Common use of Claims Analysis Clause in Contracts

Claims Analysis. 7.15.1 The A/E, in consultation with the Contracting Authority, shall respond to the Contractor’s written notice of a Claim within a reasonable time of receipt, but not to exceed 10 days.

Appears in 9 contracts

Samples: www.utoledo.edu, www.utoledo.edu, www-s3-live.kent.edu

AutoNDA by SimpleDocs

Claims Analysis. 7.15.1 8.14.1 The A/E, in consultation with the Contracting Authority, shall respond to the Contractor’s written notice of a Claim within a reasonable time of receipt, but not to exceed 10 ten days.

Appears in 2 contracts

Samples: www-s3-live.kent.edu, www-s3-live.kent.edu

Claims Analysis. 7.15.1 8.15.1 The A/E, in consultation with the Contracting Authority, shall respond to the Contractor’s written notice of a Claim within a reasonable time of receipt, but not to exceed 10 days.

Appears in 1 contract

Samples: ofcc.ohio.gov

AutoNDA by SimpleDocs

Claims Analysis. 7.15.1 4.7.1 The A/E, in consultation with the Consultant and the Contracting Authority, shall respond to the Contractor’s written notice of a Claim within a reasonable time of receipt, but not to exceed 10 days.

Appears in 1 contract

Samples: www.franklincityschools.com