.2(a) and 15.2(b) require Project Co to perform any alteration, addition, demolition, extension or variation in the Work or to suspend or delay performance of the Work as a result of such discovery and which would not otherwise be required under this Project Agreement, then any such alteration, addition, demolition, extension or variation in the Work, or suspension or delay in the performance of the Work, shall, subject to and in accordance with Article 22, be treated as a Delay Event and, subject to and in accordance with Article 23, be treated as a Compensation Event, provided however that the foregoing shall not apply to the extent that any item referred to in Section 15.1(a) was disclosed in or properly inferable, readily apparent or readily discoverable from the Site Information or would have been properly inferable, readily apparent or readily discoverable from inspections of the Site Sites carried out by Project Co or by any Project Co Party during the Request for Proposals process prior to the Submission Date.

Appears in 1 contract

Samples: Project Agreement