Client Delay Sample Clauses

Client Delay. If we are unable to commence delivery of the Services on the Service Start Date (defined below) because of any failure on your part including but not limited the failure to provide access to your resources in a timely manner), you nonetheless will begin to incur Service Fees, which you shall pay in accordance with this Service Attachment and the Master Services Agreement, beginning on the Service Start Date. Pass-Through Expenses Client shall pay Provider’s reasonable out-of-pocket expenses, including travel expenses, lodging, meals, or other similar expenses, which may be incurred by Provider in performing Services. Any such “Pass-Through Expenses” will be billed at cost and invoiced monthly.
AutoNDA by SimpleDocs
Client Delay. If EMA's performance of its obligations under these Terms is prevented or delayed by any act or omission of Client or its agents, subcontractors, consultants or employees, EMA shall not be deemed in breach of its obligations under these Terms or otherwise liable for any costs, charges or losses sustained or incurred by Client, in each case, to the extent arising directly or indirectly from such prevention or delay.
Client Delay. Screenvision shall not be in breach hereunder or otherwise liable to Client due to delays caused by Client or Client’s failure to supply materials for the Advertisements in accordance with Screenvision’s production schedule.
Client Delay. Any delay, obstruction, or hindrance by Client which materially impacts SCT (TMD)'s ability to perform its obligations under this Agreement in a timely manner will excuse a delay in SCT (TMD)'s performance of its obligations under this Agreement, it being agreed by the parties that SCT (TMD) will use good faith efforts to minimize the period of any such excusable delay on the part of SCT (TMD).
Client Delay. If we are unable to commence delivery of the Services on the Service Start Date (defined below) because of any failure on your part including but not limited the failure to provide access to your resources in a timely manner), you nonetheless will begin to incur Service Fees, which you shall pay in accordance with this Service Attachment and the Master Services Agreement, beginning on the Service Start Date. Pass-Through Expenses Client shall pay Provider’s reasonable out-of-pocket expenses, including travel expenses, lodging, meals, or other similar expenses, which may be incurred by Provider in performing Services. Any such “Pass-Through Expenses” will be billed at cost, plus fifteen percent (15%), and invoiced monthly unless otherwise provided by specific written agreement between Client and Provider. Payment Terms We must receive payment of the full amount reflected on any invoice, as owed to us, no later than the due date specified on the invoice. Without waiving any of its other remedies, Provider reserves the right to suspend services if payment is not received within twenty (20) days following due date of that invoice. You shall pay a late charge of one- and one-half percent (1.5%) per month or the maximum lawful rate, whichever is less, for all invoiced amounts not paid within ten (10) days following due date of that invoice (the “Payment Deadline”). If you dispute in good faith all or any portion of the amount owed to us, or if you otherwise require any adjustment to an invoiced amount, you must notify us in writing, prior to the Payment Deadline, of the nature and basis of the dispute and/or adjustment. If we are unable to resolve the dispute prior to the Payment Deadline, you nevertheless shall pay the entire invoiced amount by the Payment Deadline. If we ultimately determine that such amount should not have been paid, we shall apply a credit equal to such amount against any Service Fees owed for the following month Method of Payment Payment is required to be made via ACH payable to Xxxxxx Data & Voice unless other arrangements are made between Provider and Client. Exceptions to this method of payment will be detailed in the Order for services. Please see the ACH Payment Authorization Form attached to the Order for services.
Client Delay. If the Client is obliged to do or provide anything under this Agreement and fails or delays in performing that obligation, Riskcom will not be liable for any delay or failure in performance of its obligations to the extent that such failure or delay is attributable to the Client, and the time for Riskcom to perform its obligations will be extended by the period of any relevant Client delay.

Related to Client Delay

  • Payment Delay Notwithstanding any other terms of this Agreement, no payments will be made to CONTRACTOR until COUNTY is satisfied that work of such value has been rendered pursuant to this Agreement. However, COUNTY will not unreasonably withhold payment and, if a dispute exists, the withheld payment shall be proportional only to the item in dispute.

  • Tenant Delay If substantial completion of the Tenant Improvements, Warm Shell Improvements or Base Building is delayed due to any of the following (collectively, "Tenant Delays"), then the Delivery Date and/or Commencement Date, as applicable, shall be adjusted to reflect what the substantial completion date would have been if there had been no delay: (i) Tenant's failure to timely submit any items required by this Work Letter, including, without limitation, Tenant's Plans; (ii) Tenant Modifications; (iii) Tenant's failure to comply with Landlord's contractor's schedule; (iv) Tenant's or Tenant's Contractor's failure to comply with Paragraph 8, (v) Tenant's requested changes to the Tenant's Plans after they are approved by Landlord; (vi) Tenant's request for materials, finishes or installations which require longer than thirty (30) days to complete; (vii) delays caused by Tenant in construction of the Warm Shell Improvements or the Tenant Improvements; or (viii) any other event expressly constituting "Tenant Delay" pursuant to any provision of this Work Letter. Landlord shall give Tenant at least five (5) days prior notice if Landlord becomes aware that Tenant is in danger of causing a Tenant Delay, and if Tenant takes appropriate measures to prevent such delay within such five (5) day period, no adjustment to the Delivery Date or Commencement Date shall be made on account of such Tenant Delay; provided, however, that if such delay was not reasonably foreseeable by Landlord, the five (5) day period for prior notice and opportunity to mitigate provided above shall be changed to forty-eight (48) hours after Landlord becomes aware of such delay or potential delay; and provided further, that no such notice shall be required if Tenant Delay results from Tenant's failure to perform any obligation within a specific date or time period (including, without limitation, any delay in delivery of Tenant's space plan or Working Drawings or non-compliance with Landlord's contractor's schedule), or from schedule changes resulting from Tenant Modifications of which Tenant is advised by Landlord's architect or contractor as provided in Paragraph 4, or from causes that, due to the parties' relative positions with respect to the construction process, are more likely to be foreseeable by Tenant than by Landlord.

  • Excusable Delay The Contractor is entitled to an equitable adjustment of time, issued via Change Order, for delays caused by the following:

  • Force Majeure Delays In any case where either party hereto is required to do any act (other than the payment of money), delays caused by or resulting from Acts of God or Nature, war, civil commotion, fire, flood or other casualty, labor difficulties, shortages of labor or materials or equipment, government regulations, delay by government or regulatory agencies with respect to approval or permit process, unusually severe weather, or other causes beyond such party’s reasonable control the time during which act shall be completed, shall be deemed to be extended by the period of such delay, whether such time be designated by a fixed date, a fixed time or “a reasonable time.”

  • Leadwork Differential (a) Leadwork differential shall be defined as a differential for employees who have been formally assigned by their supervisor in writing, “leadwork” duties for ten (10) consecutive calendar days (or the equivalent thereof for alternate or flexible schedules) or longer provided the leadwork or team leader duties are not included in the classification specification for the employee’s position. Leadwork is where, on a recurring daily basis, the employee has been directed to perform substantially all of the following functions: to orient new employees, if appropriate; assign and reassign tasks to accomplish prescribed work efficiently; give direction to workers concerning work procedures; transmit established standards of performance to workers; review work of employees for conformance to standards; and provide informal assessment of workers’ performance to the supervisor.

  • Termination Due to Force Majeure Event If the period of Force Majeure continues or is in the reasonable judgment of the Parties likely to continue beyond a period of 120 (one hundred and twenty) Days, the Parties may mutually decide to terminate this Agreement or continue this Agreement on mutually agreed revised terms. If the Parties are unable to reach an agreement in this regard, the Affected Party shall after the expiry of the said period of 120 (one hundred and twenty ) Days be entitled to terminate the Agreement in which event, the provisions of Articles 16 and 17 shall, to the extent expressly made applicable, apply.

  • Excusable Delays Except with respect to defaults of subproviders, the Engineer shall not be in default by reason of any failure in performance of this contract in accordance with its terms (including any failure to progress in the performance of the work) if such failure arises out of causes beyond the control and without the default or negligence of the Engineer. Such causes may include, but are not restricted to, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather.

  • Tenant Delays A "Tenant Delay” shall be defined as any delay in the design, permitting or performance of the Base Building Work to the extent that such delay is actually caused by any act or, where there is a duty to act under this Lease, any failure to act by Tenant or Tenant's contractors, architects, engineers, or anyone else engaged by or on behalf of Tenant in connection with the construction of the Tenant Improvement Work as set forth in this Article III (including, without limitation, any delays resulting from the Approved Tenant Finishes under Section 3.l(C) above) and disclosed to Tenant as hereinafter provided. Notwithstanding the foregoing, in no event shall any delays in the completion of the Base Building Work caused by Tenant’s use of non-union labor constitute a Tenant Delay hereunder. Notwithstanding the foregoing, no event shall be deemed a Tenant Delay unless and until Landlord has given Tenant written notice (the "Tenant Delay Notice") advising Tenant: (x) that a Tenant Delay is occurring and setting forth Landlord's good faith estimate as to the likely length of such Tenant Delay; (y) of the basis on which Landlord has determined that a Tenant Delay is occurring; and (z) the actions which Landlord believes that Tenant must take to eliminate such Tenant Delay. No event shall be deemed to be a Tenant Delay unless and until Tenant has failed to rectify the situation causing the Tenant Delay within forty-eight (48) hours after Tenant's receipt of the Tenant Delay Notice (which for the purposes of determining receipt may be delivered by hand to Tenant's Construction Representative, with copies to follow to Tenant at the notice address set forth in Section 1.2 of this Lease within five (5) days thereafter); provided, however, that if Tenant shall fail to eliminate the delay within the aforesaid 48-hour period, then the 48-hour cure period shall be included in the period of time charged to Tenant pursuant to such Tenant Delay Notice (it being understood and agreed that if Tenant shall in fact eliminate the Tenant Delay within the 48-hour cure period, no Tenant Delay shall be deemed to have occurred for the purposes of this Article III). In addition, any delay to the extent caused by (i) Landlord Delay or (ii) subject to the limitations of subsection (D) below, Tenant's Force Majeure (as defined in said subsection (D)) shall not constitute Tenant Delay. Tenant covenants that no Tenant Delay shall delay commencement of the Term or the obligation to pay Annual Fixed Rent or Additional Rent. The Delivery Dates and/or the date of substantial completion of the Base Building Work, as applicable, shall be deemed to have occurred as of the date when such Delivery Dates and/or date of substantial completion of the Base Building Work, as applicable, would have occurred but for any Tenant Delays, as determined by Landlord in the exercise of its good faith business judgment (it being understood and agreed that the foregoing shall not be construed so as to relieve Landlord of its obligation to actually complete the Base Building Work, notwithstanding the fact that substantial completion may have been deemed to have occurred prior to actual completion as the result of Tenant Delays).

  • Six-Month Delay Notwithstanding anything to the contrary in this Agreement, no compensation or benefits, including without limitation any severance payments or benefits payable under this Section 4, shall be paid to the Executive during the six-month period following the Executive’s Separation from Service if the Company determines that paying such amounts at the time or times indicated in this Agreement would be a prohibited distribution under Section 409A(a)(2)(B)(i) of the Code. If the payment of any such amounts is delayed as a result of the previous sentence, then on the first day of the seventh month following the date of Separation from Service (or such earlier date upon which such amount can be paid under Section 409A without resulting in a prohibited distribution, including as a result of the Executive’s death), the Company shall pay the Executive a lump-sum amount equal to the cumulative amount that would have otherwise been payable to the Executive during such period.

  • Unavoidable Delay When construction is impeded as a result of strikes, lockouts, acts of God or other factors beyond the control, and ability to remedy, of the Developer.