Commercial Operation Deadline Extension. If the Commercial Operation Date does not occur on or before the Commercial Operation Deadline as the result of a Force Majeure occurring before the Commercial Operation Deadline, then the Commercial Operation Deadline will, subject to Sections 1.04 and 5.05 and Seller’s compliance with its obligations as the Claiming Party under Section 5.02, be extended on a day-for-day basis for the duration of the Force Majeure. The contents of this document are subject to restrictions on disclosure as set forth herein.
Appears in 5 contracts
Samples: Renewable Power Purchase and Sale Agreement, Renewable Power Purchase and Sale Agreement, Renewable Power Purchase and Sale Agreement
Commercial Operation Deadline Extension. If the Commercial Operation Date does not occur on or before the Commercial Operation Deadline as the result of a Force Majeure occurring before the Commercial Operation Deadline, then the Commercial Operation Deadline will, subject to Sections 1.04 and 5.05 5.04 and Seller’s compliance with its obligations as the Claiming Party under Section 5.02, be extended on a day-for-day basis for the duration of the Force Majeure. The contents of this document are subject to restrictions on disclosure as set forth herein.
Appears in 4 contracts
Samples: Renewable Power Purchase and Sale Agreement, Renewable Power Purchase and Sale Agreement, Renewable Power Purchase and Sale Agreement
Commercial Operation Deadline Extension. If the Commercial Operation Date does not occur on or before the Commercial Operation Deadline as the result of a Force Majeure occurring before the Commercial Operation Deadline, then the Commercial Operation Deadline will, subject to Sections 1.04 and 5.05 5.04 and Seller’s compliance with its obligations as the Claiming Party under Section 5.02, be extended on a day-for-day basis for the duration of the Force Majeure. The contents of this document are subject to restrictions on disclosure as set forth herein.
Appears in 3 contracts
Samples: Renewable Power Purchase and Sale Agreement, Renewable Power Purchase and Sale Agreement, Renewable Power Purchase and Sale Agreement
Commercial Operation Deadline Extension. If the Commercial Operation Date does not occur on or before the Commercial Operation Deadline as the result of a Force Majeure occurring before the Commercial Operation Deadline, then the Commercial Operation Deadline will, subject to Sections 1.04 1.05 and 5.05 and Seller’s compliance with its obligations as the Claiming Party under Section 5.02, be extended on a day-for-day basis for the duration of the Force Majeure. The contents of this document are subject to restrictions on disclosure as Notwithstanding the foregoing, the Commercial Operation Deadline shall not be extended beyond the date set forth hereinin Section 1.04(b).
Appears in 2 contracts
Samples: Renewable Power Purchase and Sale Agreement, Renewable Power Purchase and Sale Agreement
Commercial Operation Deadline Extension. If the Commercial Operation Date does not occur on or before the Commercial Operation Deadline as the result of a Force Majeure occurring before the Commercial Operation Deadline, then the Commercial Operation Deadline will, subject to Sections 1.04 1.05 and 5.05 and Seller’s compliance with its obligations as the Claiming Party under Section 5.02, be extended on a day-day- for-day basis for the duration of the Force Majeure. The contents of this document are subject to restrictions on disclosure as set forth herein.
Appears in 2 contracts
Samples: Renewable Power Purchase and Sale Agreement, Renewable Power Purchase and Sale Agreement
Commercial Operation Deadline Extension. If the Commercial Operation Date does not occur on or before the Commercial Operation Deadline as the result of a Force Majeure occurring before the Commercial Operation Deadline, then the Commercial Operation Deadline will, subject to Sections 1.04 and 5.05 5.04 and Seller’s compliance with its obligations as the Claiming Party under Section 5.02, be extended on a day-for-day basis for the duration of the Force Majeure. The contents of this document are subject to restrictions on disclosure as set forth herein.
Appears in 2 contracts
Samples: Renewable Power Purchase and Sale Agreement, Renewable Power Purchase and Sale Agreement
Commercial Operation Deadline Extension. If the Commercial Operation Date does not occur on or before the Commercial Operation Deadline as the result of a Force Majeure occurring before the Commercial Operation Deadline, then the Commercial Operation Deadline will, subject to Sections 1.04 1.03 and 5.05 5.04 and Seller’s compliance with its obligations as the Claiming Party under Section 5.02, be extended on a day-for-day basis for the duration of the Force Majeure. The contents of this document are subject to restrictions on disclosure as set forth herein.
Appears in 2 contracts
Samples: Renewable Power Purchase Agreement, Renewable Power Purchase Agreement
Commercial Operation Deadline Extension. If the Commercial Operation Date does not occur on or before the Commercial Operation Deadline as the result of a Force Majeure occurring before the Commercial Operation Deadline, then the Commercial Operation Deadline will, subject to Sections 1.04 1.05 and 5.05 and Seller’s compliance with its obligations as the Claiming Party under Section 5.02, be extended on a day-for-day day‐ for‐day basis for the duration of the Force Majeure. The contents of this document are subject to restrictions on disclosure as set forth herein.
Appears in 1 contract
Commercial Operation Deadline Extension. If the Commercial Operation Date does not occur on or before the Commercial Operation Deadline as the result of a Force Majeure occurring before the Commercial Operation Deadline, then the Commercial Operation Deadline will, subject to Sections 1.04 Two.5 and 5.05 Seven.5 and Seller’s compliance with its obligations as the Claiming Party under Section 5.02Seven.2, be extended on a day-for-day basis for the duration of the Force Majeure. The contents of this document are subject to restrictions on disclosure as Notwithstanding the foregoing, the Commercial Operation Deadline shall not be extended beyond the date set forth hereinin Section Two.4(b).
Appears in 1 contract
Commercial Operation Deadline Extension. If the Commercial Operation Date does not occur on or before the Commercial Operation Deadline as the result of a Force Majeure occurring before the Commercial Operation Table of Contents Deadline, then the Commercial Operation Deadline will, subject to Sections 1.04 1.05 and 5.05 and Seller’s compliance with its obligations as the Claiming Party under Section 5.02, be extended on a day-for-day basis for the duration of the Force Majeure. The contents of this document are subject to restrictions on disclosure as Notwithstanding the foregoing, the Commercial Operation Deadline shall not be extended beyond the date set forth hereinin Section 1.04(b).
Appears in 1 contract
Samples: Renewable Power Purchase and Sale Agreement (Montauk Renewables, Inc.)
Commercial Operation Deadline Extension. If the Commercial Operation Date does not occur on or before the Commercial Operation Deadline as the result of a Force Majeure occurring before the Commercial Operation Deadline, then the Commercial Operation Deadline will, subject to Sections 1.04 and 5.05 5.04 and Seller’s 's compliance with its obligations as the Claiming Party under Section 5.02, be extended on a day-for-day basis for the duration of the Force Majeure. The contents of this document are subject to restrictions on disclosure as set forth herein.
Appears in 1 contract